Capital Projects

Capital Projects

Download Capital / PMO Dataset

 

This page allows users to search all the projects in the 2020-2024 capital program and their programmed budget for the current year and out years. Users can search for projects by name or keyword from the Search bar of the Filter pulldown menus.  Select one filter per search.

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

 

Search

Filter

Year Agency Project Title Asset Category Mode 2020 Funding 2020-2024 Funding Funding Source(s) Status PMO
+ 2020 to 2024 CTA NML - Red/Purple Modernization (FTA Core Capacity) - Support Service Modernization Rail $612,500 $2,851,041
  • Federal: Core Capacity
  • State/Local: Tollway
Programmed

PROJECT DETAILS

Project #

304.004

Tip ID

16-10-9001

Description

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: Core Capacity
$612,500
State/Local: Tollway
$0

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

Foundation work continues in the RPB Project Area for the bypass track. Pre-Stage work for Thorndale and Montrose Interlockings is in progress. Substantially completed the Advance Utility Relocation work in LBMM. Some service relocation work and pole removal work are still in progress.

Last Updated 10.22.2020
+ 2020 to 2024 CTA NML - Red/Purple Modernization - Support Service CMAQ Modernization Rail $153,125 $153,125
  • Federal: none
  • State/Local: CMAQ
Programmed

PROJECT DETAILS

Project #

304.004

Tip ID

16-10-9001

Description

Not Available

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: none
$0
State/Local: CMAQ
$153,125

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

Foundation work continues in the RPB Project Area for the bypass track. Pre-Stage work for Thorndale and Montrose Interlockings is in progress. Substantially completed the Advance Utility Relocation work in LBMM. Some service relocation work and pole removal work are still in progress.

Last Updated 10.22.2020
+ 2020 to 2024 CTA NML - Red/Purple Modernization -Support Service CTA Bond RPM Modernization Rail $1,104,070 $1,391,901
  • Federal: none
  • State/Local: CTA RPM Bonds
Programmed

PROJECT DETAILS

Project #

304.004

Tip ID

16-10-9001

Description

Not Available

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: none
$0
State/Local: CTA RPM Bonds
$1,104,070

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

Foundation work continues in the RPB Project Area for the bypass track. Pre-Stage work for Thorndale and Montrose Interlockings is in progress. Substantially completed the Advance Utility Relocation work in LBMM. Some service relocation work and pole removal work are still in progress.

Last Updated 10.22.2020
+ 2020 to 2024 CTA Purchase Rail Cars - 7000' Series (Base Order 400) Rolling Stock Rail $62,353,288 $66,522,896
  • Federal: none
  • State/Local: CTA Bond
Programmed

PROJECT DETAILS

Project #

132.056

Tip ID

16-15-0005

Description

Not Available

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: none
$0
State/Local: CTA Bond
$62,353,288

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

The Chicago plant has been closed from 3/27 to 5/31. This will delay the delivery of prototype cars. The CRC plant in China is also still closed due to COVID19. The assembly of body shells in China are planned for restarting in July/August. An updated schedule will be provided on the next report. Progress is being made on the development and review of testing plans and Safety Certification documents.

Last Updated 10.22.2020
+ 2020 to 2024 CTA Purchase up to 70 Electric Buses and up to nine chargers Rolling Stock Bus $0 $38,603,470
  • Federal: CMAQ
  • State/Local: Tollway
Programmed

PROJECT DETAILS

Project #

031.054

Tip ID

N/A

Description

Not Available

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: CMAQ
$0
State/Local: Tollway
$0

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

Five of the pilot buses were accepted in November 2019. The sixth bus, which originally failed due to climatic testing, was finally delivered in January 2020 with testing and monitoring ongoing. The 100% design documents were completed, reviewed, and submitted for permits. ComEd coordination is ongoing with field testing results have been approved. Delivery of the charging station equipment is ongoing. Installation of the charging stations to begin.

Last Updated 10.22.2020
+ 2020 to 2024 CTA Rehabilitate Blue Line - Grand, Chicago and Division Station Renovation (Phase 4) (YNB) Modernization Rail $3,978,519 $3,978,519
  • Federal: none
  • State/Local: Rebuild Illinois
Programmed

PROJECT DETAILS

Project #

195.027

Tip ID

16-14-0007

Description

The scope this project provides for rehabilitation work on Blue Line - O'Hare Branch stations. These station investments are critical part of the Your New Blue program, and include upgrades to the stations along the O'Hare Branch of the Blue Line between O'Hare Airport and Downtown Chicago Loop. Planned work includes bringing structural and mechanical elements into a state of good repair, and strategically upgrading passenger amenities to improve the riding experience deliver visible neighborhood improvements. Grand, Chicago and Division Stations work will provide safe and dry improvements as appropriate for these stations, and that includes entry stairs from street improvements: installation of granite stair treads and risers, glazed wall tiles, ceiling repainting's, and stair lighting replacement. Other improvements are within the mezzanine which includes epoxy finish on concrete floor, new ceiling plaster, high efficiency lighting and stainless steel rota-gates.

Platform improvements may include escalator replacements, granite pavers, stainless steel over concrete block walls, replacement of panel doors with stainless steel, new light fixtures in new stainless steel shroud above center platform and general replacement of furniture.

Street Level:
• Installation of new entry canopies at each stair opening.
• Repairs to the stairs.
• Installation of new glazed tile walls at stairway.
• Replacement of lighting.

Mezzanine Level:
• Refinishing offloors.
• Repairs to the existing glazed tile walls.
• Replacement of lighting.
• Replacement of exit rota-gates and security fencing.
• Replacement of Customer Assistant's booth.

Platform Level:
• Refinish of floors.
• Repairs to the existing glazed tile walls.
• Re-lamping of lighting.
• Refurbishment of escalators.
• Repairs to the stairs.

Other Resources

Funding Amounts by Source for Current Year

Source Amount
Federal: none
$0
State/Local: Rebuild Illinois
$3,978,519

PMO UPDATES

Budget Status

On Budget

Schedule Status

On Schedule

Current Activities

This project is in the closeout phase with punch list items being addressed. The contractor has applied for and was granted substantial completion in May 2020.

Last Updated 10.22.2020