Capital Projects

Regional Capital Program

Download Capital Dataset

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measure which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Project Mode 2023 Fundingsort descending 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Uncategorized Projects - CTA System $927,004 $41,578,565 $160,000,000 $118,421,435

Description:

These are a miscellaneous set of Capital projects undertaken by CTA

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Transit OPACK Teams Sustainability Miscellaneous System $0 $0

PROJECT DETAILS

Description:

Funding will provide essential layer in Chicago's transit-dedicated strategy to deter, detect, prevent and respond to terrorism in, on and in proximity to critical mass transit infrastructure within the City of Chicago and the surrounding region. This funding provides visible and covert deterrence patrols on train platforms in the downtown business district and in other high-risk/high-consequence assets within the CTA infrastructure and throughout the system.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,503,744
$0
$0
$4,503,744

Last Updated 12.16.2022

+ Transit Terrorism Surge Operations (CPD) Miscellaneous System $0 $0

PROJECT DETAILS

Description:

Funding provides for directed patrols on overtime (surge) activity by CPD SWAT Transit Operational Response with Canine and Heavy Weapons (TORCH) Teams. This project intends to supplement the current surge project which is only activated for selected holidays, significant dates and events and will provide a transit anti-terrorism protection measure on summer weekend rush hours that are still marked by an increase of passenger volume in the downtown business district, creating a heightened risk of terrorist exploitation.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$634,305
$0
$0
$634,305

Last Updated 12.16.2022

+ Cicero Grade Crossing Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

The Cicero Grade Crossing Enhancements project will be located at the Cicero Pink Line, at the intersection of Cicero Ave and 21st Place . Changes to this grade crossing are a priority for CTA and the Illinois Department of Transportation (IDOT) due to several safety incidents at the grade crossing that have put CTA staff and passengers at potential risk. The enhancements to this crossing cover both civil and signal system upgrades. The roadway surfaces and continuous protective rubber boots at South Cicero Avenue have deteriorated over time.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$803,100
$0
$0
$803,100

Last Updated 12.16.2022

+ 95th St. Corridor Transit Oriented Development Study Miscellaneous System $0 $0

PROJECT DETAILS

Description:

CTA in partnership with City of Chicago Department of Planning and Development (DPD) will complete a comprehensive Equitable Transit Oriented Development (eTOD) planning study along a 2 mile stretch of the 95th Street Corridor, on the far south side of Chicago. This corridor includes five multimodal transit capital projects as follows: (1) RLE; (2) 95th Street Terminal Reconstruction; (3) Metra 95th Street/Chicago State University Station; and (4) & (5) Pace Pulse Halsted Rapid Transit Line and 95th Rapid Transit Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$800,000
$0
$0
$800,000

Last Updated 12.16.2022

+ Match for FTA Discretionary Awards Miscellaneous System $0 $40,000,000

PROJECT DETAILS

Description:

Local source of funds are in reserved to match Annual Federal Discretionary Awards.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$40,000,000
$40,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$40,000,000
$40,000,000

Last Updated 12.16.2022

+ Farebox Replacement Miscellaneous System $927,004 $1,578,565

PROJECT DETAILS

Description:

The new Farebox system will reduce in-service defects, improve network security by upgrading the data reporting system, reduce counterfeit bill transactions, and improve the efficiency of portable farebox operations for special events, while providing a more accurate location and complete ridership data picture of cash- paying customers.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$927,004
$651,561
$1,578,565
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$927,004
$651,561
$1,578,565

Last Updated 12.16.2022

+ CTA Systemwide Track Renewal Rail $961,000 $961,000 $396,611,635 $395,650,635

Description:

Track improvements to address the most immediate critical track needs throughout the CTA rail system

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Green & Pink Line West - Track Improvements Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Green & Pink Line West - Track Improvements (GTT)
Tower 18 to the Paulina Connector- Preserve the integrity of Lake St Elevated tracks through replacement of ties, fasteners, footwalks, improved curve geometry, and rail grinding as well as replacing the top flange as necessary.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,308,465
$0
$0
$1,308,465

Last Updated 12.16.2022

+ Red & Blue Line Subway - Track Improvements Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Red & Blue Line Subway - Track Improvements (GTT)
- Dearborn Subway Water Management and Track Improvements - This is a targeted project to replace assets that have been deteriorated by water infiltration. Work includes replace select rail, rail fasteners and direct fixation concrete ties, grind 100% of the running rail, and select drainage improvements

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,639,070
$0
$0
$5,639,070

Last Updated 12.16.2022

+ Third Rail Isolation Demonstration Project Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

CTA utilizes an exposed third rail system to provide power to trains on all revenue and non-revenue tracks. The third rail is typically installed on insulator chairs spaced eight feet apart just outside one of the running rails. CTA's rail cars utilize a “gravity shoe” to collect 600 Volts DC from the top surface of the third rail. In station areas, the third rail is typically located on the opposite side of the track from the station platform – this provides some level of protection from a person falling off the platform and coming in contact with the electrified third rail.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,478,864
$0
$0
$1,478,864

Last Updated 12.16.2022

+ Nagle Curve Improvements Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project includes removing and replacing existing rail in the Nagle Curve area on the O’Hare Branch of the Blue Line. Project replaces the existing rail with new continuous welded rail at Nagle Curve. The new rail will be set into the existing plates with 100% replacement of double studded pads, heavy duty insulators, and pandrol e-clips. Work also includes a track survey to record the track geometry (profile, alignment, cross level and gauge), clearances, and the location of the track.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$75,004
$0
$0
$75,004

Last Updated 12.16.2022

+ Congress Blue Line - P1 Track Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

The project includes various priority trackwork on the Blue Line Congress branch.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,500,000
$0
$0
$2,500,000

Last Updated 12.16.2022

+ Congress Line (Fast Tracks) Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project will replace rails, bars, plates, and address causes of water infiltration in Dearborn Subway between LaSalle and south portal.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$7,024,058
$0
$0
$7,024,058

Last Updated 12.16.2022

+ DC Breakers (Fast Tracks) Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project will replace DC breakers in Sacramento, Franklin, and Nagle Substations. This DC breaker replacement may require some changes to the organization of other equipment inside the substation.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,571,295
$0
$0
$6,571,295

Last Updated 12.16.2022

+ Rehabilitate Blue Line - Kimball Subway Waterproofing Electrical, Signal & Communications Rail $961,000 $961,000

PROJECT DETAILS

Description:

Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$961,000
$0
$961,000
Total
$0
$961,000
$0
$961,000

PMO:

Total Project Budget^

$6,824,710

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Aug 2021

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 06.22.2023

+ Pace Administration - Pace System $1,200,000 $1,200,000 $0 $0

Description:

Provide for program administration

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Professional Project Management and Oversight Consulting Services Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Project Management for Priority Capital Projects - Consulting services to assist Pace in the successful delivery of priority capital projects funded by Rebuild Illinois.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$425,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jul 2021

End Date

Nov 2021

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A contract was executed with STV Construction Inc. for project management consulting services. Task 1 involved a systems review of Pace's capital projects completion process and recommendations of industry best practices. The consultant completed the task order for this funding. This will be the final update of this project.

Last Updated 07.10.2022

+ 2021/2022 - Professional Project Management and Oversight Consulting Services Miscellaneous Bus $1,200,000 $1,200,000

PROJECT DETAILS

Description:

Project Management for Priority Capital Projects - Consulting services to assist Pace in the successful delivery of priority capital projects funded by Rebuild Illinois.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,200,000
$0
$1,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,200,000
$0
$1,200,000

PMO:

Total Project Budget^

$1,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jul 2021

End Date

Mar 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contractor, STV, completed all the work under contract for PMO services Task Order #5, which included e-Builder administration, augmentation of Pace staff, and other consulting services. Final invoices remain and this will be the final update on this project.

Last Updated 06.22.2023

+ Pace Pulse Infrastructure System $1,464,000 $21,031,500 $84,525,000 $63,493,500

Description:

Enhance Pulse service

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Pulse 95th Street Design and Construction Stations & Passenger Facilities Bus $1,464,000 $21,031,500

PROJECT DETAILS

Description:

Design and construction of stations of the Pulse 95th Rapid Transit Line. The project corridor is approximately 12.4 miles in length and runs east-west between the CTA Red Line 95th/Dan Ryan Station in Chicago and Moraine Valley Community College in Palos Hills primarily routed along 95th Street, as well as several other roadways in Bridgeview, Chicago Ridge, Hickory Hills, and Palos Hills.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,464,000
$15,654,000
$17,118,000
State
$0
$0
$3,913,500
$3,913,500
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,464,000
$19,567,500
$21,031,500

Last Updated 12.16.2022

+ Pace Regional Transit Signal Priority (RTSP) System $1,913,378 $7,913,378 $36,599,307 $28,685,929

Description:

Expand Transit Signal Priority installations region-wide

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $1,913,378 $7,913,378

PROJECT DETAILS

Description:

Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,680,000
$6,000,000
$7,680,000
State
$0
$0
$0
$0
RTA
$0
$233,378
$0
$233,378
Service Board / Local
$0
$0
$0
$0
Total
$2,400,693
$1,913,378
$6,000,000
$10,314,071

PMO:

Total Project Budget^

$10,293,685

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2019

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th.

Last Updated 06.22.2023

+ Pace Fixed Route Buses - Electric Bus $1,920,000 $61,720,000 $374,400,000 $312,680,000

Description:

Replacement of buses reaching useful life with electric buses

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Fixed Route Electric Buses Rolling Stock Bus $1,920,000 $61,720,000

PROJECT DETAILS

Description:

Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,920,000
$59,800,000
$61,720,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$20,550,058
$1,920,000
$59,800,000
$82,270,058

PMO:

Total Project Budget^

$26,301,403

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

May 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace is also in the process of increasing the order by two additional buses, bring the total to 22 electric buses.

Last Updated 06.22.2023

+ Pace Security, Computer, Software, and Office Systems Upgrades Bus $1,963,505 $13,544,635 $47,900,000 $34,355,365

Description:

Upgrade systems to provide enhanced asset protection and business systems

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Computer Systems - Hardware & Software Support Facilities & Equipment Bus $0 $3,500,000

PROJECT DETAILS

Description:

Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$3,500,000
$3,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$3,500,000
$3,500,000

PMO:

Total Project Budget^

$1,100,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2022

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with a rebid for the procurement of digital screens for the interior of the buses due to low responses. Additional tasks will be added throughout the duration of this project.

Last Updated 06.22.2023

+ Bus Security Cameras Electrical, Signal & Communications Bus $0 $2,000,000

PROJECT DETAILS

Description:

This project purchases security cameras for bues.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$2,000,000
$2,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$2,000,000
$2,000,000

Last Updated 12.16.2022

+ Onboard Digital Screens Electrical, Signal & Communications Bus $1,963,505 $8,044,635

PROJECT DETAILS

Description:

Purchase and install digital screens inside existing buses to display passenger information, such as next-stop announcements, detour notices, and passenger notices.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,963,505
$6,081,130
$8,044,635
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,963,505
$6,081,130
$8,044,635

Last Updated 06.22.2023

+ CTA Tactical Signal Improvements Rail $2,125,768 $2,125,768 $21,630,000 $19,504,232

Description:

State of Good Repair projects and replacing obsolete equipment on CTA rail signal system

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Tactical Traction Power (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $2,125,768 $2,125,768

PROJECT DETAILS

Description:

State of Good Repair projects and replacing obsolete equipment on CTA rail signal system

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,125,768
$0
$2,125,768
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$2,125,768
$0
$2,125,768

PMO:

Total Project Budget^

$10,293,685

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2022

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Permits for the project were received in the last reporting period. Currently, the General Contractor is submitting process plans for start of construction and mobilization on site. Delivery of onsite storage containers is ongoing. CTA is working with the contractor to start the first phase of the project, which is the electrical shop equipment relocation.

Last Updated 06.22.2023

+ CTA Non-Revenue Vehicle Replacement Program System $2,494,359 $10,944,359 $81,741,905 $70,797,546

Description:

Replacement of vehicles needed for maintenance and operations support

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Non-Revenue Vehicles - Diesel Locomotives Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Equipment and Non-Revenue Vehicles (Diesel Locomotives): Funding will provide for the replacement of CTA's diesel locomotive snow fighters. The self-propelled locomotives with special attachments to remove snow and ice during severe winter weather conditions are able to operate and clear system track, so that CTA can safely power up the system to restore/provide service. When traction power is down, this equipment will also be used to move rolling stock to secure locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,333,095
$0
$0
$3,333,095

PMO:

Total Project Budget^

$22,731,013

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Aug 2020

End Date

May 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The structural design was approved by the CTA. The project is in full production mode and the contractor managed to start the first engine skid during this reporting period. The first locomotive is beginning the final assembly including all of the wiring, hoses, connection plates, and controls between various parts. CTA and the contractor are coordinating a site visit for when the load testing will be performed by the contractor. If the load test passes, the contractor will commission vehicle #1 and continue the assembly of the remaining vehicles.

Last Updated 06.22.2023

+ Non-Revenue Utility Vehicle Replacement Support Facilities & Equipment System $1,225,000 $3,675,000

PROJECT DETAILS

Description:

Heavy-Duty Vehicles to support routine infrastructure maintenance, emergency repairs, and recovery operations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,225,000
$2,450,000
$3,675,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,225,000
$1,225,000
$2,450,000
$4,900,000

Last Updated 05.18.2023

+ Equipment and Non-Revenue Vehicles Program Support Facilities & Equipment System $1,269,359 $7,269,359

PROJECT DETAILS

Description:

CTA plans to invest funds annually to fund the phased replacement of aged equipment and vehicles used by CTA maintenance groups that include Bus, Rail, Power & Way, and Facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,269,359
$6,000,000
$7,269,359
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,269,359
$6,000,000
$7,269,359

Last Updated 05.18.2023

+ Pace Paratransit Vehicles - Replacement Bus $2,801,859 $20,228,863 $50,825,000 $30,596,137

Description:

Replacement of vehicles reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Electric Paratransit Vehicles Rolling Stock Bus $1,000,000 $1,000,000

PROJECT DETAILS

Description:

This project will fund the purchase of electric paratransit vehicles.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$0
$1,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$0
$1,000,000

Last Updated 06.22.2023

+ Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,801,859 $19,228,863

PROJECT DETAILS

Description:

Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,801,859
$17,427,004
$19,228,863
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,567,180
$1,801,859
$17,427,004
$24,796,043

PMO:

Total Project Budget^

$69,991,388

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Nov 2015

End Date

Nov 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 118 vehicles and 24 more are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are expected to be executed in Q4-2023.

Last Updated 06.22.2023