PROJECT DETAILS
Core Requirement(s) | |
---|---|
Maintain and Improve Safety and Reliability | ✓ |
Achieve Full Accessibility | |
Meet Regulatory Requirements | ✓ |
Improve Equity |
Strategic Goal | |
---|---|
Deliver Value on Investment | ✓ |
Build on the Strengths of Our Network | |
Stay Competitive |
Funding Amounts by Source:
Source | Previous Funding* | 2023 Funding | 2024-2027 Funding | Total |
---|---|---|---|---|
Federal |
$0 |
$0 |
$0 |
$0 |
State |
$0 |
$0 |
$0 |
$0 |
RTA |
$0 |
$0 |
$0 |
$0 |
Service Board / Local |
$0 |
$0 |
$0 |
$0 |
Total |
$38,000,000 |
$0 |
$0 |
$38,000,000 |
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
Oct 2022End Date
Dec 2024^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.
Last Updated 06.22.2023