Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Projectsort descending Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Blue Line Forest Park Modernization - Phase 2 Rail $0 $0 $653,077,000 $653,077,000

Description:

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

No Results Found

+ CTA Blue Line Forest Park Modernization - Phase 3 Rail $0 $0 $598,030,000 $598,030,000

Description:

Track improvement and special work placement, interlocking relocation and station renovations

No Results Found

+ CTA Blue Line Forest Park Modernization - Phase 4 Rail $0 $0 $597,030,000 $597,030,000

Description:

Des Plaines Yard and Forest Park terminal reconstruction

No Results Found

+ CTA Bond Repayment, Interest Cost & Finance Cost System $197,095,845 $1,011,656,756 $1,874,473,580 $862,816,824

Description:

Support CTA Debt

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ CTA Bond Repayment - Principal/Interest Miscellaneous System $197,095,845 $1,011,656,756

PROJECT DETAILS

Description:

Bond Repayment, Interest Cost, & Finance Cost: Provide for debt service and the cost of issuance of bonds, notes and other indebtedness incurred by the CTA.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$197,095,845
$814,560,911
$1,011,656,756
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$317,940,808
$197,095,845
$814,560,911
$1,329,597,564

Last Updated 12.16.2022

+ Metra Bridge Replacement and Repair Rail $60,490,000 $135,248,500 $2,046,135,000 $1,910,886,500

Description:

Replace and repair 61 bridges systemwide.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 275-Old 96th Ave. Bridge Track & Structure Rail $0 $2,500,000

PROJECT DETAILS

Description:

This project funds the replacement of Bridge 275 on Metra’s Rock Island District. The 94-year-old bridge spans over 96th Avenue in Mokena at milepost 27.5.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$2,500,000
$2,500,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$2,500,000
$2,500,000

Last Updated 12.16.2022

+ Bridge 86 - 78th St Entrance Track & Structure Rail $30,100,000 $30,100,000

PROJECT DETAILS

Description:

Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$30,100,000
$0
$30,100,000
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$30,100,000
$0
$33,100,000

PMO:

Total Project Budget^

$3,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Aug 2021

End Date

Dec 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for the bridge and entrance is at 65% completion, and proceeding to 90% completion. Design is expected to be complete by end of 2023.

Last Updated 06.22.2023

+ Bridge A-32 Reconstruction Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$38,041,561

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2020

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities on site and is 43% complete.

Last Updated 06.22.2023

+ Bridge A110/56 Track & Structure Rail $1,500,000 $1,500,000

PROJECT DETAILS

Description:

This project funds the replacement of Bridges A110 and A56 on Metra’s Milwaukee District North (MD-N) Line. Both bridges were constructed in 1909 and span the North Branch Chicago River. Bridge A110 is located in Northbrook at milepost 21.3 and Bridge A56 is at milepost 10.85 in Chicago just south of the Edgebrook station. This is a multi-year, multi-phase project that will fund design engineering services and any environmental analyses as required by the National Environmental Policy Act (NEPA). Construction funds are provided in later years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$1,500,000
$0
$1,500,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,595,000
$1,500,000
$0
$4,095,000

Last Updated 03.15.2023

+ Bridge A318 Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project funds design services and the construction of a replacement bridge that will increase the capacity of trains and service on the Milwaukee District North (MD-N) Line. The new Bridge A318 will add a second-track siding over the North Branch Chicago River in Rondout at milepost 32.4. A second-track siding will allow for additional train movements through the Fox Lake Subdivision, which runs northwest of Rondout and includes seven stations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,000,000
$0
$0
$2,000,000

Last Updated 12.16.2022

+ Bridge A418 Track & Structure Rail $3,200,000 $3,200,000

PROJECT DETAILS

Description:

This project funds the engineering design of a bridge replacement that spans the Mud Creek in Long Lake at milepost 45.8. The project has construction funds in following year to replace the circa 1909 structure on the Fox Lake Subdivision, which runs north-west from Rondout to Fox Lake along the Milwaukee District North Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$3,200,000
$0
$3,200,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$3,200,000
$0
$3,200,000

Last Updated 03.16.2023

+ Bridges & Retaining Walls BNS Track & Structure Rail $3,000,000 $10,562,500

PROJECT DETAILS

Description:

This project will provide for the rehabilitation of retaining walls on the BNSF commuter line. Retaining wall sections at intermittent locations along the right-of-way will be rehabilitated. This work typically includes complete reconstruction with steel sheet piling, concrete panels or bin wall to prevent retaining wall deterioration that can result in destabilization of the roadbed and in turn lead to track shifting.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,000,000
$7,562,500
$10,562,500
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,250,000
$3,000,000
$7,562,500
$12,812,500

Last Updated 12.16.2022

+ Bridges & Retaining Walls MED Track & Structure Rail $1,390,000 $8,990,000

PROJECT DETAILS

Description:

These projects improvement of bridges and the rehabilitation of retaining walls at various locations to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,390,000
$7,600,000
$8,990,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$600,000
$1,390,000
$7,600,000
$9,590,000

Last Updated 12.16.2022

+ Bridges & Retaining Walls MWD Track & Structure Rail $550,000 $11,400,000

PROJECT DETAILS

Description:

These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the MWD to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$550,000
$10,850,000
$11,400,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$700,000
$550,000
$10,850,000
$12,100,000

Last Updated 12.16.2022

+ Bridges & Retaining Walls RID Track & Structure Rail $2,550,000 $11,310,000

PROJECT DETAILS

Description:

These projects improvement of bridges and the rehabilitation of retaining walls at various locations to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,550,000
$8,760,000
$11,310,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$200,000
$2,550,000
$8,760,000
$11,510,000

Last Updated 12.16.2022

+ Bridges & Retaining Walls UPR Track & Structure Rail $200,000 $2,200,000

PROJECT DETAILS

Description:

These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the UPR to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$200,000
$2,000,000
$2,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$200,000
$2,000,000
$2,200,000

Last Updated 12.16.2022

+ CREATE EW-2 Bridge Lift Track & Structure Rail $3,000,000 $3,000,000

PROJECT DETAILS

Description:

This project involves lifting a bridge between 78th Street and 79th Street on Metra’s Rock Island Line. The bridge spans over three sets of railroad tracks owned by The Belt Railway of Chicago and Norfolk Southern in Chicago at milepost 8.7. This project is a necessary component of the new Auburn Park station project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$3,000,000
$0
$3,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$3,000,000
$0
$4,000,000

PMO:

Total Project Budget^

$8,404,189

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jun 2021

End Date

Dec 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for the project has been completed. Metra advertised the construction procurement and received only one bid. The proposed cost exceeded the allocated construction budget for the project. Metra made a decision to re-design the project to reduce the risk off of the potential contractor and attract more bids. A change order has been issued to the designer and the re-design is 90% complete.

Last Updated 06.22.2023

+ Evanston Bridge Repainting Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project involves the sanding, abatement and repainting of the Dempster Street and Davis Street
bridges in Evanston on the Union Pacific North Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$3,300,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jun 2021

End Date

Dec 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contractor finished painting and applying the protective coating on the bridge in December. Final invoices remain and this will be the final update on this project.

Last Updated 06.22.2023

+ Grand Avenue Bridge Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project funds engineering design services for the replacement of the Grand Avenue Bridge. Three main line tracks utilize the bridge including the Milwaukee District North and West Lines and the North Central Service. The bridge, constructed in 1898, spans over the intersection of Grand Avenue and Homan Avenue at milepost 4.5. Construction funds are provided in future years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$16,000,000
$0
$0
$16,000,000

Last Updated 12.16.2022

+ Gresham Area Bridges Track & Structure Rail $15,000,000 $15,000,000

PROJECT DETAILS

Description:

This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$15,000,000
$0
$15,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,000,000
$15,000,000
$0
$17,000,000

PMO:

Total Project Budget^

$16,816,250

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jul 2021

End Date

Nov 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Design work for the Vincennes Ave. Bridge #98 and Morgan St. Bridge #S- 102 were completed. City land swap negotiations are ongoing. Metra is proceeding without the property swap and is investigating the original elevation ordinance for the legal right to construct on City property. The designer submitted 100% drawings for review and coordination with the City of Chicago is ongoing. Bid documents are in process.

Last Updated 06.22.2023

+ Hickory Creek Bridge Track & Structure Rail $0 $200,000

PROJECT DETAILS

Description:

This project funds repair activities to rehabilitate the existing piers and abutments. The existing bridge spans the Hickory Creek.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$200,000
$200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$200,000
$200,000

Last Updated 12.16.2022

+ Replace Bridges - 18th to 55th - RID Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Phase 1 and 2 design and construction are complete. The Phase 3 design task was
issued an NTP in August 2018. The Phase 3 design was completed in July 2019. The
Phase 3 construction contract and construction management contract were both
awarded in September 2020. Construction started with site work in March 2021
and is ongoing. Current activities are related to obtaining permits. The estimated
project completion date for construction is December 2021 to allow enough time
for phase 3 construction.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$120,282,161

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Aug 2018

End Date

Dec 2021

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Phase 1 and 2 design and construction are complete. The Phase 3 design task was issued an NTP in August 2018. The Phase 3 design was completed in July 2019. The Phase 3 construction contract and construction management contract were both awarded in September 2020. Construction started with site work in March 2021 and is ongoing. Current activities are related to obtaining permits. The project reached substantial completion in December 2021. This will be the final update on this project.

Last Updated 07.10.2022

+ Stoney Creek Bridge- SWS Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$8,500,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Apr 2022

End Date

Oct 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is in the design phase. There are some delays related to the National Environmental Policy Act (NEPA) process and the Illinois State Historic Preservation Office (SHPO) review. The 30% design has been completed. Once the NEPA and SPHO process is complete, work will continue on the design to advance to 60%.

Last Updated 06.22.2023

+ UP North Line - North 11 Bridges and Ravenswood Station Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, the

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$50,255,463

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jul 2017

End Date

Aug 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The bridge construction has been completed in September 2021. The station contractor continues with finishing work at the station including installation of drywall, hardware, lighting, painting and installation of infrared heating. Supply chain issues are delaying the installation of structural glazed facing tile at the station.

Last Updated 06.22.2023

+ UP North Line - South 11 Bridges Track & Structure Rail $0 $35,286,000

PROJECT DETAILS

Description:

This project will provide for the reconstruction of bridges and retaining walls on the Union Pacific North Line, and Ravenswood Station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$27,157,000
$27,157,000
State
$0
$0
$8,129,000
$8,129,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$35,286,000
$35,286,000

PMO:

Total Project Budget^

$162,100,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jun 2020

End Date

May 2028

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is in the design phase. The National Environmental Policy Act (NEPA) review process is ongoing. Design activities are 60% complete and will progress to 90% once the NEPA process is completed.

Last Updated 06.22.2023

+ Z14C- Keystone Ave. Bridge Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

This project funds engineering design services for the replacement of the Z 14 C in Chicago. The bridge, constructed in 1903, spans over the intersection of Keystone Avenue Bridge at milepost 5.69. Construction funds are provided in future years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$11,600,000
$0
$0
$11,600,000

Last Updated 12.16.2022

+ CTA Brown Line Improvements Rail $0 $0 $436,384,000 $436,384,000

Description:

Upgrades and State of Good Repair projects along the Brown Line

No Results Found

+ CTA BRT/Bus Slow Zone Removal/ TSP/Dedicated Lane projects System $15,200,000 $15,200,000 $231,240,000 $216,040,000

Description:

Targeted street and traffic signal improvements to increase bus speeds

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Slow Zones Elimination Program Miscellaneous Bus $15,200,000 $15,200,000

PROJECT DETAILS

Description:

This is a joint partnership with CDOT where CTA and CDOT will implement a coordinated program of bus priority treatments and targeted solutions for specific problem areas, in order to improve speed and reliability on major bus corridors. Project funds will cover final design and construction for all six routes.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$15,200,000
$0
$15,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$15,200,000
$0
$15,200,000

Last Updated 12.16.2022

+ CTA Bus Garage Improvements Bus $43,009,730 $141,009,730 $248,090,000 $107,080,270

Description:

Provide repairs at bus maintenance garages and shops

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Hoist Replacement Program Support Facilities & Equipment Bus $15,000,000 $15,000,000

PROJECT DETAILS

Description:

Project will support an updated assessment of the bus hoists to determine which may need replacement, as well as design and construction for those locations. This funding will provide for the purchase and installation of bus hoists at five CTA bus garages.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$15,000,000
$0
$15,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$15,000,000
$0
$15,000,000

Last Updated 03.15.2023

+ Improve Facilities - Electric Bus Program Planning Support Facilities & Equipment Bus $28,009,730 $126,009,730

PROJECT DETAILS

Description:

CTA has committed to a full electrification of the bus fleet by 2040, providing significant air quality improvements to the region and the immediate vicinity of the garage facilities. To implement the program, the garages will need to be converted to allow for routing servicing / charging of the buses as well as new maintenance requirements. The work will generally involve significant electrical upgrades, installation of charger infrastructure, and general updates to the facility to support the conversion to an electric fleet.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$11,590,000
$98,000,000
$109,590,000
State
$0
$16,419,730
$0
$16,419,730
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$16,590,000
$28,009,730
$98,000,000
$142,599,730

Last Updated 12.16.2022

+ North Park Garage – Building Demolition Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Project will cover the building demolition and site restoration of 5323 N. Kedzie.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$177,485
$0
$0
$177,485

Last Updated 12.16.2022

+ Pace Bus on Shoulder (BoS) Infrastructure Bus $0 $17,025,000 $17,025,000 $0

Description:

Passenger facilities for Bus on Shoulder service

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-294 Stations & Park-n-Rides Stations & Passenger Facilities Bus $0 $17,025,000

PROJECT DETAILS

Description:

I-294 Stations and Park-n-Rides : The Illinois Tollway is planning to add a Flex Lane on 22 miles of I-294, and infrastructure is needed to make connections to the transit system. Pace is currently conducting market analysis and workshops for this project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$17,025,000
$17,025,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$17,025,000
$17,025,000

Last Updated 12.16.2022

+ Pace Charging Infrastructure Bus $0 $0 $36,000,000 $36,000,000

Description:

Charging infrastructure at garages to charge electric buses, including power supply lines, charging station equipment, and backup generators .

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Charging Infrastructure Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Maintenance of existing building structures, systems, asphalt/concrete, etc. Charging infrastructure at North, North Shore, and Southwest Divisions.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,500,000
$0
$0
$5,500,000

Last Updated 12.16.2022

+ North Division Garage Improvements Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

These funds will be used to prepare the North Garage for Electirc buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$10,181,017
$0
$0
$10,181,017

Last Updated 12.16.2022