Capital Projects

Regional Capital Program

Download Capital Dataset

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measure which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Project Mode 2023 Fundingsort descending 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Tactical Traction Power Improvements (Systemwide) Rail $0 $0 $155,739,098 $155,739,098

Description:

Traction power substation, third rail replacement and SCADA upgrades

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Systemwide Tactical Traction Power Upgrades (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

Tactical Traction Power (Equipment/Cable/Enclosures) -The purpose of this project is to implement traction power system improvements that will enable the CTA to continue to meet existing traction power needs, increase traction power capacity to meet future demand, and address state of good repair by repairing or replacing worn or obsolete equipment.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$10,864,902
$0
$0
$10,864,902

PMO:

Total Project Budget^

$15,166,629

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Jul 2021

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contractor made significant headway during this reporting period and was able to reach substantial completion in July of this year. The contractor was able to finish the final walkthrough inspection and completed all punchlist items and is in contract closeout. This will be the final update on this project.

Last Updated 01.10.2022

+ Pace Fixed Route Buses - Replacement Bus $0 $9,750,000 $79,300,000 $69,550,000

Description:

Replacement of buses reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase 40' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$41,786,531

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2019

End Date

Nov 2020

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.

Last Updated 07.10.2021

+ Fixed Route CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement CNG buses - Pace plans to replace 115 diesel buses with 40' Compressed Natural Gas (CNG) buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the future Northwest Division garage in Wheeling, currently being designed as a CNG fueling facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$28,050,000
$0
$0
$28,050,000

Last Updated 12.16.2022

+ Fixed Route Coach Buses Rolling Stock Bus $0 $9,750,000

PROJECT DETAILS

Description:

Coach Buses - Pace plans to replace 13 40' diesel coach buses, including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the I-55 Bus on Shoulder service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$9,750,000
$9,750,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$9,750,000
$9,750,000

Last Updated 12.16.2022

+ Purchase 30' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

This project is a new contract awarded in September 2019 for a new five‐year
indefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. The
minimum quantity to be purchased under this contract is 67 buses and the total
number of buses procured will not exceed the maximum amount of 164.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$80,261,908

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2019

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia.

Last Updated 06.22.2023

+ Purchase 40' Low-Floor CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Pace will purchase 40FT CNG Buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$75,896,625

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Mar 2022

End Date

Mar 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses.

Last Updated 06.22.2023

+ CTA Brown Line Improvements Rail $0 $0 $436,384,000 $436,384,000

Description:

Upgrades and State of Good Repair projects along the Brown Line

No Results Found

+ Metra A-2 Interlocking Replacement Rail $0 $0 $787,500,000 $787,500,000

Description:

Separate tracks at busiest switching location on Metra system

No Results Found

+ CTA Signal Replacement (Systemwide) Rail $0 $0 $619,339,000 $619,339,000

Description:

Replacement of outdated signal systems systemwide

No Results Found

+ Pace Improve Passenger Facilities - Park-n-Ride Lots Bus $0 $0 $7,450,000 $7,450,000

Description:

Updates and repairs to Park-n-Ride lots

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-55 Park-n-Rides Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,750,000
$0
$0
$6,750,000

Last Updated 12.16.2022

+ Pace Uncategorized Projects - Pace Bus $0 $0 $0 $0

Description:

These are a miscellaneous set of Capital projects undertaken by Pace

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Vision Plan Implementation Study Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Vision Plan Implementation Study - Consulting services to include a system-wide market analysis and proposed service restructuring plan that will address the goals and objectives of Pace’s Driving Innovation Strategic Vision Plan.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$0
$1,000,000

Last Updated 12.16.2022

+ Transit Asset Management Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Transit Asset Management - Consulting services for TAM Plan updates, including condition assessments of Pace facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$400,000
$0
$0
$400,000

Last Updated 12.16.2022

+ Unanticipated Capital Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Contingency funding for existing projects or small new projects

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$0
$0
$3,000,000

Last Updated 12.16.2022

+ Pace Associated Capital Maintenance Items Bus $0 $0 $89,600,000 $89,600,000

Description:

Capital costs associated with the maintenance of buses

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Engine/Transmission Retrofits & Maintenance Capital Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Engine/Transmission Retrofits & Associated Capital - Replacement of engines and transmissions at a unit cost of $160,000 per bus and $8,000 per paratransit vehicle, and associated capital (radiator, pumps, alternator, filters, belts, compressors, coils, shafts, modules, clamps, heaters, turbochargers, etc.).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,912,569
$0
$0
$5,912,569

Last Updated 12.16.2022

+ Pace Support Equipment/Non-Revenue Vehicles System $400,000 $3,900,000 $22,850,000 $18,950,000

Description:

Facility and system maintenance equipment and vehicles

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Support Equipment - Non-Revenue Vehicles Support Facilities & Equipment Bus $400,000 $3,900,000

PROJECT DETAILS

Description:

Support Equipment/Non-Revenue Vehicles - Projects in 2021 include the purchase of 18 compact SUVs and one minivan with wheelchair ramp.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$400,000
$3,500,000
$3,900,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$400,000
$3,500,000
$3,900,000

Last Updated 12.16.2022

+ CTA Program Development System $525,000 $2,625,000 $6,250,000 $3,625,000

Description:

Provide for Program Development

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Program Development - UWP Contingencies and Administration System $525,000 $2,625,000

PROJECT DETAILS

Description:

Develop and refine CTA's capital programs for inclusion into five year regional Transportation Improvement Program. Provide support as required to finalize the current TIP. Analyze project proposals for potential inclusion in the Authority's Capital Program, presentations to the public, CTA Board and Regional Transportation Authority (RTA).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$420,000
$1,680,000
$2,100,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$105,000
$420,000
$525,000
Total
$625,000
$525,000
$2,100,000
$3,250,000

Last Updated 12.16.2022