Replace Bridges - 18th to 55th - RID

Back to Regional Capital ProgramView Regional Capital Projects Dashboard

Replace Bridges - 18th to 55th - RID

Agency
Metra
Asset Category
Track & Structure
Mode
Rail
2023 Funding
$0
2024-2027 Funding
$0
PMO

Project Map More info

Project Description

Phase 1 and 2 design and construction are complete. The Phase 3 design task was
issued an NTP in August 2018. The Phase 3 design was completed in July 2019. The
Phase 3 construction contract and construction management contract were both
awarded in September 2020. Construction started with site work in March 2021
and is ongoing. Current activities are related to obtaining permits. The estimated
project completion date for construction is December 2021 to allow enough time
for phase 3 construction.