Capital Projects

Regional Capital Program

Download Capital Dataset

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measure which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agencysort descending Priority Project Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Pace Uncategorized Projects - Pace Bus $0 $0 $0 $0

Description:

These are a miscellaneous set of Capital projects undertaken by Pace

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Transit Asset Management Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Transit Asset Management - Consulting services for TAM Plan updates, including condition assessments of Pace facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$400,000
$0
$0
$400,000

Last Updated 12.16.2022

+ Unanticipated Capital Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Contingency funding for existing projects or small new projects

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$0
$0
$3,000,000

Last Updated 12.16.2022

+ Vision Plan Implementation Study Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Vision Plan Implementation Study - Consulting services to include a system-wide market analysis and proposed service restructuring plan that will address the goals and objectives of Pace’s Driving Innovation Strategic Vision Plan.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$0
$1,000,000

Last Updated 12.16.2022

+ Pace Construct New Support Facilities Bus $0 $0 $0 $0

Description:

Add needed capacity for bus maintenance and storage

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ New I-55 Garage - Plainfield Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Plainfield Garage - Completion of construction of a new 189,000 square foot bus storage and maintenance facility in Plainfield, housing up to 130 buses with 12 maintenance bays and administrative offices. Pace has executed an I.G.A. with Northern Builders and the village of Plainfield to construct the project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$425,000
$0
$0
$425,000

PMO:

Total Project Budget^

$55,385,593

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Nov 2020

End Date

Apr 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Construction of the facility has been completed in September 2022. Pace received the occupancy permit and the facility operations as well as bus service started in October 2022. Pace added an additional phase to the project to include an electric bus charger and electric car chargers, as well as procurement of various furniture and equipment for the facility and offices. This last phase of the project has reached substantial completion in April 2023. This project is currently in close out.

Last Updated 06.22.2023

+ New Northwest Garage - Wheeling Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Northwest Wheeling Garage - Completion of the renovation of a 430,000 square feet bus storage and maintenance facility in Wheeling that will replace Pace's Northwest Division garage in Des Plaines. This CNG fueling facility will house approximately 133 buses with 17 maintenance bays and administrative offices.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$81,129,563

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Dec 2020

End Date

Nov 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace has entered into an Intergovernmental Agreement (IGA) with the Village of Wheeling. The improvements to Old Willow Road have been completed. The initial design has been finalized. The project is in the process of being re-scoped to add the electrification component. The design will be updated once Pace’s electrification study is completed to include the additional scope of work.

Last Updated 06.22.2023

+ River Division Expansion Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

This project is for architectural and engineering services that will provide pre-design services, geotechnical engineering, land surveys, traffic studies, existing facilities testing and evaluation and feasibility studies. It will also include design and construction administration, inspections and project oversight. Pace intends to expand and improve its existing River Division bus garage onto newly acquired property south of the existing garage. It will be designed to accommodate storage, servicing,

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$36,110,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Oct 2020

End Date

Jun 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace has entered into a contract for Architectural and Engineering services for pre-design and design services. The contractor completed the pre-design activities, and final pre-design report was submitted to Pace. The adjacent property acquisition has been completed. Pace is undertaking an electrification study that will inform the design changes needed to make this facility compatible with an electric bus fleet. The design activities are currently on hold pending the recommendations from this study. Pace will need to revise the initial 30% design to incorporate future electrification components before activities resume with the designer.

Last Updated 06.22.2023

+ South Campus Project - Markham Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

This project will provide for construction, project management oversight, project administration, and any associated equipment and services for the Pace South Campus project. New facilities will be built on a 22-acre site that is situated next door to Pace’s South Division (2107 W. 163rd Place) Garage in Markham, Illinois, which is already owned by Pace. The purpose of this project is to consolidate certain operational functions currently operating at each garage into one location.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$36,916,905

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Dec 2020

End Date

Oct 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed for construction has been issued in January 2022. Construction activities are in progress. The Acceptance Facility precast wall installation is ongoing. The office building work included roofing, under slab electrical installation, metal framing and HVAC layout.

Last Updated 06.22.2023

+ Pace Vanpool Vehicles - Replacement Bus $0 $0 $12,640,000 $12,640,000

Description:

Replacement of vans reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase 7-passenger Vanpool Vehicles Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Vanpool Vehicles - Pace plans to purchase 164 replacement 17'-20' vans including associated equipment and services (Buy America audit and inspections) for vanpool services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$13,899,800

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2019

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

To date a total of 25 vans have been ordered, all have been received. Pace has executed a contract to install OEM passenger running boards on the first order of 25 vans. All the running boards have been installed and are in the active fleet. Pace continued to work on an action plan for ordering more vehicles based on projected needs. The vans will be utilized in the six county Pace service area.

Last Updated 06.22.2023

+ Pace Farebox System Bus $0 $0 $0 $0

Description:

Replace fareboxes that are over 20-years old

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Farebox System Replacement Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Farebox System Replacement - Over 700 fareboxes on Pace fixed route buses will be replaced, with prior PAYGO funding of $7.5M from 2020 included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,079,344
$0
$0
$3,079,344

PMO:

Total Project Budget^

$7,500,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Nov 2020

End Date

Mar 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace awarded their procurement for a new farebox system and production and delivery of the farebox equipment is ongoing. Farebox equipment continues to be installed and projected to be completed by Q1-2024.

Last Updated 06.22.2023

+ Pace Fixed Route Buses - Electric Bus $1,920,000 $61,720,000 $374,400,000 $312,680,000

Description:

Replacement of buses reaching useful life with electric buses

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Fixed Route Electric Buses Rolling Stock Bus $1,920,000 $61,720,000

PROJECT DETAILS

Description:

Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,920,000
$59,800,000
$61,720,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$20,550,058
$1,920,000
$59,800,000
$82,270,058

PMO:

Total Project Budget^

$26,301,403

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

May 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace is also in the process of increasing the order by two additional buses, bring the total to 22 electric buses.

Last Updated 06.22.2023

+ Pace Fixed Route Buses - Expansion Bus $0 $0 $83,889,000 $83,889,000

Description:

Buses for new services

No Results Found

+ Pace Fixed Route Buses - Replacement Bus $0 $9,750,000 $79,300,000 $69,550,000

Description:

Replacement of buses reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Fixed Route CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement CNG buses - Pace plans to replace 115 diesel buses with 40' Compressed Natural Gas (CNG) buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the future Northwest Division garage in Wheeling, currently being designed as a CNG fueling facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$28,050,000
$0
$0
$28,050,000

Last Updated 12.16.2022

+ Fixed Route Coach Buses Rolling Stock Bus $0 $9,750,000

PROJECT DETAILS

Description:

Coach Buses - Pace plans to replace 13 40' diesel coach buses, including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the I-55 Bus on Shoulder service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$9,750,000
$9,750,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$9,750,000
$9,750,000

Last Updated 12.16.2022

+ Purchase 30' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

This project is a new contract awarded in September 2019 for a new five‐year
indefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. The
minimum quantity to be purchased under this contract is 67 buses and the total
number of buses procured will not exceed the maximum amount of 164.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$80,261,908

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2019

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia.

Last Updated 06.22.2023

+ Purchase 40' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$41,786,531

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2019

End Date

Nov 2020

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.

Last Updated 07.10.2021

+ Purchase 40' Low-Floor CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Pace will purchase 40FT CNG Buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$75,896,625

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Mar 2022

End Date

Mar 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses.

Last Updated 06.22.2023

+ Pace Improve Passenger Facilities - Park-n-Ride Lots Bus $0 $0 $7,450,000 $7,450,000

Description:

Updates and repairs to Park-n-Ride lots

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-55 Park-n-Rides Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,750,000
$0
$0
$6,750,000

Last Updated 12.16.2022

+ Pace Improve Passenger Facilities - Transportation Centers Bus $5,400,000 $5,400,000 $72,550,000 $67,150,000

Description:

Improvements to Transportation and Transfer Facilities

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Harvey Transportation Center - Pace Stations & Passenger Facilities Bus $5,400,000 $5,400,000

PROJECT DETAILS

Description:

Pace is partnering with Metra, the City of Harvey, and IDOT with the intent to move the transportation center and combine it with the Metra station.

The elements of the construction may include pavement, lighting, platforms, shelters, restrooms, structures and systems and may have a taxi release area to create a multimodal facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,400,000
$0
$5,400,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$25,450,000
$5,400,000
$0
$30,850,000

Last Updated 12.16.2022

+ Improve Passenger Facilities Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Improve Passenger Facilities - Fabrication of a new Ventra machine for the O'Hare multimodal facility in 2021. Future renovations are being evaluated for Burr Ridge & Hillside Park-n-Rides, Chicago Heights Transfer Center, Riverdale Bus Turnaround, and Gurnee Mills Transportation Center.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$120,000
$0
$0
$120,000

Last Updated 12.16.2022

+ Joliet Gateway Center - Bus Stop Improvements Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby public
properties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopment
the City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public and
inter-city transit which will include parking improvements and the construction of new vehicular and
pedestrian access and circulation system. The new Bus Station is south of New Street, north of Marion

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$9,509,500

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Feb 2021

End Date

Jun 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk‐through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.

Last Updated 01.09.2023

+ Pace Improve Support Facilities Bus $49,750,000 $188,492,000 $237,322,483 $48,830,483

Description:

Improvements to garage facilities including underground storage tanks

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Construct Salt Shed Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Pace is in need of a stand-alone storage solution and will construct a shed to store and secure up to 10
tons of bulk rock salt that is used during the winter season. The construction of the shed will be within the
footprint of Pace's parcel. This shed will allow for accessible use with Pace's skidsteer to load rock salt
onto the pickup trucks and distribute it on approximately more than 15,000 square yards of grounds
(parking lots and driveways), in addition to sidewalks, in a safe and more efficient manner. Currently

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$75,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Mar 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A construction contract was awarded. There were some delays related to the Village code requirements and permits. All activities were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ Fire Loop System Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Replacement of underground loop, piping, valves, and pump for fire suppression.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,050,000
$0
$0
$2,050,000

Last Updated 12.16.2022

+ Headquarters Renovation Support Facilities & Equipment Bus $750,000 $16,750,000

PROJECT DETAILS

Description:

Paint and carpet replacement at Administrative Office in Arlington Heights. HQ is currently 2 floors of employees with the building capable of a 3rd floor structure. Adding a third floor we would incorporate high efficient heating and cooling with hospital grade filters update the colors and carpet and workspace on the first and second floor to match the third floor.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$750,000
$16,000,000
$16,750,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$750,000
$16,000,000
$16,750,000

Last Updated 12.16.2022

+ North Division Electrification/Expansion Support Facilities & Equipment Bus $49,000,000 $77,600,000

PROJECT DETAILS

Description:

Renovation and expansion of North Division Garage located in Waukegan, including installation of charging capabilities for electric buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$49,000,000
$28,600,000
$77,600,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$49,000,000
$28,600,000
$77,600,000

Last Updated 12.16.2022

+ North Shore Division Expansion Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

North Shore Division Expansion - A/E design and construction to renovate and expand Pace's North Shore Division bus garage.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$20,000,000
$0
$0
$20,000,000

Last Updated 12.16.2022

+ Southwest Division Electrification/Expansion Support Facilities & Equipment Bus $0 $94,142,000

PROJECT DETAILS

Description:

The facilities will be built on a 22-acre site that is situated next door to Pace’s South
Division Garage in Markham and owned by Pace. The purpose of this project is to consolidate certain
operational functions currently operating at each garage into one location. This will improve productivity
and control costs by eliminating duplication. The original plan was to construct three separate buildings:
1) an Active Transit Management Center to accommodate Central Dispatching; 2) a new Central Stores

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$61,000,000
$61,000,000
State
$0
$0
$33,142,000
$33,142,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$94,142,000
$94,142,000

Last Updated 12.16.2022