Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Project Modesort ascending 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Bus Garage Improvements Bus $43,009,730 $141,009,730 $248,090,000 $107,080,270

Description:

Provide repairs at bus maintenance garages and shops

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Improve Facilities - Electric Bus Program Planning Support Facilities & Equipment Bus $28,009,730 $126,009,730

PROJECT DETAILS

Description:

CTA has committed to a full electrification of the bus fleet by 2040, providing significant air quality improvements to the region and the immediate vicinity of the garage facilities. To implement the program, the garages will need to be converted to allow for routing servicing / charging of the buses as well as new maintenance requirements. The work will generally involve significant electrical upgrades, installation of charger infrastructure, and general updates to the facility to support the conversion to an electric fleet.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$11,590,000
$98,000,000
$109,590,000
State
$0
$16,419,730
$0
$16,419,730
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$16,590,000
$28,009,730
$98,000,000
$142,599,730

Last Updated 12.16.2022

+ North Park Garage – Building Demolition Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Project will cover the building demolition and site restoration of 5323 N. Kedzie.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$177,485
$0
$0
$177,485

Last Updated 12.16.2022

+ Bus Hoist Replacement Program Support Facilities & Equipment Bus $15,000,000 $15,000,000

PROJECT DETAILS

Description:

Project will support an updated assessment of the bus hoists to determine which may need replacement, as well as design and construction for those locations. This funding will provide for the purchase and installation of bus hoists at five CTA bus garages.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$15,000,000
$0
$15,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$15,000,000
$0
$15,000,000

Last Updated 03.15.2023

+ CTA Systemwide Structural Renewal Bus $0 $17,621,610 $336,200,000 $318,578,390

Description:

State of Good Repair projects on CTA 'L' structure

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Infrastructure State of Good Repair Program Track & Structure System $0 $17,621,610

PROJECT DETAILS

Description:

Project funds will be targeted to Safety and State of Good Repair projects throughout CTA’s right-of-way infrastructure. All work planned and performed will maintain the asset(s) in proper condition through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset. Funding will provide for the replacement of ties, running rail and third rail on the elevated structure systemwide. Beyond track renewal, work will focus on key deficient structural elements that have been identified through structural inspections.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$17,621,610
$17,621,610
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$17,621,610
$17,621,610

Last Updated 12.16.2022

+ Harlem Bus Bridge Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

This project will replace the Harlem Bus Bridge at our O'Hare Line Harlem Station. The bridge removal
and reconstruction limits are from the north end of the bridge expansion joint to the south limits of the
bridge expansion joint. The work includes all removal and reconstruction of the existing bridge structure
with a new superstructure galvanized steel and bearing assemblies, concrete bridge deck, concrete
sidewalks, approach slabs, curb and gutters, drainage, expansion joint assemblies, guard rails, trash

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$39,982,424

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jul 2021

End Date

Mar 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this project has been completed in October 2022. CTA has developed a construction procurement package and it is currently out for bid.

Last Updated 06.22.2023

+ CTA Life-Extending Bus Overhaul 430 (1000 series) Bus $10,195,422 $16,932,852 $19,567,505 $2,634,653

Description:

Overhauls to maintain sufficient fleet until the first order of replacement buses is received

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Life Extending Bus Overhaul - 430 Standard (1000 Series) Rolling Stock Bus $10,195,422 $16,932,852

PROJECT DETAILS

Description:

Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$10,195,422
$6,737,430
$16,932,852
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$14,905,007
$10,195,422
$6,737,430
$31,837,859

PMO:

Total Project Budget^

$1,893,610

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2022

End Date

Oct 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The CTA Team drafted technical specs and project scope were completed and under review as of this reporting period. The team tested a new pilot Haldex air dryers on two buses.

Last Updated 06.22.2023

+ Pace Farebox System Bus $0 $0 $0 $0

Description:

Replace fareboxes that are over 20-years old

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Farebox System Replacement Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Farebox System Replacement - Over 700 fareboxes on Pace fixed route buses will be replaced, with prior PAYGO funding of $7.5M from 2020 included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,079,344
$0
$0
$3,079,344

PMO:

Total Project Budget^

$7,500,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Nov 2020

End Date

Mar 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace awarded their procurement for a new farebox system and production and delivery of the farebox equipment is ongoing. Farebox equipment continues to be installed and projected to be completed by Q1-2024.

Last Updated 06.22.2023

+ CTA Mid-Life Bus Overhaul (4300 series) Bus $0 $0 $0 $0

Description:

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Mid-Life Bus Overhaul 4300 Series Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Overhauls of the 4300 articulated buses to maintain vehicles, ensure reliability and enable to perform through full useful life

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,615,472
$0
$0
$9,615,472

PMO:

Total Project Budget^

$9,615,472

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2022

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Production meetings with the contractor begun during this reporting period and continue to happen. The setup for the first two pilot buses is ongoing and expected to be received in the next reporting period.

Last Updated 06.22.2023

+ Pace Fixed Route Buses - Electric Bus $1,920,000 $61,720,000 $374,400,000 $312,680,000

Description:

Replacement of buses reaching useful life with electric buses

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Fixed Route Electric Buses Rolling Stock Bus $1,920,000 $61,720,000

PROJECT DETAILS

Description:

Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,920,000
$59,800,000
$61,720,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$20,550,058
$1,920,000
$59,800,000
$82,270,058

PMO:

Total Project Budget^

$26,301,403

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

May 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace is also in the process of increasing the order by two additional buses, bring the total to 22 electric buses.

Last Updated 06.22.2023

+ Pace Fixed Route Buses - Expansion Bus $0 $0 $83,889,000 $83,889,000

Description:

Buses for new services

No Results Found

+ CTA Electric Bus Infrastructure Program Bus $3,580,270 $20,590,270 $291,100,000 $270,509,730

Description:

Electric bus infrastructure upgrades necessary to begin transition to electrify CTA's bus service. Full electric conversion of Chicago and 103rd Garages, Chargers installation, and 95th Substation upgrades.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Garage Electricfication - Chicago Support Facilities & Equipment Bus $3,580,270 $20,590,270

PROJECT DETAILS

Description:

The project will provide for the necessary electrical, communications, and life safety system modernization at the Chicago Bus Garage to support the ongoing fleet conversion. This is a share of funding necessary for full upgrade to modify the Chicago Avenue bus garage. When engineering assessment and design criteria are complete, construction work can proceed with the first of CTA system bus garages. Order of magnitude estimate for Chicago Garage work is $100.0M, complete estimate will come from the engineering assessment.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$17,010,000
$17,010,000
State
$0
$3,580,270
$0
$3,580,270
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$22,993,064
$3,580,270
$17,010,000
$43,583,334

Last Updated 12.16.2022

+ Pace Fixed Route Buses - Replacement Bus $0 $9,750,000 $79,300,000 $69,550,000

Description:

Replacement of buses reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase 40' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$41,786,531

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2019

End Date

Nov 2020

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.

Last Updated 07.10.2021

+ Fixed Route CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Replacement CNG buses - Pace plans to replace 115 diesel buses with 40' Compressed Natural Gas (CNG) buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the future Northwest Division garage in Wheeling, currently being designed as a CNG fueling facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$28,050,000
$0
$0
$28,050,000

Last Updated 12.16.2022

+ Fixed Route Coach Buses Rolling Stock Bus $0 $9,750,000

PROJECT DETAILS

Description:

Coach Buses - Pace plans to replace 13 40' diesel coach buses, including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for the I-55 Bus on Shoulder service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$9,750,000
$9,750,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$9,750,000
$9,750,000

Last Updated 12.16.2022

+ Purchase 30' Diesel Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

This project is a new contract awarded in September 2019 for a new five‐year
indefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. The
minimum quantity to be purchased under this contract is 67 buses and the total
number of buses procured will not exceed the maximum amount of 164.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$80,261,908

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2019

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia.

Last Updated 06.22.2023

+ Purchase 40' Low-Floor CNG Buses Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Pace will purchase 40FT CNG Buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$75,896,625

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Mar 2022

End Date

Mar 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses.

Last Updated 06.22.2023

+ Pace Improve Passenger Facilities - Park-n-Ride Lots Bus $0 $0 $7,450,000 $7,450,000

Description:

Updates and repairs to Park-n-Ride lots

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-55 Park-n-Rides Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,750,000
$0
$0
$6,750,000

Last Updated 12.16.2022