Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Sort descending Mode 2024 Funding 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Blue Line Forest Park Modernization - Phase 2 Rail $0 $0 $653,077,000 $653,077,000

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

+ CTA Blue Line Forest Park Modernization - Phase 3 Rail $0 $0 $598,030,000 $598,030,000

Track improvement and special work placement, interlocking relocation and station renovations

+ CTA Blue Line Forest Park Modernization - Phase 4 Rail $0 $0 $597,030,000 $597,030,000

Des Plaines Yard and Forest Park terminal reconstruction

+ CTA Bond Repayment, Interest Cost & Finance Cost System $205,480,599 $992,830,555 $1,841,370,472 $848,539,917

Support CTA Debt

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ CTA Bond Repayment - Principal/Interest Contingencies and Administration System $205,480,599 $992,830,555

Project Details

Description
Bond Repayment, Interest Cost, & Finance Cost: Provide for debt service and the cost of issuance of bonds, notes and other indebtedness incurred by the CTA.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $205,480,599 $787,349,956 $992,830,555
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $515,036,653 $205,480,599 $787,349,956 $1,507,867,208

Last Updated 12.16.2022

+ Metra Bridge Replacement and Repair Rail $143,795,000 $297,084,423 $2,081,462,250 $1,784,377,827

Replace and repair 61 bridges systemwide.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 275-Old 96th Ave. Bridge Track & Structure Rail $0 $0

Project Details

Description
This project funds the replacement of Bridge 275 on Metra’s Rock Island District. The 94-year-old bridge spans over 96th Avenue in Mokena at milepost 27.5.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,800,000 $0 $0 $2,800,000

Last Updated 12.16.2022

+ Bridge 86 - 78th St Entrance Track & Structure Rail $0 $33,160,000 ✔︎

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $33,160,000 $33,160,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $0 $33,160,000 $48,140,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the bridge and entrance continued to 90% completion. Design is expected to be complete by Q1-2024.

Last Updated 12.14.2023

+ Bridge A-32 Reconstruction Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,041,561
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities by completing drilled shafts, forming & pouring bridge piers and abutment walls. The project is 57% complete.

Last Updated 12.14.2023

+ Bridge A110/56 Track & Structure Rail $0 $0

Project Details

Description
This project funds the replacement of Bridges A110 and A56 on Metra’s Milwaukee District North (MD-N) Line. Both bridges were constructed in 1909 and span the North Branch Chicago River. Bridge A110 is located in Northbrook at milepost 21.3 and Bridge A56 is at milepost 10.85 in Chicago just south of the Edgebrook station. This is a multi-year, multi-phase project that will fund design engineering services and any environmental analyses as required by the National Environmental Policy Act (NEPA). Construction funds are provided in later years.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,095,000 $0 $0 $4,095,000

Last Updated 03.15.2023

+ Bridge A318 Track & Structure Rail $0 $7,600,000

Project Details

Description
This project funds design services and the construction of a replacement bridge that will increase the capacity of trains and service on the Milwaukee District North (MD-N) Line. The new Bridge A318 will add a second-track siding over the North Branch Chicago River in Rondout at milepost 32.4. A second-track siding will allow for additional train movements through the Fox Lake Subdivision, which runs northwest of Rondout and includes seven stations. This is a multi-year project that works in concert with the separate projects to improve the Rondout Interlocking, the Rondout CP Tri-State track, and the Lake Forest Crossovers.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $7,600,000 $7,600,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $0 $7,600,000 $9,600,000

Last Updated 12.14.2023

+ Bridge A418 Track & Structure Rail $0 $0

Project Details

Description
This project funds the engineering design of a bridge replacement that spans the Mud Creek in Long Lake at milepost 45.8. The project has construction funds in following year to replace the circa 1909 structure on the Fox Lake Subdivision, which runs north-west from Rondout to Fox Lake along the Milwaukee District North Line.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,200,000 $0 $0 $3,200,000

Last Updated 03.16.2023

+ Bridge Rehabilitation Program Track & Structure Rail $3,215,000 $6,525,000

Project Details

Description
This on-going project will fund the preliminary engineering phase and environmental analyses as required by the National Environmental Policy Act (NEPA) for up to five proposed bridge rehabilitation projects per year. Projects that advance to the final design and construction phases will be funded by new, location-specific project numbers as funding becomes available. Specific bridge rehabilitation project locations are to be determined based on reviewing annual bridge condition inspections, bridge sufficiency ratings, and other factors that will inform which bridges can be improved with a life-extending rehabilitation. The bridge rehabilitation program is a multi-year project. Final design and construction funds have not been identified for 2024 activities that will be funded by this project
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $3,215,000 $3,310,000 $6,525,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $3,215,000 $3,310,000 $6,525,000

Last Updated 12.14.2023

+ Bridge Replacement Program Track & Structure Rail $6,660,000 $13,520,000

Project Details

Description
This on-going project will fund the preliminary engineering phase and environmental analyses as required by the National Environmental Policy Act (NEPA) for up to five proposed bridge replacement projects per year. Projects that advance to the final design and construction phases will be funded by new, location-specific project numbers as funding becomes available. Specific bridge replacement project locations are to be determined based on priority needs, annual bridge condition inspections, bridge sufficiency ratings, and the potential for bundling multiple bridge replacement projects in one construction contract procurement. The bridge replacement program is a multi-year project. Final design and construction funds have not been identified for 2024 activities that will be funded by this project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $6,660,000 $6,860,000 $13,520,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $6,660,000 $6,860,000 $13,520,000

Last Updated 12.14.2023

+ Bridges & Retaining Walls BNS Track & Structure Rail $2,800,000 $10,842,500

Project Details

Description
This project will provide for the rehabilitation of retaining walls on the BNSF commuter line. Retaining wall sections at intermittent locations along the right-of-way will be rehabilitated. This work typically includes complete reconstruction with steel sheet piling, concrete panels or bin wall to prevent retaining wall deterioration that can result in destabilization of the roadbed and in turn lead to track shifting.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,800,000 $8,042,500 $10,842,500
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,250,000 $2,800,000 $8,042,500 $16,092,500

Last Updated 12.14.2023

+ Bridges & Retaining Walls MED Track & Structure Rail $1,750,000 $10,450,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,750,000 $8,700,000 $10,450,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,990,000 $1,750,000 $8,700,000 $12,440,000

Last Updated 12.14.2023

+ Bridges & Retaining Walls MWD Track & Structure Rail $500,000 $6,400,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the MWD to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $500,000 $5,900,000 $6,400,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,250,000 $500,000 $5,900,000 $7,650,000

Last Updated 12.14.2023

+ Bridges & Retaining Walls RID Track & Structure Rail $1,750,000 $9,850,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,750,000 $8,100,000 $9,850,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,750,000 $1,750,000 $8,100,000 $12,600,000

Last Updated 12.14.2023

+ Bridges & Retaining Walls UPR Track & Structure Rail $1,500,000 $10,900,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the UPR to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,500,000 $9,400,000 $10,900,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $200,000 $1,500,000 $9,400,000 $11,100,000

Last Updated 12.14.2023

+ CREATE EW-2 Bridge Lift Track & Structure Rail $3,040,000 $3,040,000 ✔︎

Project Details

Description
This project involves lifting a bridge between 78th Street and 79th Street on Metra’s Rock Island Line. The bridge spans over three sets of railroad tracks owned by The Belt Railway of Chicago and Norfolk Southern in Chicago at milepost 8.7. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,040,000 $0 $3,040,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $3,040,000 $0 $7,040,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$8,404,189
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the project has been completed. Metra advertised the construction procurement and received only one bid. The proposed cost exceeded the allocated construction budget for the project. Metra made a decision to re-design the project to reduce the risk off of the potential contractor and attract more bids. A change order has been issued to the designer and the re-design is 90% complete.

Last Updated 12.14.2023

+ Evanston Bridge Repainting Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project involves the sanding, abatement and repainting of the Dempster Street and Davis Streetbridges in Evanston on the Union Pacific North Line.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,300,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor finished painting and applying the protective coating on the bridge in December. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ Grand Avenue Bridge Track & Structure Rail $0 $0

Project Details

Description
This project funds engineering design services for the replacement of the Grand Avenue Bridge. Three main line tracks utilize the bridge including the Milwaukee District North and West Lines and the North Central Service. The bridge, constructed in 1898, spans over the intersection of Grand Avenue and Homan Avenue at milepost 4.5. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $16,000,000 $0 $0 $16,000,000

Last Updated 12.16.2022

+ Gresham Area Bridges Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution. Both bridges are named after the Chicago street over which they cross, carry two main line tracks, and will be replaced with resilient concrete bridges.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $17,000,000 $0 $0 $17,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$31,816,250
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Design work for the Vincennes Ave. Bridge #98 and Morgan St. Bridge #S-102 were completed. City land swap negotiations are ongoing. Metra is proceeding without the property swap and is investigating the original elevation ordinance for the legal right to construct on City property. The 100% drawings were completed, and vendor selected. The contractor was given the Notice to Proceed in August and kick-off meeting was held at the beginning of October. The contractor is working on submittals and long lead time items.

Last Updated 12.14.2023

+ Hickory Creek Bridge Track & Structure Rail $2,750,000 $2,750,000

Project Details

Description
This project funds repair activities to rehabilitate the existing piers and abutments. The existing bridge spans the Hickory Creek.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $2,750,000 $0 $2,750,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $2,750,000 $0 $2,750,000

Last Updated 12.14.2023

+ Replace Bridges - 18th to 55th - RID Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Phase 1 and 2 design and construction are complete. The Phase 3 design task wasissued an NTP in August 2018. The Phase 3 design was completed in July 2019. ThePhase 3 construction contract and construction management contract were bothawarded in September 2020. Construction started with site work in March 2021and is ongoing. Current activities are related to obtaining permits. The estimatedproject completion date for construction is December 2021 to allow enough timefor phase 3 construction.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$120,282,161
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Phase 1 and 2 design and construction are complete. The Phase 3 design task was issued an NTP in August 2018. The Phase 3 design was completed in July 2019. The Phase 3 construction contract and construction management contract were both awarded in September 2020. Construction started with site work in March 2021 and is ongoing. Current activities are related to obtaining permits. The project reached substantial completion in December 2021. This will be the final update on this project.

Last Updated 12.14.2023

+ Stoney Creek Bridge- SWS Track & Structure Rail $2,830,000 $2,830,000 ✔︎

Project Details

Description
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $2,830,000 $0 $2,830,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $2,830,000 $0 $2,830,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$8,500,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. There are some delays related to the National Environmental Policy Act (NEPA) process and the Illinois State Historic Preservation Office (SHPO) review. The 30% design has been completed. Once the NEPA and SPHO process is complete, work will continue on the design to advance to 60%.

Last Updated 12.14.2023

+ UP North Line - North 11 Bridges and Ravenswood Station Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, theproject will include various signal improvements, including: new interlockers at Addison Street (MP 5.0) and Rosehill (MP 7.3, between Balmoral Avenue and Bryn Mawr Avenue), and upgrades to the Deering interlocker (MP 3.2). In
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$50,255,463
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The bridge construction has been completed in September 2021. The station contractor reached substantial completion in August 2023. The contractor continues to address punch list items on the station. The station had a soft opening at the beginning of August and its opening ceremony at the beginning of October. This will be the final update of this project.

Last Updated 12.14.2023

+ UP North Line - South 11 Bridges Track & Structure Rail $117,000,000 $179,216,923 ✔︎

Project Details

Description
This project will provide for the reconstruction of bridges and retaining walls on the Union Pacific North Line, and Ravenswood Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $117,000,000 $56,400,000 $173,400,000
State $0 $0 $5,816,923 $5,816,923
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $117,000,000 $62,216,923 $179,216,923

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$162,100,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The National Environmental Policy Act (NEPA) review process is ongoing. Design activities are at the 60% design mark. Benesch is continuing to review and respond to comments from Metra and UPRR as they come in. Once all comments are addressed, the design will continue to 90% design.

Last Updated 12.14.2023

+ Z14C- Keystone Ave. Bridge Track & Structure Rail $0 $0

Project Details

Description
This project funds engineering design services for the replacement of the Z 14 C in Chicago. The bridge, constructed in 1903, spans over the intersection of Keystone Avenue Bridge at milepost 5.69. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,600,000 $0 $0 $11,600,000

Last Updated 12.16.2022

+ CTA Brown Line Improvements Rail $0 $0 $436,384,000 $436,384,000

Upgrades and State of Good Repair projects along the Brown Line

+ CTA BRT/Bus Slow Zone Removal/ TSP/Dedicated Lane projects Bus $0 $0 $231,240,000 $231,240,000

Targeted street and traffic signal improvements to increase bus speeds

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Bus Priority Corridor Study Electrical, Signal & Communications Bus $0 $0

Project Details

Description
The Chicago Transit Authority (CTA) is pursuing the Bus Priority Corridor Study to advance planning for key bus corridors in the City of Chicago to identify concepts to dramatically improve bus service. The project will advance equity and mobility justice by enabling higher quality transit services to communities that have the greatest needs, mitigate congestion, improve air quality, and promote economic development and access to opportunity.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $575,000 $0 $0 $575,000

Last Updated 12.14.2023

+ Bus Slow Zones Elimination Program Electrical, Signal & Communications Bus $0 $0

Project Details

Description
This is a joint partnership with CDOT where CTA and CDOT will implement a coordinated program of bus priority treatments and targeted solutions for specific problem areas, in order to improve speed and reliability on major bus corridors. Project funds will cover final design and construction for all six routes.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $15,200,000 $0 $0 $15,200,000

Last Updated 12.16.2022

+ CTA Bus Garage Improvements Bus $0 $0 $248,090,000 $248,090,000

Provide repairs at bus maintenance garages and shops

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Bus Hoist Replacement Program Support Facilities & Equipment Bus $0 $0

Project Details

Description
Project will support an updated assessment of the bus hoists to determine which may need replacement, as well as design and construction for those locations.This funding will provide for the purchase and installation of bus hoists at five CTA bus garages.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $15,000,000 $0 $0 $15,000,000

Last Updated 03.15.2023

+ Improve Facilities - Electric Bus Program Planning Support Facilities & Equipment Bus $0 $0

Project Details

Description
CTA has committed to a full electrification of the bus fleet by 2040, providing significant air quality improvements to the region and the immediate vicinity of the garage facilities. To implement the program, the garages will need to be converted to allow for routing servicing / charging of the buses as well as new maintenance requirements. The work will generally involve significant electrical upgrades, installation of charger infrastructure, and general updates to the facility to support the conversion to an electric fleet.The primary locations for the electric charger upgrades will be within all of the CTA bus garages. Secondary locations will be on route charging at major terminals to support the longer bus routes. A study is ongoing to recommend network options and charging requirements. Additionally, load flow studies will be required at all of the garages to properly determine the specific charging needs.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $44,599,730 $0 $0 $44,599,730

Last Updated 12.16.2022

+ North Park Garage – Building Demolition Support Facilities & Equipment Bus $0 $0

Project Details

Description
Project will cover the building demolition and site restoration of 5323 N. Kedzie.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $177,485 $0 $0 $177,485

Last Updated 12.16.2022

+ Pace Bus on Shoulder (BoS) Infrastructure Bus $0 $0 $17,025,000 $17,025,000

Passenger facilities for Bus on Shoulder service

+ Pace Charging Infrastructure Bus $0 $0 $36,000,000 $36,000,000

Charging infrastructure at garages to charge electric buses, including power supply lines, charging station equipment, and backup generators .

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Charging Infrastructure Support Facilities & Equipment Bus $0 $0

Project Details

Description
Maintenance of existing building structures, systems, asphalt/concrete, etc. Charging infrastructure at North, North Shore, and Southwest Divisions.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,500,000 $0 $0 $5,500,000

Last Updated 12.16.2022

+ North Division Garage Improvements Support Facilities & Equipment Bus $0 $0

Project Details

Description
These funds will be used to prepare the North Garage for Electirc buses.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,181,017 $0 $0 $10,181,017

Last Updated 12.16.2022