Year Project Title Program Project Type Project Partner Budget Funding Source(s) Statussort descending
+ 2024 Harvard Pace Route Access Improvements - Route 173 Access to Transit Program Pedestrian Access to Transit Harvard $55,000
  • RTA
Programmed

PROJECT DETAILS

Related Reports

Other Resources

Description

The RTA has awarded $55,000 to the City of Harvard for Phase I engineering needed for pedestrian access improvements along Illinois Route 173 from Marengo Road to US Route 14, including new sidewalks, ADA crosswalks, and pedestrian access over Mokeler Creek. Currently, there are no sidewalks along Route 173, forcing pedestrians to walk on the shoulder. At the crossing of Mokeler Creek, pedestrians have to walk in the travel lanes of Route 173 to get over the creek.

Current Activities

 Phase I engineering plans have been submitted to IDOT. Working with IDOT on Final Approval.

Funding Amounts by Source

Source Amount
RTA
$55,000
Last Updated 08.18.2023
+ 2024 Harvey Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Harvey $55,000
  • RTA
Programmed

PROJECT DETAILS

Related Reports

Other Resources

Description

The RTA has awarded $55,000 to the City of Harvey to complete Phase I engineering required for improvements along Broadway Avenue in downtown Harvey. The project will include transit access improvements such as bus shelters, pedestrian improvements including ADA-compliant intersections, and new roadway bike facilities. These improvements will better provide for a multi-modal downtown Harvey and will connect the new Pace Harvey Transportation Center with Broadway Avenue.

Current Activities

Engineering firm has been selected. City is working to move design forward.

Funding Amounts by Source

Source Amount
RTA
$55,000
Last Updated 07.06.2023
+ 2024 Maywood Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Maywood $44,000
  • RTA
Programmed

PROJECT DETAILS

Related Reports

Other Resources

Description

The RTA has awarded $44,000 to the Village of Maywood for Phase I engineering needed for a covered bicycle shelter near the 5th Avenue Metra station served by the Union Pacific West line, heated bus shelters along 5th Avenue as served by Pace, wayfinding signage for the train station, and pavement marking improvements.

Current Activities

Maywood is in the process of selecting a firm to perform the Phase I Engineering.

Funding Amounts by Source

Source Amount
RTA
$44,000
Last Updated 08.18.2023
+ 2024 Ford Heights Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Ford Heights $53,628
  • RTA
Programmed

PROJECT DETAILS

Related Reports

Other Resources

Description

The RTA has awarded $53,628 to the Village of Ford Heights for Phase I engineering needed to improve the sidewalk network, add concrete pads to select bus stops, and install ADA-compliant crosswalks at key intersections surrounding the Pace Route 357. The bus route runs through the center of the village and forms a loop around the future 60-acre mixed-use New Town Center development. There are currently significant gaps in the sidewalk network that connects these surrounding areas with bus stops, and most crosswalks in the area are faded and are not ADA-compliant.

Current Activities

Ford Heights has selected a firm to perform Phase I Engineering and held an IDOT kickoff meeting. Coordination with Pace will begin in the 3rd quarter 2023.

Funding Amounts by Source

Source Amount
RTA
$53,628
Last Updated 08.18.2023
+ 2022 Prospect Heights Pace and Metra Improvements Access to Transit Program Pedestrian Access to Transit Prospect Heights $1,870,123
  • RTA
  • Local
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will construct new sidewalk on the east side of Wolf Road between the Prospect Heights Metra station and Willow Road. This will connect to a previous phase of the multi-use path on Wolf Road that goes north from Willow Road to Palatine Road. The project also includes the installation of pedestrian signals at Camp McDonald Road.

Current Activities

Final Plans submitted to IDOT. Plans will need to be resubmitted after land acquisition is complete and letting date confirmed. Targeting a November 2023 letting.

Funding Amounts by Source

Source Amount
RTA
$89,347
Local
$284,678
Federal
$1,496,098
Last Updated 08.18.2023
+ 2016 Oak Forest Metra Station and Pace Route Improvements Access to Transit Program Pedestrian Access to Transit Oak Forest $564,887
  • RTA
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

Improvements to the Oak Forest station area include improving sidewalk connectivity, signage, ADA accessibility, and pedestrian lighting. Access to eight Pace bus stops on Route #383 will also be improved.

Current Activities

The City is in the process of securing construction easements. Constructions agreements have been submitted to IDOT.

Funding Amounts by Source

Source Amount
RTA
$112,977
Federal
$451,910
Last Updated 07.06.2023
+ 2020 Niles Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Niles $795,721
  • RTA
  • Local
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will construct sidewalk infill along Golf Road and Milwaukee Avenue in Niles, near the Golf Mill Shopping center, a major transfer center for Pace. Both Golf Road and Milwaukee Avenue are principal arterials currently without complete sidewalks and the new sidewalk will vary in width between 5 and 7 feet. The section of Golf Road will complete sidewalks from Milwaukee Avenue going east and will comprise nearly 4,000 linear feet in new sidewalk. The Milwaukee Avenue sidewalk improvements will be from Golf Road going southwest and will comprise nearly 2,400 feet of sidewalk infill. A new crosswalk with pedestrian signal and push button will be also installed across Milwaukee Avenue at the Golf Mill main entrance.

Current Activities

Phase II Engineering kicked off. Final PS&E expected to go to IDOT August 2023.

Funding Amounts by Source

Source Amount
RTA
$79,572
Local
$79,572
Federal
$636,577
Last Updated 07.07.2023
+ 2020 North Chicago Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit North Chicago $517,694
  • RTA
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will create pedestrian access improvements to Pace bus stops located at Route 137 and Lewis Avenue in North Chicago, at the Lovell Federal Healthcare Center. The project includes new crosswalks, the removal of curbed signal islands and repaving where the curbed islands stand, installation of ADA compliant curbing and sidewalks, a section of retaining wall, a new bus shelter and pad, advanced prismatic pavement markings and signage, and signal modifications to include advanced audible countdown pedestrian heads at all legs of the intersection.

Current Activities

The City is in the process of securing a firm to do Phase II Engineering.

Funding Amounts by Source

Source Amount
RTA
$103,539
Federal
$414,155
Last Updated 07.06.2023
+ 2022 Evanston Pace and CTA Route Access Improvements Access to Transit Program Pedestrian Access to Transit Evanston $300,481
  • RTA
  • Local
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will convert all of the bus stops in the City of Evanston from flagged to posted stops and include the installation of ADA compliant bus stop pads. In addition, this project will install shelters, pedestrian signals, truncated domes, and new and replaced sidewalk to further enhance the new bus stops. Shelters are proposed for stops with 20 average daily boardings.

Current Activities

Evanston is considering moving forward with this project outside of the CMAQ program due to engineering requirements. 

Funding Amounts by Source

Source Amount
RTA
$30,048
Local
$30,048
Federal
$240,385
Last Updated 08.18.2023
+ 2020 Blue Island Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Blue Island $469,000
  • RTA
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will construct access improvements along Irving Avenue adjacent to the Vermont Street Metra station to improve the safety for people walking and biking to the station. Irving Avenue will be reconfigured and reconstructed between New Street and Vermont Street for one-way northbound traffic, including the construction of a sidewalk to provide pedestrian connections and parkway beautification elements. New on-street bike lanes along Irving Avenue will included to connect to the Cal Sag Regional Trail.

Current Activities

Phase I engineering is complete.

Funding Amounts by Source

Source Amount
RTA
$93,800
Federal
$375,200