Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Project Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Needsort descending
+ CTA Station Communication Infrastructure Rail $0 $0 $158,800,000 $158,800,000

Description:

These are all the life safety mission critical systems which all have to be upgraded at the same time, and are all interrelated. For example the rail station commmunications infrastructure upgrades are needed by PA system, the digital signage system, cameras system, telephone system, radio system etc.

No Results Found

+ CTA Rail Shops Improvements Rail $31,007,124 $89,807,124 $255,900,000 $166,092,876

Description:

Provide repair and replacement to worn components at rail maintenance shops

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 63rd Shop - Non-Revenue Equipment and Service Support Facilities & Equipment Rail $3,000,000 $3,000,000

PROJECT DETAILS

Description:

Purchase of equipment associated with 63rd Shop operations moving from Skokie to 63rd. Also, contracts for movement of existing equipment/material. This is necessary to allow use of the new shop as planned.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,000,000
$0
$3,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$3,000,000
$0
$3,000,000

Last Updated 12.16.2022

+ Improve Facilities - Diesel Locomitve Storage Shed Support Facilities & Equipment Rail $11,000,000 $11,000,000

PROJECT DETAILS

Description:

The purpose of this project is to support the expansion of CTA’s diesel-powered snow fighter locomotives via the construction of three sheds, one at each of the following locations: 98th, Midway, and Rosemont Yards to house the four new snow fighter locomotives. The sheds will fully enclose the locomotives. Work at each location provides for a pre-engineered insulated metal building structure, overhead coiling doors, plumbing, mechanical, electrical, fire alarms system, and tie-ins for sewer and electrical service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$11,000,000
$0
$11,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$11,000,000
$0
$12,000,000

Last Updated 12.16.2022

+ Midway Shop - Wheel Truing Machine Bldg. Extension and Access Track. Support Facilities & Equipment Rail $0 $13,800,000

PROJECT DETAILS

Description:

Provide railcar access from the north yard. Both cars of a railcar unit will be able to be trued without removing the unit from the shop to turn around. Allows for increased wheel truing activity, improves ride quality, and extends wheel life and track life.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$13,800,000
$13,800,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$13,800,000
$13,800,000

Last Updated 12.16.2022

+ Non-Revenue Rail Vehicle Equipment - Replacement Support Facilities & Equipment Rail $5,507,124 $15,507,124

PROJECT DETAILS

Description:

Replace various rail-borne non-revenue vehicles that have exceeded their useful lives. Repairs and spare parts have become increasingly difficult which raises maintenance costs and increases duration of downtime of this critical equipment. Equipment includes: car movers, rail borne sewer vacuum, subway washer vehicle, rail profile grinder, rail cranes, 2 locomotive crane 22 ton, 2 tie cranes w/ close clearance tie replacement head, sky trim tree trimmer, tie inserters, MKVI tamper and stabilizer.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,507,124
$10,000,000
$15,507,124
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,507,124
$10,000,000
$15,507,124

Last Updated 12.16.2022

+ Rail Car Facility Maintenance Support Facilities & Equipment Rail $1,000,000 $15,000,000

PROJECT DETAILS

Description:

Replacement of various shop facility heavy equipment that is ending their useful lives. Equipment includes: carbody hoists at Harlem, spin jacks at Rosemont and Wheel truing machine at 54th (replace with 4-axle), office space at Harlem above classroom, security gates at Kimball/54th for when rollup doors are raised, 2 man gates at DesPlaines.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$14,000,000
$15,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$14,000,000
$15,000,000

Last Updated 12.16.2022

+ Replace Non-Revenue 61st Rail Shop Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Construct a new non-revenue vehicle maintenance facility for maintenance and repair of non-revenue
equipment. Facility will also include covered storage tracks for track maintenance equipment. The
purpose of the new Non-Revenue Rail Vehicle Maintenance Facility is to provide facilities for
maintenance and repair of over 125 pieces of non-revenue equipment used for right-of-way maintenance
and other rail-mounted non-revenue vehicles.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$70,017,063

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Mar 2021

End Date

Nov 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The 61st rail shop project had most site planning activities completed. The foundations were poured, and the building enclosure erected as well as roof installed. The contractor continues to make headway with procurement of equipment related to installation of utilities such as transformers for the electrical requirements of the facility and plumbing elements. The contractor is working on design work packages for the parking lot and landscaping for the facility.

Last Updated 06.22.2023

+ Skokie Clean Room - Bench Test Equipment Miscellaneous System $0 $0

PROJECT DETAILS

Description:

Skokie Clean Room - Bench Test Equipment:
The scope of work provides for modifications to the CTA Skokie Shop (Heavy Maintenance Facility) to accommodate the addition of clean rooms. All of the necessary architectural and MEP systems would be reworked and reactivated in the expanded / modified spaces.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,400,000
$0
$0
$4,400,000

Last Updated 12.16.2022

+ Skokie Shops - Railcar Hoists Support Facilities & Equipment Rail $5,000,000 $20,000,000

PROJECT DETAILS

Description:

Construct two new Rail car body hoists where the non-revenue unit is currently situated. This unit is to move to new facility in late 2023 or early 2024. Additional space with new hoists increases the capacity to overhaul series cars. Over the next five years, CTA will need to continue the overhaul of the 5000 Series, while also addressing life extending work on existing 2600 and 3200 Series expected to remain in fleet until replacement cars are available from a future order.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,000,000
$15,000,000
$20,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,000,000
$15,000,000
$20,000,000

Last Updated 12.16.2022

+ Skokie Shops - Wheel truing machine replacement Support Facilities & Equipment Rail $4,500,000 $9,000,000

PROJECT DETAILS

Description:

Design and install new wheel truing machine.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$4,500,000
$4,500,000
$9,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$4,500,000
$4,500,000
$9,000,000

Last Updated 12.16.2022

+ Skokie Shops Improvements Other Support Facilities & Equipment Rail $1,000,000 $2,500,000

PROJECT DETAILS

Description:

Various shop improvements, including: Repurpose truck wash machine area to HVAC/truck wash, fill in truck transfer pit and install truck hi-line, add truck hi-line positions (and lighting, hose reels) in truck storage area, additional air operated 2-ton crane in Paint Booth, engineering lab, additional crane in truck shop on existing rails.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$1,500,000
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$1,500,000
$2,500,000

Last Updated 12.16.2022

+ CTA Perform Bus Maintenance Activities Bus $36,000,000 $180,000,000 $360,000,000 $180,000,000

Description:

Preform bus maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2021 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$53,365,222

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities continued in this reporting period. Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2022 - Bus Maintenance Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$56,000,000
$0
$0
$56,000,000

PMO:

Total Project Budget^

$36,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2021

End Date

Mar 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Bus maintenance activities for this project are on hold until the Bus Maintenance – 2021 project is fully expended. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.22.2023

+ 2023 - Bus Maintenance Rolling Stock Bus $36,000,000 $180,000,000

PROJECT DETAILS

Description:

Perform Bus Maintenance Activities

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$36,000,000
$144,000,000
$180,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$36,000,000
$144,000,000
$180,000,000

Last Updated 12.16.2022

+ Purchase and Install Driver Barrier Doors for Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Retrofit approximately 740 buses removing the current polycarbonate barrier shield by installing a full top to bottom barrier door improving security while minimizing glare and anti-reflection effect. The specific fleet buses to be retrofitted will include the 1000 Series buses that are not be replaced with the current order, 4000 Series, and the 4300 Series. All new buses for the current contract and going forward will contain full door shields.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,309,417
$0
$0
$3,309,417

Last Updated 12.16.2022

+ CTA Elevated Track and Structure Systemwide Rail $38,000,000 $190,000,000 $380,000,000 $190,000,000

Description:

Preform elevated track and structure maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Mar 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure work was completed, and final billing remains. This will be the final update on this project.

Last Updated 07.10.2022

+ 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$38,000,000
$0
$0
$38,000,000

PMO:

Total Project Budget^

$38,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2022

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.

Last Updated 06.22.2023

+ 2023 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $38,000,000 $190,000,000

PROJECT DETAILS

Description:

Elevated Track and Structure Systemwide

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$38,000,000
$152,000,000
$190,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$38,000,000
$152,000,000
$190,000,000

Last Updated 12.16.2022

+ CTA BRT/Bus Slow Zone Removal/ TSP/Dedicated Lane projects System $15,200,000 $15,200,000 $231,240,000 $216,040,000

Description:

Targeted street and traffic signal improvements to increase bus speeds

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Slow Zones Elimination Program Miscellaneous Bus $15,200,000 $15,200,000

PROJECT DETAILS

Description:

This is a joint partnership with CDOT where CTA and CDOT will implement a coordinated program of bus priority treatments and targeted solutions for specific problem areas, in order to improve speed and reliability on major bus corridors. Project funds will cover final design and construction for all six routes.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$15,200,000
$0
$15,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$15,200,000
$0
$15,200,000

Last Updated 12.16.2022

+ CTA Blue Line (O'Hare) Traction Power Capacity & Track Improvements Rail $0 $0 $217,940,463 $217,940,463

Description:

Upgrades and State of Good Repair projects along the O'Hare Branch of the Blue Line

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Blue Line O'Hare Branch - Special Trackwork Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Funds provide for the replacement of stock rails, switch points, frogs, switch ties, and plates on the O’Hare Line that are no longer in a state of good repair and require concentrated maintenance by CTA forces to ensure service. The component replacement will take place between the Jefferson Park interlocking and the O’Hare terminal.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,013,674
$0
$0
$2,013,674

Last Updated 12.16.2022

+ Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$12,405,159
$0
$0
$12,405,159

PMO:

Total Project Budget^

$207,100,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2018

End Date

Mar 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 06.22.2023

+ Blue Line Traction Power - Barry, Damen and Canal Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (at
Barry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on the
Blue Line. These assets will support increasing ridership demands as well as the power needed to
support 5000 and 7000 series rail cars. The location of the tie house and substations were determined
by the Blue Line Load Flow study, which identified areas that were likely to experience traction power
issues.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,200,191
$0
$0
$2,200,191

PMO:

Total Project Budget^

$122,417,171

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Oct 2021

End Date

Jan 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Construction is ongoing at Canal, Damen and Haymarket, with majority of construction forces working at Damen Substation on structural steel installation and electrical work. Substation equipment factory testing is ongoing. A change order to add the scope for the Kimball Subway Belmont crossover has been authorized. Work on the Belmont-Kimball crossover is ongoing during the weekends. There are project delays associated with underground obstructions discovered at the Damen location during micropile installations. A workaround has been developed and a new permitting application process is ongoing.

Last Updated 06.22.2023

+ Old Mannheim Replacement Foot walk Track & Structure Rail $0 $0

PROJECT DETAILS

Description:

Restore footwalk at Old Manheim on the O'Hare Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$250,000
$0
$0
$250,000

Last Updated 12.16.2022

+ Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non‐PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$12,030,427

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2022

End Date

Jan 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ CTA Rail Car Maintenance Activities Rail $0 $60,000,000 $300,000,000 $240,000,000

Description:

Preform rail car maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$27,074,655

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2020

End Date

Sep 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ 2021 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$10,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.

Last Updated 06.22.2023

+ 2022 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$18,106,390
$0
$0
$18,106,390

PMO:

Total Project Budget^

$18,106,390

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

Jun 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.

Last Updated 06.22.2023

+ 2023 - Rail Car Maintenance Rolling Stock Rail $0 $60,000,000

PROJECT DETAILS

Description:

Rail Car Maintenance Activities - CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$60,000,000
$60,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$60,000,000
$60,000,000

Last Updated 12.16.2022

+ CTA All Stations Accessibility Program Rail $189,925,938 $232,025,938 $473,900,000 $241,874,062

Description:

The purpose of this Program is to support accessibility in locations throughout the CTA system. ASAP’s emphasis is on making all platforms and stations vertically accessible so that people with mobility impairments can use the rail system. ASAP upgrades also include accessible entrances/doors, accessible routes from curbs to platforms, improved directional signage, enhanced lighting as appropriate, removal of platform obstructions, and accessible employee facilities.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ All Station Accessibility Program & Canopies at Montrose Stations & Passenger Facilities Rail $1,385,947 $1,385,947

PROJECT DETAILS

Description:

This job order will provide for the design/construction of two new elevators at the Montrose Blue Line Station. Further this project will fund replacement of canopies at Montrose station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$1,385,947
$0
$1,385,947
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,317,875
$1,385,947
$0
$7,703,822

PMO:

Total Project Budget^

$23,317,875

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Apr 2045

End Date

Nov -0001

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed for the design has been issued in May 2023. The kickoff meeting was held and the design validation is in progress.

Last Updated 06.22.2023

+ All Station Accessibility Program - Austin Station Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Rehabilitate Rail Stations - ASAP (AUSTIN)
This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.
Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$13,930,000
$0
$0
$13,930,000

PMO:

Total Project Budget^

$25,564,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 06.22.2023

+ All Station Accessibility Program - California Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project with provide for the renovation and expansion of the California Station. It will include a new platform, new emergency exist stairs and two new elevators. The station will be 100% ADA accessible. In addition, state of good repair work will be performed as part of the station renovation.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,570,000
$0
$0
$9,570,000

PMO:

Total Project Budget^

$36,000,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Feb 2022

End Date

Nov 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed has been granted to the designer in February 2022. The 60% design is underway and is expected to be submitted to CTA at the end of May. The real estate survey has been completed to determine property acquisition needs for the placement of elevators.

Last Updated 06.22.2023

+ All Station Accessibilty Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $8,916,776

PROJECT DETAILS

Description:

Funding will provide for second installment of funds to rehabilitate and/or replace elevators throughout the system. This funding along with the granted Rebuild Illinois funds provide in part for phase one of the program.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$8,916,776
$8,916,776
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$11,585,000
$0
$8,916,776
$20,501,776

PMO:

Total Project Budget^

$25,370,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jun 2022

End Date

Mar 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The Notice to Proceed for the designer has been issued in June 2022. The designer is completing site assessments and elevator inspections. An assessment report will be developed to prioritize the elevator replacement or rehabilitation locations. The report will also provide the scope of work needed for each individual elevator. A draft report is expected to be submitted to CTA in June. Once the report is finalized, CTA will issue a procurement for construction based on the priority recommendations from the assessment report.

Last Updated 06.22.2023

+ All Station Accessibilty Program - Station Design/Consultant Services (Oak Pk, Ridgeland, Irving Pk, Belmont, Grand, and Division) Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Project provides funding to complete the 100% design plan for all six targeted Stations. Additional funding will be made available to retrofit or rebuild stations to achieve make vertically accessible.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$26,000,000
$0
$0
$26,000,000

Last Updated 12.16.2022

+ All Stations Accessibility Program - Belmont Station Construction Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Fully fund Belmont O’Hare Blue.
Scope of work for this station includes:
• Maintain all existing stairways and escalators;
• Provide one elevator for access between street level and the unpaid side of the stationhouse;
• Provide one elevator for access between the paid side of the stationhouse and the platform; and
• Install and emergency stairway at the south end of platform and provide street-level exit at northeast quadrant of Barry Ave./ Kimball Ave.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

Last Updated 03.15.2023

+ All Stations Accessibility Program - Escalator Replacement Stations & Passenger Facilities System $0 $15,000,000

PROJECT DETAILS

Description:

Project will fund the replacement of a select number of escalators. CTA is currently in development of a PPS document to prioritize the replacement effort.

This program upgrades or replaces aging escalators within the system. The general scope of work includes: demolition of the existing escalator, modification of the existing
structure, and fabrication and installation of the new escalator. Stations along the Blue line
O’Hare branch have been identified as priority locations for escalator replacement.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$15,000,000
$15,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$15,000,000
$15,000,000

Last Updated 12.16.2022

+ All Stations Accessibility Program - Irving Park Station Construction Stations & Passenger Facilities Rail $113,620,000 $113,620,000

PROJECT DETAILS

Description:

Fully fund Irving Park - O’Hare Blue.
Scope of work for this station includes:
• Two new stationhouses each with a CA kiosk and elevators providing access to the north and south ends
of the platform;
• To add accessibility at this station, the existing stationhouse on the south side of Irving Park Road is
proposed to be converted to a stationhouse without a CA kiosk; and
• The stationhouse on the west side of Pulaski Road will remain unchanged.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$84,000,000
$0
$84,000,000
State
$0
$29,620,000
$0
$29,620,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$113,620,000
$0
$113,620,000

Last Updated 03.15.2023

+ All Stations Accessibility Program - Oak Park, Ridgeland, Partial Construction - Lake Green Line Stations & Passenger Facilities Rail $40,439,991 $40,439,991

PROJECT DETAILS

Description:

Partial Construction funds will provide for the Oak Park & Ridgeland Stations on the Green Line.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$8,925,938
$0
$8,925,938
State
$0
$31,514,053
$0
$31,514,053
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$40,439,991
$0
$40,439,991

Last Updated 03.15.2023

+ All Stations Accessibility Program - Pulaski Station Stations & Passenger Facilities Rail $34,480,000 $34,480,000

PROJECT DETAILS

Description:

The project will reconstruct the main Pulaski entrance to replace the current non-compliant ramp to platform level with one elevator and one staircase. The closed Keeler Ave. auxiliary entrance will be reopened, and the ramp will be reconstructed to meet accessibility requirements for landings, providing a redundant pathway not dependent on an elevator. All station signage will be updated for improved wayfinding. At platform level, passenger amenities such as benches or shelters, will be improved with a focus on the head car location where most passengers with disabilities ride.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$34,480,000
$0
$34,480,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$34,480,000
$0
$34,480,000

Last Updated 03.15.2023

+ All Stations Accessibility Program Phase II (ELEVATOR REPLACEMENT) Stations & Passenger Facilities System $0 $18,183,224

PROJECT DETAILS

Description:

CTA developed the Elevator Replacement Program to strategically maintain existing passenger elevators across the rail system as vertical accessibility is expanded via ASAP. The Elevator Replacement Program will rehabilitate or replace existing passenger elevators throughout the CTA rail system to reduce the backlog of elevator rehabilitation and replacement needs and bring them into a state of good repair.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$18,183,224
$18,183,224
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$18,183,224
$18,183,224

Last Updated 12.16.2022

+ CTA Rail Yard Improvements System $6,819,867 $6,819,867 $259,324,412 $252,504,545

Description:

Improvements to CTA Rail Yards

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Facilities Critical Needs ‐ Harlem Yard Water Tower Demolition Support Facilities & Equipment Rail $2,869,867 $2,869,867

PROJECT DETAILS

Description:

Demolotion of the Harlem Water Tower at the Harlem Yard.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$2,869,867
$0
$2,869,867
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$2,869,867
$0
$2,869,867

Last Updated 03.15.2023

+ Rail Facilities (Yards) Support Facilities & Equipment Rail $3,950,000 $3,950,000

PROJECT DETAILS

Description:

Funding will provide for the upgrades to be made to the rail yard system infrastructure including track and associated components, fire suppression, and lighting. Other facility deficiencies will be address including but not limited to: boilers, trash collection systems, roofs, windows, pavement replacement, rail hoist replacement, inspection pit rehabilitation, roof replacements, and heating and ventilation air conditioning systems. Overall this project will allow CTA to address multiple state of good repair needs at rail yard facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,950,000
$0
$3,950,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,950,000
$3,950,000
$0
$7,900,000

Last Updated 12.16.2022

+ Rail Facilities - Des Plaines Yard Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

The Rail Facilities State of Good Repair Program focuses on critical improvements at CTA rail yards, which include improvements to the yard infrastructure itself (ties, rail, fasteners, ballast, contact rail etc.) as well as the yard fire suppression systems and lighting. The Des Plaines Yard project will include the reconstruction and reconfiguration of the inner and outer lead tracks, including associated special trackwork. Replacement and reconfiguration of the special trackwork in the east yard storage, including the road crossings to the yard shops will also be completed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$22,858,137

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Mar 2022

End Date

Feb 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this project has been completed in December 2022. CTA developed a procurement package for construction and it is currently out for bid.

Last Updated 06.22.2023

+ Pace ADA ADA Regional Paratransit Program System $0 $0 $260,378,000 $260,378,000

Description:

Replacement of vehicles and radio systems for existing program. New vehicles, transfer locations and maintenance facilities for direct Pace ownership of assets for ADA service within City of Chicago

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ ADA Technology Upgrades and Transfer Centers Miscellaneous Bus $0 $0

PROJECT DETAILS

Description:

Regional ADA Paratransit Communication Technology and Transfer Locations - Projects include upgrades to the Trapeze software, TripCheck online booking and tracking, TripCheck Interactive Voice Response phone system, text/email notifications, and Ventra integration. In areas with frequent transfers, funding will be used to purchase land, build facilities, and provide amenities for riders. Pace has identified a location that is adjacent to the Northwest Transportation Center in Schaumburg that is planned to be the first of these transfer locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$20,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2020

End Date

Dec 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A Notice to Proceed was issued in February 2023 for the construction of the Northwest Transportation Center ADA Transfer Facility. The contractor is currently working on submittals, permits and is getting ready for field mobilization. Progress continues on the implementation of various technology enhancement projects. The first two phases of the Taxi Access Program have been completed and the vendor is currently working on the third phase. Activity continues on two phases of Trapeze technology enhancements to Pace’s Trapeze paratransit scheduling system. Work has progressed on enhancements to the Account Base Processing back-office system.

Last Updated 06.22.2023