Planning

Planning Programs and Projects

Download RTA Programs and Projects Dataset

 

This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus. 

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

 

Search More info

Filter

Year Project Title Programsort descending Project Type Project Partner Budget Funding Source(s) Status
+ 2022 University Park Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit University Park $50,000
  • RTA
Completed

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will fund Phase I engineering needed for a side path that will connect the University Park Metra Station to the I-57 Industrial Corridor. This project will complete a multimodal connection between transit and a growing employment center, making it easier and more safe for workers to access jobs via transit.

Current Activities

Project is complete

Funding Amounts by Source

Source Amount
RTA
$50,000
Last Updated 01.18.2023
+ 2014 Rolling Meadows Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Rolling Meadows $1,216,500
  • RTA
  • Federal
Completed

PROJECT DETAILS

Related Reports

Other Resources

Description

This project provides new sidewalks, crosswalks, and pedestrian signal heads along a one-and-a-half mile section of Golf Road, improving access to three Pace fixed routes that operate on the corridor (#209, #606, and #757). Several major employers are located on this corridor and it has also been chosen by Pace as a potential Arterial Rapid Transit (ART) route.

Current Activities

Construction completed in summer of 2017.

Funding Amounts by Source

Source Amount
RTA
$243,000
Federal
$973,500
Last Updated 02.16.2021
+ 2022 Northbrook Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Northbrook $200,863
  • RTA
  • Local
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will install new shared lane markings (AKA sharrows), allowing the Village to implement low-cost recommendations from its Master Bicycle and Pedestrian Plan. The project also includes installation of covered bike parking and wayfinding at the Northbrook Metra station.

Current Activities

 Phase II engineering has been completed. Notice to Proceed issued for construction. Once bicycle shelters are delivered, construction will begin.

Funding Amounts by Source

Source Amount
RTA
$20,086
Local
$20,086
Federal
$160,691
Last Updated 10.11.2023
+ 2022 Berkeley Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Berkeley $50,000
  • RTA
Completed

PROJECT DETAILS

Related Reports

Other Resources

Description

This project funds Phase I engineering necessary for future sidewalk network improvements that will provide access from residential neighborhoods south of St. Charles Road to Pace Bus Route 313. Engineering will be completed for sidewalk gaps along Lee Boulevard, Morris Avenue, Rohde Avenue, Spencer Avenue, and Jerele Boulevard.

Current Activities

Project has been completed.

Funding Amounts by Source

Source Amount
RTA
$50,000
Last Updated 06.26.2023
+ 2022 Sauk Village Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Sauk Village $50,000
  • RTA
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will fund Phase I engineering necessary for sidewalk, crosswalk, and other intersection improvements along Sauk Trail and Torrence Avenue. Future improvements will fill sidewalk gaps and make ADA and safety related improvements at key intersections along Pace Bus Route 358.

Current Activities

Phase I Engineering consultant has been selected and work is underway.

Funding Amounts by Source

Source Amount
RTA
$50,000
Last Updated 08.18.2023
+ 2016 Chicago Ridge Metra Station and Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Chicago Ridge $998,239
  • RTA
  • Federal
Completed

PROJECT DETAILS

Related Reports

Other Resources

Description

The project funds pedestrian-related improvements along Ridgeland Avenue between 102nd and 111th Streets, which is served by the Chicago Ridge Metra station and Pace Route 384. Improvements include a new crosswalk, pedestrian signal countdowns, pavement striping, pedestrian railroad safety gates, ornamental lighting, way-finding signs, and bike racks.

Current Activities

Project completed.

Funding Amounts by Source

Source Amount
RTA
$199,647
Federal
$798,592
Last Updated 10.17.2022
+ 2024 Ford Heights Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Ford Heights $53,628
  • RTA
Programmed

PROJECT DETAILS

Related Reports

Other Resources

Description

The RTA has awarded $53,628 to the Village of Ford Heights for Phase I engineering needed to improve the sidewalk network, add concrete pads to select bus stops, and install ADA-compliant crosswalks at key intersections surrounding the Pace Route 357. The bus route runs through the center of the village and forms a loop around the future 60-acre mixed-use New Town Center development. There are currently significant gaps in the sidewalk network that connects these surrounding areas with bus stops, and most crosswalks in the area are faded and are not ADA-compliant.

Current Activities

Phase I Engineering is underway.

Funding Amounts by Source

Source Amount
RTA
$53,628
Last Updated 10.31.2023
+ 2016 Evanston CTA and Metra Main Street Stations Bicycle Parking Access to Transit Program Pedestrian Access to Transit Evanston $70,000
  • RTA
  • Federal
Completed

PROJECT DETAILS

Related Reports

Other Resources

Description

This project included the purchase and installation of a total of 40 bike parking facilities on three new concrete pads around the CTA and Metra Main Street Stations.

Current Activities

Construction on the project and installation of the bike racks was completed in fall of 2017. Improvements include increased access to the Metra and CTA Main Street stations, CTA #205 and Northwestern University Intercampus Shuttle bus routes. The bike parking facilities improve access to these transit stations, in addition to business and commercial districts along Chicago Avenue and Main Street. Moreover, this project complements the City of Evanston's other efforts to encourage alternative transportation use.

Funding Amounts by Source

Source Amount
RTA
$14,000
Federal
$56,000
Last Updated 06.26.2023
+ 2022 Calumet Park Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Calumet Park $264,126
  • RTA
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will construct bicycle facilities along 124th Street to better facilitate safe access between bus transit services along Halsted Street to the Ashland Metra station at Ashland Avenue. Additional improvements include completing a sidewalk gap on 124th Street between Laflin and Bishop Streets and pedestrian improvements to the intersection of 124th Street and Laflin Street.

Current Activities

After a period of delays, the Phase II engineering has resumed.

Funding Amounts by Source

Source Amount
RTA
$52,825
Federal
$211,301
Last Updated 10.11.2023
+ 2018 Northlake Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Northlake $229,920
  • RTA
  • Local
  • Federal
In Progress

PROJECT DETAILS

Related Reports

Other Resources

Description

This project will repair a gap in the sidewalk connectivity along Wolf Road near North Avenue. Repairs will allow pedestrians to directly cross the intersection of Wolf Road and an access driveway to a shopping center. This section of Wolf Road is served by Pace Route 309 and Routes 318 and 320 operate nearby on North Avenue. Two bus shelters will also be constructed at the stops just to the south of this intersection as part of the project.

Current Activities

Consultant has been selected to complete Phase II Engineering. Waiting for IDOT to approve the engineering agreement.

Funding Amounts by Source

Source Amount
RTA
$11,496
Local
$34,488
Federal
$183,936
Last Updated 04.20.2023