PROJECT DETAILS
Description:
This project will provide engineering for the 75th Street Corridor Improvement Project (CIP) that will relieve rail congestion by separating freight and passenger rail lines. Bottlenecks will be eliminated, and train idling will be reduced.
Core Requirement(s) | |
---|---|
Maintain and Improve Safety and Reliability | ✓ |
Achieve Full Accessibility | |
Meet Regulatory Requirements | |
Improve Equity | ✓ |
Strategic Goal | |
---|---|
Deliver Value on Investment | |
Build on the Strengths of Our Network | |
Stay Competitive | ✓ |
Funding Amounts by Source:
Source | Previous Funding* | 2022 Funding | 2023-2026 Funding | Total |
---|---|---|---|---|
Federal |
$0 |
$0 |
$0 |
$0 |
State |
$0 |
$0 |
$0 |
$0 |
RTA |
$0 |
$0 |
$0 |
$0 |
Service Board / Local |
$0 |
$0 |
$0 |
$0 |
Total |
$6,500,000 |
$0 |
$0 |
$6,500,000 |
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
Aug 2020End Date
Sep 2023^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
This project is currently in design. The 60% design has been completed and is under review by Metra. Metra developed a solicitation package for Right‐of‐Way (ROW) acquisition services and the procurement process is ongoing.
Last Updated 06.16.2022