Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Projectsort descending Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Maintenance Facilities Rehabilitation System $12,000,000 $60,000,000 $200,000,000 $140,000,000

Description:

Perform facilities maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$12,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Dec 2021

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements is part of an ongoing program. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. This particular part of the program is completed. This will be the final update on this project.

Last Updated 07.10.2022

+ 2021 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$20,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements are ongoing. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures.

Last Updated 06.22.2023

+ 2022 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$12,000,000
$0
$0
$12,000,000

PMO:

Total Project Budget^

$12,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2021

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements are ongoing. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures.

Last Updated 06.22.2023

+ 2023 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $12,000,000 $60,000,000

PROJECT DETAILS

Description:

Maintenance Facilities Rehabilitation:

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$12,000,000
$48,000,000
$60,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$12,000,000
$48,000,000
$60,000,000

Last Updated 12.16.2022

+ Facilities - Substation Roof Repairs Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Program would address the most immediate critical needs at CTA facilities systemwide to enable their
safe and reliable operation. The goal would be to have an annual appropriation in the CIP that would
be solely dedicated toward addressing this Program. Transit service safety and reliability is affected by
out-of-date rail, bus, and maintenance facilities.
The project will complete roof replacements at five CTA substations: Calvary, Lotus, Des Plaines,
Ashland, and O’Hare. The project will also complete exterior façade repair at the O’Hare Substation,

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,628,767
$0
$0
$3,628,767

PMO:

Total Project Budget^

$3,628,767

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Nov -0001

End Date

Nov -0001

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Design has been completed by CTA’s in-house engineering staff. The Notice to Proceed for construction was issued in March 2023. The contractor is currently working through the submittal process and getting ready to mobilize for field work.

Last Updated 06.22.2023

+ CTA Mid-Life Bus Overhaul (4300 series) Bus $0 $0 $0 $0

Description:

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Mid-Life Bus Overhaul 4300 Series Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Overhauls of the 4300 articulated buses to maintain vehicles, ensure reliability and enable to perform through full useful life

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,615,472
$0
$0
$9,615,472

PMO:

Total Project Budget^

$9,615,472

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2022

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Production meetings with the contractor begun during this reporting period and continue to happen. The setup for the first two pilot buses is ongoing and expected to be received in the next reporting period.

Last Updated 06.22.2023

+ CTA Mid-Life Bus Overhaul (7900 series) Rail $0 $74,151,466 $80,488,850 $6,337,384

Description:

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Overhaul - Mid-Life 450 Nova (7900 Series) Rolling Stock Bus $0 $74,151,466

PROJECT DETAILS

Description:

Funding will provide for the mid-life overhaul of the CTA Nova buses 7900 Series. Buses placed into service between 2014 and 2017 will receive a bus overhaul and will be returned to a state of good repair. This scheduled Mid-Life Bus Overhaul Program will allow for safe, effective operation of the buses throughout their standard estimated life of 15 years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$74,151,466
$74,151,466
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$74,151,466
$74,151,466

Last Updated 05.18.2023

+ CTA New Control and Training Center System $175,000,000 $175,000,000 $0 $0

Description:

Construct new CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ New Control & Training Center Support Facilities & Equipment System $175,000,000 $175,000,000

PROJECT DETAILS

Description:

CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$175,000,000
$0
$175,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$142,270,670
$175,000,000
$0
$317,270,670

Last Updated 03.15.2023

+ CTA Non-Revenue Vehicle Replacement Program System $2,494,359 $10,944,359 $81,741,905 $70,797,546

Description:

Replacement of vehicles needed for maintenance and operations support

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Equipment and Non-Revenue Vehicles Program Support Facilities & Equipment System $1,269,359 $7,269,359

PROJECT DETAILS

Description:

CTA plans to invest funds annually to fund the phased replacement of aged equipment and vehicles used by CTA maintenance groups that include Bus, Rail, Power & Way, and Facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,269,359
$6,000,000
$7,269,359
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,269,359
$6,000,000
$7,269,359

Last Updated 05.18.2023

+ Non-Revenue Utility Vehicle Replacement Support Facilities & Equipment System $1,225,000 $3,675,000

PROJECT DETAILS

Description:

Heavy-Duty Vehicles to support routine infrastructure maintenance, emergency repairs, and recovery operations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,225,000
$2,450,000
$3,675,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,225,000
$1,225,000
$2,450,000
$4,900,000

Last Updated 05.18.2023

+ Non-Revenue Vehicles - Diesel Locomotives Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Equipment and Non-Revenue Vehicles (Diesel Locomotives): Funding will provide for the replacement of CTA's diesel locomotive snow fighters. The self-propelled locomotives with special attachments to remove snow and ice during severe winter weather conditions are able to operate and clear system track, so that CTA can safely power up the system to restore/provide service. When traction power is down, this equipment will also be used to move rolling stock to secure locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,333,095
$0
$0
$3,333,095

PMO:

Total Project Budget^

$22,731,013

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Aug 2020

End Date

May 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The structural design was approved by the CTA. The project is in full production mode and the contractor managed to start the first engine skid during this reporting period. The first locomotive is beginning the final assembly including all of the wiring, hoses, connection plates, and controls between various parts. CTA and the contractor are coordinating a site visit for when the load testing will be performed by the contractor. If the load test passes, the contractor will commission vehicle #1 and continue the assembly of the remaining vehicles.

Last Updated 06.22.2023

+ Pace Paratransit Vehicles - Expansion Bus $0 $0 $13,000,000 $13,000,000

Description:

New Dial-a-Ride and ADA vehicles for aging population

No Results Found

+ Pace Paratransit Vehicles - Replacement Bus $2,801,859 $20,228,863 $50,825,000 $30,596,137

Description:

Replacement of vehicles reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Electric Paratransit Vehicles Rolling Stock Bus $1,000,000 $1,000,000

PROJECT DETAILS

Description:

This project will fund the purchase of electric paratransit vehicles.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$0
$1,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$0
$1,000,000

Last Updated 06.22.2023

+ Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,801,859 $19,228,863

PROJECT DETAILS

Description:

Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,801,859
$17,427,004
$19,228,863
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,567,180
$1,801,859
$17,427,004
$24,796,043

PMO:

Total Project Budget^

$69,991,388

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Nov 2015

End Date

Nov 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 118 vehicles and 24 more are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are expected to be executed in Q4-2023.

Last Updated 06.22.2023

+ Pace Pedestrian Infrastructure/Shelters/Signs Bus $0 $8,000,000 $30,500,000 $22,500,000

Description:

Shelters, pedestrian access, and completion of conversion to posted stops

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$1,550,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Oct 2020

End Date

Apr 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Activities continued on this project with Pace submitting an order for 10-15 shelters. Shelters are expected to be delivered in Q3-2023. The general contractor for concrete pads continued by applying for additional permits as well installation of pads during this reporting period.

Last Updated 06.22.2023

+ 2020 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$750,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2020

End Date

Apr 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.

Last Updated 06.22.2023

+ 2021 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$1,330,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Feb 2022

End Date

Apr 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The installation of shelters and benches is in progress. Similarly, the contractor continues to make headway with installation of concrete pads. Finally, A/E services for bus stop infrastructure continues to progress.

Last Updated 06.22.2023

+ 2021 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$600,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Feb 2022

End Date

Oct 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 06.22.2023

+ 2022 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,125,000
$0
$0
$1,125,000

Last Updated 12.16.2022

+ 2022 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$425,000
$0
$0
$425,000

Last Updated 12.16.2022

+ 2023 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $6,000,000

PROJECT DETAILS

Description:

Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, benches, and signs

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$6,000,000
$6,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$6,000,000
$6,000,000

Last Updated 12.16.2022

+ 2023 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $2,000,000

PROJECT DETAILS

Description:

Production of new electric signs and associated installation costs to provide real-time bus information to riders.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$2,000,000
$2,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$2,000,000
$2,000,000

Last Updated 12.16.2022

+ CTA Perform Bus Maintenance Activities Bus $36,000,000 $180,000,000 $360,000,000 $180,000,000

Description:

Preform bus maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2021 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$53,365,222

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities continued in this reporting period. Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2022 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$56,000,000
$0
$0
$56,000,000

PMO:

Total Project Budget^

$36,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2021

End Date

Mar 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities for this project are on hold until the Bus Maintenance – 2021 project is fully expended. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2023 - Bus Maintenance Rolling Stock Bus $36,000,000 $180,000,000

PROJECT DETAILS

Description:

Perform Bus Maintenance Activities

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$36,000,000
$144,000,000
$180,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$36,000,000
$144,000,000
$180,000,000

Last Updated 12.16.2022

+ Purchase and Install Driver Barrier Doors for Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Retrofit approximately 740 buses removing the current polycarbonate barrier shield by installing a full top to bottom barrier door improving security while minimizing glare and anti-reflection effect. The specific fleet buses to be retrofitted will include the 1000 Series buses that are not be replaced with the current order, 4000 Series, and the 4300 Series. All new buses for the current contract and going forward will contain full door shields.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,309,417
$0
$0
$3,309,417

Last Updated 12.16.2022

+ CTA Program Development System $525,000 $2,625,000 $6,250,000 $3,625,000

Description:

Provide for Program Development

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Program Development - UWP Contingencies and Administration System $525,000 $2,625,000

PROJECT DETAILS

Description:

Develop and refine CTA's capital programs for inclusion into five year regional Transportation Improvement Program. Provide support as required to finalize the current TIP. Analyze project proposals for potential inclusion in the Authority's Capital Program, presentations to the public, CTA Board and Regional Transportation Authority (RTA).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$420,000
$1,680,000
$2,100,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$105,000
$420,000
$525,000
Total
$625,000
$525,000
$2,100,000
$3,250,000

Last Updated 12.16.2022