Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agencysort descending Priority Project Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Blue Line Forest Park Modernization - Phase 4 Rail $0 $0 $597,030,000 $597,030,000

Description:

Des Plaines Yard and Forest Park terminal reconstruction

No Results Found

+ CTA Railcar Overhauls Rail $26,899,057 $214,245,363 $216,027,620 $1,782,257

Description:

Quarter-life overhaul of 5000-series rail cars and life-extending overhauls of older 2600 and 3200-series rail cars

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $21,899,057 $71,172,694

PROJECT DETAILS

Description:

5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter‐Life Overhaul on the 5000‐Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$15,299,632
$15,299,632
State
$0
$20,000,000
$33,974,005
$53,974,005
RTA
$0
$0
$0
$0
Service Board / Local
$0
$1,899,057
$0
$1,899,057
Total
$11,335,000
$21,899,057
$49,273,637
$82,507,694

PMO:

Total Project Budget^

$400,000,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Oct 2020

End Date

Jan 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

As of the end of April 2023, 266 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 06.22.2023

+ Life extending Overhaul 2600/3200 Series Rolling Stock Rail $0 $118,072,669

PROJECT DETAILS

Description:

Life extending overhaul on the 258 3200 Series and 300 2600 Series cars. Work on these cars will focus on major systems starting with the proplusion/powering.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$118,072,669
$118,072,669
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$118,072,669
$118,072,669

Last Updated 12.16.2022

+ Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of
the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in
August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery of

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$25,314,552

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2019

End Date

Mar 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 07.10.2022

+ Replace video system 3200 and 5000-Series railcars Rolling Stock Rail $5,000,000 $25,000,000

PROJECT DETAILS

Description:

Replace the existing video system on the 5000-series rail cars which is obsolete and no longer supported by the vendor. Replace existing video system on the 3200-series rail cars with a more reliable system. Useable components removed from the 3200s will be re-used to support the same system on the 2600-seriese rail cars.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,000,000
$20,000,000
$25,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,000,000
$20,000,000
$25,000,000

Last Updated 12.16.2022

+ CTA Systemwide Station Program Rail $24,536,026 $65,104,655 $140,877,056 $75,772,401

Description:

Station upgrades, modernization and accessibility improvements

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 43rd Street Station Green Line - Improvements Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Project will revise an exit only stair to reduce the street level footprint and make other aesthetic and state-of-good repair upgrades to coordinate with an upcoming new adjacent development.
Creates a Green Line TOD project at 43rd Station in Southeast side of the City and provides for an enhanced environment to sustain the redevelopment occurring within the neighborhood.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$12,000,000
$0
$0
$12,000,000

Last Updated 12.16.2022

+ Central Station (Purple Line) - Stair Replacement Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Replace Central Station stairway, in Evanston, which include risers, treads, stair stringers, handrails, guardrails, canopies and enclosures.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,414,066
$0
$0
$2,414,066

Last Updated 12.16.2022

+ Clark and Lake Stair Replacement Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Replace stairs at mezzanine level at Blue Line Clark and Lake Station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$650,000
$0
$0
$650,000

Last Updated 12.16.2022

+ Cottage Grove Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

CTA has partnered with the Preservation of Affordable Housing (POAH) to revitalize the southeast
corner of 63rd Street and Cottage Grove Avenue with a new multi-use office/retail space, which will
contain a new Cottage Grove station house. Overall the general design concept relocates the Cottage
Grove station house within POAH's new Woodlawn Crossing mixed-use development at the southeast
corner of 63rd Street and Cottage Grove Avenue, while the existing platforms and other related rail

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$76,447,966

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2021

End Date

May 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A contract has been awarded in January 2021 and CTA has issued a notice to proceed. The 60% design has been completed. Negotiations with POAH and City of Chicago Department of Planning and Development (CDPD) on final design for building where station entrance will be located are ongoing. POAH procured their own designer to support this project. Design is currently on hold until an agreement is reached with POAH and CDPD. CTA is exploring the option to continue design on the structural and track component of the project, as this work will be done by CTA internal forces.

Last Updated 06.22.2023

+ Irving Park Station - Escalator and Canopy Replacement Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Platform canopies and escalators will be replaced at Irving Park station on the O'Hare Blue Line. This project will address safety and state of good repair needs by replacing the worn and damaged platform
canopies at this station. Platform canopies that are in a state of disrepair allow water infiltration, which can cause damage to additional building materials and equipment and pose a safety risk to both

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$14,782,125

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Mar 2021

End Date

Aug 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The construction work has been completed. The escalators have been installed and the canopy work has reached substantial completion. Activities on final punch list items are ongoing. The project is in the close out phase.

Last Updated 01.09.2023

+ Loyola Station Red Line - Stair and Elevator Replacement Stations & Passenger Facilities Rail $2,500,000 $2,500,000

PROJECT DETAILS

Description:

Project will reconstruct or replace the existing cast-in-place concrete stairs that go from the main stationhouse to the elevated platform. Additionally, the traction elevator will be fully replaced with all new components including cab, platform, cables, motor, and controller.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,500,000
$0
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,500,000
$2,500,000
$0
$4,000,000

Last Updated 12.16.2022

+ Park & Ride Improvements Stations & Passenger Facilities System $1,500,000 $1,500,000

PROJECT DETAILS

Description:

Capital maintenance work is necessary to improve or maintain parking lots at a SOGR. Renewal work for priority locations includes concrete structure restoration, surface paving, curb and sidewalk, drainage systems, and installation of parking machines.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,500,000
$0
$1,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,500,000
$0
$1,500,000

Last Updated 12.16.2022

+ Public Address Communication Modernization & Upgrade Electrical, Signal & Communications Rail $0 $12,000,000

PROJECT DETAILS

Description:

Project will provide for the comprehensive overhaul of CTA's Public Address System to upgrade the Authority's PA system from antiquated and obsolete technology to modern digital technology with disaster recovery/business continuity solutions, increased capacity, and compliance with NFPA 130. The PA system upgrade will include the upgrade/replacement of the master head-end system at the Control Center and Backup Control Center, and remote systems at each rail station, with ancillary physical infrastructure.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$12,000,000
$12,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$12,000,000
$12,000,000

Last Updated 12.16.2022

+ Quincy Loop Station Upgrade Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

The purpose of this project is make improvements to the historic Quincy Loop station, including the addition of two elevators to make this station accessible. In addition, this project will repair, repaint and refinish interior elements throughout the stationhouse, and will also paint the exterior of the stationhouse. Lighting will be upgraded and the canopy roof will be repaired where necessary.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$731,332
$0
$0
$731,332

Last Updated 12.16.2022

+ Rail Station Communications Infrastructure Modernization Electrical, Signal & Communications Rail $0 $10,000,000

PROJECT DETAILS

Description:

Project will provide for the comprehensive rehabilitation, overhaul, and expansion of communications infrastructure at all CTA rail stations to support new and modern technologies for customer facing as well as life safety functions. The rail station communications infrastructure upgrade will include the upgrade/rehabilitaion/expansion of communications infrasturcture at each rail station, including but not limted to conduit, cabling, power sources, networking, HVAC, grounding, and other ancillary physical infrastructure.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$10,000,000
$10,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$10,000,000
$10,000,000

Last Updated 12.16.2022

+ Refresh and Renew Program Expansion Stations & Passenger Facilities Rail $3,000,000 $12,000,000

PROJECT DETAILS

Description:

Provides a heavy investment in refreshing stations and facilities every five years to promote safety, security and longevity to all CTA facilities including, but not limited to Rail Stations and Platforms, Bus Garages and Rail Shops across the system.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,000,000
$9,000,000
$12,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$3,000,000
$9,000,000
$15,000,000

Last Updated 12.16.2022

+ Rehabilitate Rail Stations - Systemwide Support Facilities & Equipment Rail $2,336,026 $2,336,026

PROJECT DETAILS

Description:

Rehabilitate Rail Stations Systemwide
- Rail Stations Program would provide an annual appropriation for much-needed rehabilitation and modernization work at existing CTA rail stations. In addition, Infrastructure’s Rail Stations Program funds could be re-appropriated to support other critical needs at rail stations as they arise and implementation of systemwide projects can be scaled dependent on funding and locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$2,336,026
$0
$2,336,026
Total
$5,925,000
$2,336,026
$0
$8,261,026

Last Updated 12.16.2022

+ Rehabilitate Rail Stations -95th Terminal Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This new job order will support the final change order for the construction firm, including the removal of several underground storage tanks near the terminal.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$625,384
$0
$0
$625,384

Last Updated 12.16.2022

+ Security Camera Modernization and Upgrade Electrical, Signal & Communications System $2,000,000 $11,568,629

PROJECT DETAILS

Description:

Project will provide for the comprehensive overhaul of CTA's CCTV Security Camera Video System to upgrade the Authority's camera and video management system and communications transport system from antiquated and obsolete technology to modern high-speed technology with disaster recovery/business continuity solutions, increased capacity, and inter-operability with City of Chicago OEMC.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,000,000
$9,568,629
$11,568,629
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$2,000,000
$9,568,629
$11,568,629

Last Updated 12.16.2022

+ Station Security Enhancements Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Station Security Enhancements Systemwide
(Safe and Secure) Initiative invests $15 million to provide for enhancements to be made to stations that include lighting, repairs, and other improvements. This multiple year effort is expected to touch over 100 stations throughout the system

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$0
$0
$3,000,000

Last Updated 12.16.2022

+ Systemwide Security Cameras Improvements (Safe & Secure) Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Systemwide Security Cameras Improvements (Safe & Secure):
Systemwide Security Cameras Safe and Secure investment of $18.0 M will add 1,000 new cameras and upgrade more than 3,800 older-model cameras throughout the system, including adding additional camera coverage to CTA-owned bus turnarounds and add monitors at all 146 CTA kiosks.

$5M Modernize cameras
$1M Install monitors at all kiosks
$4M Install cameras at all CTA owned bus turnarounds
$8M Maintain cameras in state of the art condition

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,707,200
$0
$0
$4,707,200

Last Updated 12.16.2022

+ Western Station Brown Line - Reconstruction Stations & Passenger Facilities Rail $13,200,000 $13,200,000

PROJECT DETAILS

Description:

Rehabilitation required at this station that was not part of the Brown Line Reconstruction project and has older elevators that are part of the ASAP program on replacing existing elevators.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$13,200,000
$0
$13,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$16,800,000
$13,200,000
$0
$30,000,000

Last Updated 12.16.2022

+ CTA Elevated Track and Structure Systemwide Rail $38,000,000 $190,000,000 $380,000,000 $190,000,000

Description:

Preform elevated track and structure maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Mar 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure work was completed, and final billing remains. This will be the final update on this project.

Last Updated 07.10.2022

+ 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$38,000,000
$0
$0
$38,000,000

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2022

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.

Last Updated 06.22.2023

+ 2023 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $38,000,000 $190,000,000

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$38,000,000
$152,000,000
$190,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$38,000,000
$152,000,000
$190,000,000

Last Updated 12.16.2022

+ CTA Perform Bus Maintenance Activities Bus $36,000,000 $180,000,000 $360,000,000 $180,000,000

Description:

Preform bus maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2021 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$53,365,222

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities continued in this reporting period. Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2022 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$56,000,000
$0
$0
$56,000,000

PMO:

Total Project Budget^

$36,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2021

End Date

Mar 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities for this project are on hold until the Bus Maintenance – 2021 project is fully expended. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2023 - Bus Maintenance Rolling Stock Bus $36,000,000 $180,000,000

PROJECT DETAILS

Description:

Perform Bus Maintenance Activities

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$36,000,000
$144,000,000
$180,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$36,000,000
$144,000,000
$180,000,000

Last Updated 12.16.2022

+ Purchase and Install Driver Barrier Doors for Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Retrofit approximately 740 buses removing the current polycarbonate barrier shield by installing a full top to bottom barrier door improving security while minimizing glare and anti-reflection effect. The specific fleet buses to be retrofitted will include the 1000 Series buses that are not be replaced with the current order, 4000 Series, and the 4300 Series. All new buses for the current contract and going forward will contain full door shields.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,309,417
$0
$0
$3,309,417

Last Updated 12.16.2022

+ CTA All Stations Accessibility Program Rail $189,925,938 $232,025,938 $473,900,000 $241,874,062

Description:

The purpose of this Program is to support accessibility in locations throughout the CTA system. ASAP’s emphasis is on making all platforms and stations vertically accessible so that people with mobility impairments can use the rail system. ASAP upgrades also include accessible entrances/doors, accessible routes from curbs to platforms, improved directional signage, enhanced lighting as appropriate, removal of platform obstructions, and accessible employee facilities.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ All Station Accessibility Program & Canopies at Montrose Stations & Passenger Facilities Rail $1,385,947 $1,385,947

PROJECT DETAILS

Description:

This job order will provide for the design/construction of two new elevators at the Montrose Blue Line Station. Further this project will fund replacement of canopies at Montrose station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$1,385,947
$0
$1,385,947
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,317,875
$1,385,947
$0
$7,703,822

PMO:

Total Project Budget^

$23,317,875

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Apr 2045

End Date

Nov -0001

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed for the design has been issued in May 2023. The kickoff meeting was held and the design validation is in progress.

Last Updated 06.22.2023

+ All Station Accessibility Program - Austin Station Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Rehabilitate Rail Stations - ASAP (AUSTIN)
This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.
Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$13,930,000
$0
$0
$13,930,000

PMO:

Total Project Budget^

$25,564,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 06.22.2023

+ All Station Accessibility Program - California Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project with provide for the renovation and expansion of the California Station. It will include a new platform, new emergency exist stairs and two new elevators. The station will be 100% ADA accessible. In addition, state of good repair work will be performed as part of the station renovation.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,570,000
$0
$0
$9,570,000

PMO:

Total Project Budget^

$36,000,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Feb 2022

End Date

Nov 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed has been granted to the designer in February 2022. The 60% design is underway and is expected to be submitted to CTA at the end of May. The real estate survey has been completed to determine property acquisition needs for the placement of elevators.

Last Updated 06.22.2023

+ All Station Accessibilty Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $8,916,776

PROJECT DETAILS

Description:

Funding will provide for second installment of funds to rehabilitate and/or replace elevators throughout the system. This funding along with the granted Rebuild Illinois funds provide in part for phase one of the program.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$8,916,776
$8,916,776
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$11,585,000
$0
$8,916,776
$20,501,776

PMO:

Total Project Budget^

$25,370,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jun 2022

End Date

Mar 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed for the designer has been issued in June 2022. The designer is completing site assessments and elevator inspections. An assessment report will be developed to prioritize the elevator replacement or rehabilitation locations. The report will also provide the scope of work needed for each individual elevator. A draft report is expected to be submitted to CTA in June. Once the report is finalized, CTA will issue a procurement for construction based on the priority recommendations from the assessment report.

Last Updated 06.22.2023

+ All Station Accessibilty Program - Station Design/Consultant Services (Oak Pk, Ridgeland, Irving Pk, Belmont, Grand, and Division) Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Project provides funding to complete the 100% design plan for all six targeted Stations. Additional funding will be made available to retrofit or rebuild stations to achieve make vertically accessible.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$26,000,000
$0
$0
$26,000,000

Last Updated 12.16.2022

+ All Stations Accessibility Program - Belmont Station Construction Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Fully fund Belmont O’Hare Blue.
Scope of work for this station includes:
• Maintain all existing stairways and escalators;
• Provide one elevator for access between street level and the unpaid side of the stationhouse;
• Provide one elevator for access between the paid side of the stationhouse and the platform; and
• Install and emergency stairway at the south end of platform and provide street-level exit at northeast quadrant of Barry Ave./ Kimball Ave.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

Last Updated 03.15.2023

+ All Stations Accessibility Program - Escalator Replacement Stations & Passenger Facilities System $0 $15,000,000

PROJECT DETAILS

Description:

Project will fund the replacement of a select number of escalators. CTA is currently in development of a PPS document to prioritize the replacement effort.

This program upgrades or replaces aging escalators within the system. The general scope of work includes: demolition of the existing escalator, modification of the existing
structure, and fabrication and installation of the new escalator. Stations along the Blue line
O’Hare branch have been identified as priority locations for escalator replacement.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$15,000,000
$15,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$15,000,000
$15,000,000

Last Updated 12.16.2022

+ All Stations Accessibility Program - Irving Park Station Construction Stations & Passenger Facilities Rail $113,620,000 $113,620,000

PROJECT DETAILS

Description:

Fully fund Irving Park - O’Hare Blue.
Scope of work for this station includes:
• Two new stationhouses each with a CA kiosk and elevators providing access to the north and south ends
of the platform;
• To add accessibility at this station, the existing stationhouse on the south side of Irving Park Road is
proposed to be converted to a stationhouse without a CA kiosk; and
• The stationhouse on the west side of Pulaski Road will remain unchanged.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$84,000,000
$0
$84,000,000
State
$0
$29,620,000
$0
$29,620,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$113,620,000
$0
$113,620,000

Last Updated 03.15.2023

+ All Stations Accessibility Program - Oak Park, Ridgeland, Partial Construction - Lake Green Line Stations & Passenger Facilities Rail $40,439,991 $40,439,991

PROJECT DETAILS

Description:

Partial Construction funds will provide for the Oak Park & Ridgeland Stations on the Green Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$8,925,938
$0
$8,925,938
State
$0
$31,514,053
$0
$31,514,053
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$40,439,991
$0
$40,439,991

Last Updated 03.15.2023

+ All Stations Accessibility Program - Pulaski Station Stations & Passenger Facilities Rail $34,480,000 $34,480,000

PROJECT DETAILS

Description:

The project will reconstruct the main Pulaski entrance to replace the current non-compliant ramp to platform level with one elevator and one staircase. The closed Keeler Ave. auxiliary entrance will be reopened, and the ramp will be reconstructed to meet accessibility requirements for landings, providing a redundant pathway not dependent on an elevator. All station signage will be updated for improved wayfinding. At platform level, passenger amenities such as benches or shelters, will be improved with a focus on the head car location where most passengers with disabilities ride.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$34,480,000
$0
$34,480,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$34,480,000
$0
$34,480,000

Last Updated 03.15.2023

+ All Stations Accessibility Program Phase II (ELEVATOR REPLACEMENT) Stations & Passenger Facilities System $0 $18,183,224

PROJECT DETAILS

Description:

CTA developed the Elevator Replacement Program to strategically maintain existing passenger elevators across the rail system as vertical accessibility is expanded via ASAP. The Elevator Replacement Program will rehabilitate or replace existing passenger elevators throughout the CTA rail system to reduce the backlog of elevator rehabilitation and replacement needs and bring them into a state of good repair.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$18,183,224
$18,183,224
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$18,183,224
$18,183,224

Last Updated 12.16.2022

+ CTA Radio System Upgrade Rail $0 $0 $35,000,000 $35,000,000

Description:

Replacement of obsolete radio system

No Results Found

+ CTA Rail Car Maintenance Activities Rail $0 $60,000,000 $300,000,000 $240,000,000

Description:

Preform rail car maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$27,074,655

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2020

End Date

Sep 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ 2021 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$10,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.

Last Updated 06.22.2023

+ 2022 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$18,106,390
$0
$0
$18,106,390

PMO:

Total Project Budget^

$18,106,390

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

Jun 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.

Last Updated 06.22.2023

+ 2023 - Rail Car Maintenance Rolling Stock Rail $0 $60,000,000

PROJECT DETAILS

Description:

Rail Car Maintenance Activities - CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$60,000,000
$60,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$60,000,000
$60,000,000

Last Updated 12.16.2022

+ CTA Station Communication Infrastructure Rail $0 $0 $158,800,000 $158,800,000

Description:

These are all the life safety mission critical systems which all have to be upgraded at the same time, and are all interrelated. For example the rail station commmunications infrastructure upgrades are needed by PA system, the digital signage system, cameras system, telephone system, radio system etc.

No Results Found

+ CTA BRT/Bus Slow Zone Removal/ TSP/Dedicated Lane projects System $15,200,000 $15,200,000 $231,240,000 $216,040,000

Description:

Targeted street and traffic signal improvements to increase bus speeds

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Slow Zones Elimination Program Miscellaneous Bus $15,200,000 $15,200,000

PROJECT DETAILS

Description:

This is a joint partnership with CDOT where CTA and CDOT will implement a coordinated program of bus priority treatments and targeted solutions for specific problem areas, in order to improve speed and reliability on major bus corridors. Project funds will cover final design and construction for all six routes.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$15,200,000
$0
$15,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$15,200,000
$0
$15,200,000

Last Updated 12.16.2022