Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode 2024 Funding Sort descending 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Replacement Bus Purchase (4300 series) - Electric Buses Rail $0 $0 $140,000,000 $140,000,000

Ongoing need to replace diesel articulated buses as they age with electric buses.

+ CTA Blue Line (O'Hare) Traction Power Capacity & Track Improvements Rail $0 $0 $215,740,272 $215,740,272

Upgrades and State of Good Repair projects along the O'Hare Branch of the Blue Line

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ Blue Line Traction Power - Barry, Damen and Canal Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (atBarry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on theBlue Line. These assets will support increasing ridership demands as well as the power needed tosupport 5000 and 7000 series rail cars. The location of the tie house and substations were determinedby the Blue Line Load Flow study, which identified areas that were likely to experience traction powerissues.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,200,191 $0 $0 $2,200,191

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$122,417,171
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor during this reporting worked out of sequence to reduce the delays to the project. Construction continues at Damen, Barry and Canal Tie House. Community notices are being put together for the Haymarket elevated work, which includes installing and testing the grounding system as well as steel mesh installation at track level. ComEd coordination meetings have begun for power sources.

Last Updated 04.15.2024

+ Blue Line O'Hare Branch - Special Trackwork Track & Structure Rail $0 $0

Project Details

Description
Funds provide for the replacement of stock rails, switch points, frogs, switch ties, and plates on the O’Hare Line that are no longer in a state of good repair and require concentrated maintenance by CTA forces to ensure service. The component replacement will take place between the Jefferson Park interlocking and the O’Hare terminal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,013,674 $0 $0 $2,013,674

Last Updated 12.16.2022

+ Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,030,427
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Old Mannheim Replacement Foot walk Track & Structure Rail $0 $0

Project Details

Description
Restore footwalk at Old Manheim on the O'Hare Line.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $250,000 $0 $0 $250,000

Last Updated 12.16.2022

+ CTA Blue Line Forest Park Modernization - Phase 1 Rail $0 $0 $131,245,158 $131,245,158

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Forest Park: Phase 1 - Trackwork Halsted to IMD Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to Illinois Medical District (IMD), an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $43,497,351 $0 $0 $43,497,351

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$124,596,980
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor submitted a request for substantial completion for the date of 12/8/23. CTA has performed a walkthrough and generated a punchlist. Contractor continues with punchlist work. Fence enclosure, barrier wall, and downspouts were completed. Fiber optic splicing and testing is ongoing.

Last Updated 04.15.2024

+ Forest Park: Phase 1 - Racine Station and Morgan Substation & Hermitage Traction Power Improvements Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $67,471,237 $0 $0 $67,471,237

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$97,080,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
FHP heavy mobilization is expected to begin in late April 2024 at the new laydown location at Leavitt and Lake. Heavy mobilization is expected to involve FHP’s construction materials, construction trailers and equipment. FHP plans on having their first 54-hour line cut that is scheduled for April 26, 2024, with May 3, 2024, being a backup date as contingency. During this line cut, FHP expects to perform steel erection at Racine Station and Morgan house. FHP has requested a TAO (Track Access Occurrence) that allows manpower to work without ROW (Right of Way) training due to the complete power shut down and no train service in the work zone. The line cut work zone will extend between UIC Halsted and IMD and will be supported by CTA bus shuttles in the area. The dates are contingent on steel fabrication and submittal approvals. Morgan steel fabrication is in the final stages and currently undergoing the galvanizing stage. Racine is currently being fabr

Last Updated 12.14.2023

+ Forest Park: Phase 1 - Advance Utility Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch.This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine,advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. Thiswork will enhance service quality via speed, reliability, and comfort, and improve operational efficiency onthe Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,396,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractors for all four surveys completed their work during this reporting period and two are in final comments. Invoicing continues and all four contracts are considered to be in financial closeout. This will be the last update on this project.

Last Updated 12.14.2023

+ CTA Blue Line Forest Park Modernization - Phase 2 Rail $0 $0 $653,077,000 $653,077,000

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

+ CTA Green Line Improvements Rail $0 $0 $645,293,069 $645,293,069

Track, structural, station, and power improvements

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Green Line Improvements - Station Repairs to Green West and South Track & Structure Rail $0 $0

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs.This funding will improve Green line infrastructure including track, substations, traction power cable replacements, stations, and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,447,966 $0 $0 $1,447,966

Last Updated 12.16.2022

+ Green Line Jackson Park Branch Trackwork Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,855,446
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.

Last Updated 12.14.2023

+ Green Line - Lake Street Bridge Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs.This funding would support track improvements on both sides of the Lake Street Bridge, which isscheduled to be completely replaced by the Chicago Department of Transportation in 2023. The scopeof the project will include: improve the curve geometry on the east side of the bridge; replace thetimber ties and rail fasteners, install new gauge planking, replace equipment at both the east and westturnouts, and replace structural steel framing for the three side platforms adjacent to the track.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,025,296
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for the designer was issued in February 2022. The design activities are nearing completion. Coordination efforts with CDOT are ongoing. Once the CTA design is completed it will be on hold until CDOT finishes their portion of the design in order to align the timeline for construction activities.

Last Updated 12.14.2023

+ Lake Street Line (Track and Structure) Track & Structure Rail $0 $0

Project Details

Description
Track renewal work focusing on the Lake Street elevated tracks from Ada Street to the Abutment West of Laramie Avenue. This work builds upon the recent track renewal work completed from Harlem to Laramie Avenue.The specific area of work within this segment of track will be determine based on funding availability and the condition of track. This provides for the initial installment of funds that are required for a significantly larger investment to complete work. Additional phased funding will be required to complete the entire segment of Track.Scope includes replacement of ties, fasteners, timber guards, contact rail chairs, footwalks, handrails, track planking, selective running and contact rail, including at special trackwork and the middle track locations. The scope also includes improved curve geometry, running rail grinding, and incidental signal/traction power work. Lake Street
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,408,000 $0 $0 $11,408,000

Last Updated 12.16.2022

+ Englewood Racine Green Line Station Feasibility Study (EPI) Track & Structure Rail $0 $0

Project Details

Description
Study to determine the possiblity of reopening the Green Line Racine Station in Englewood
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,778,500 $0 $0 $2,778,500

Last Updated 12.14.2023

+ Green Line Improvements - 59th Junction Track & Structure Rail $0 $0

Project Details

Description
Replacement of special track work and adjacent mainline trackwork at Green Line 59th Junction. Rehab of track surves over the Dan Ryan Expressway, and rehabilitation of track on adjacent bridges over the Norfolk Southern and Metra Train lines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $21,911,108 $0 $0 $21,911,108

Last Updated 03.15.2023

+ CTA Red Line Improvements Rail $0 $0 $396,400,000 $396,400,000

Upgrades and State of Good Repair projects along the Red Line

+ CTA Brown Line Improvements Rail $0 $0 $436,384,000 $436,384,000

Upgrades and State of Good Repair projects along the Brown Line

+ CTA Systemwide Track Renewal Rail $0 $0 $396,611,635 $396,611,635

Track improvements to address the most immediate critical track needs throughout the CTA rail system

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Rehabilitate Blue Line - Kimball Subway Waterproofing Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $961,000 $0 $0 $961,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,824,710
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 12.14.2023

+ Green & Pink Line West - Track Improvements Track & Structure Rail $0 $0

Project Details

Description
Green & Pink Line West - Track Improvements (GTT) Tower 18 to the Paulina Connector- Preserve the integrity of Lake St Elevated tracks through replacement of ties, fasteners, footwalks, improved curve geometry, and rail grinding as well as replacing the top flange as necessary.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,308,465 $0 $0 $1,308,465

Last Updated 12.16.2022

+ Red & Blue Line Subway - Track Improvements Track & Structure Rail $0 $0

Project Details

Description
Red & Blue Line Subway - Track Improvements (GTT) - Dearborn Subway Water Management and Track Improvements - This is a targeted project to replace assets that have been deteriorated by water infiltration. Work includes replace select rail, rail fasteners and direct fixation concrete ties, grind 100% of the running rail, and select drainage improvements
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,639,070 $0 $0 $5,639,070

Last Updated 12.16.2022

+ Nagle Curve Improvements Track & Structure Rail $0 $0

Project Details

Description
This project includes removing and replacing existing rail in the Nagle Curve area on the O’Hare Branch of the Blue Line. Project replaces the existing rail with new continuous welded rail at Nagle Curve. The new rail will be set into the existing plates with 100% replacement of double studded pads, heavy duty insulators, and pandrol e-clips. Work also includes a track survey to record the track geometry (profile, alignment, cross level and gauge), clearances, and the location of the track.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $75,004 $0 $0 $75,004

Last Updated 12.16.2022

+ Congress Blue Line - P1 Track Track & Structure Rail $0 $0

Project Details

Description
The project includes various priority trackwork on the Blue Line Congress branch.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,500,000 $0 $0 $2,500,000

Last Updated 12.16.2022

+ Third Rail Isolation Demonstration Project Track & Structure Rail $0 $0

Project Details

Description
CTA utilizes an exposed third rail system to provide power to trains on all revenue and non-revenue tracks. The third rail is typically installed on insulator chairs spaced eight feet apart just outside one of the running rails. CTA's rail cars utilize a “gravity shoe” to collect 600 Volts DC from the top surface of the third rail. In station areas, the third rail is typically located on the opposite side of the track from the station platform – this provides some level of protection from a person falling off the platform and coming in contact with the electrified third rail. Unfortunately, there are incidences when a passenger falls off the platform with sufficient momentum to reach the far side of the track and make contact with the third rail. This proposed project will add additional safety features on the third rail in the vicinity of station platforms.Funding will provide for two technologies: the Third Rail Isolation System and the Third Rail Side Guards (sideboards).The first feature is a safety feature proposed to include the isolation of the third rail through the stations such that when no train is approaching or present at the station, the third rail would be de-energized. This additional feature would include a control device to energize the third rail in the station, and by-pass cables to carry current around the station to feed the third rail outside the station.The second feature would include non-conductive side boards on both sides of the third rail which would reduce the likelihood of a person making contact with the rail. The sideboards would also provide an opportunity to apply warning labels directly on the third rail so as to better direct passengers to the hazard posed by this element. The sideboards would also provide a layer of protection for CTA employees that are required to walk alongside the third rail during maintenance activities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,478,864 $0 $0 $1,478,864

Last Updated 12.16.2022

+ Congress Line (Fast Tracks) Track & Structure Rail $0 $0

Project Details

Description
This project will replace rails, bars, plates, and address causes of water infiltration in Dearborn Subway between LaSalle and south portal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,024,058 $0 $0 $7,024,058

Last Updated 12.16.2022

+ DC Breakers (Fast Tracks) Track & Structure Rail $0 $0

Project Details

Description
This project will replace DC breakers in Sacramento, Franklin, and Nagle Substations. This DC breaker replacement may require some changes to the organization of other equipment inside the substation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,571,295 $0 $0 $6,571,295

Last Updated 12.16.2022

+ CTA Systemwide Structural Renewal System $0 $100,000,000 $336,200,000 $236,200,000

State of Good Repair projects on CTA 'L' structure

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Harlem Bus Bridge Track & Structure Bus $0 $0 ✔︎

Project Details

Description
This project will replace the Harlem Bus Bridge at our O'Hare Line Harlem Station. The bridge removaland reconstruction limits are from the north end of the bridge expansion joint to the south limits of thebridge expansion joint. The work includes all removal and reconstruction of the existing bridge structurewith a new superstructure galvanized steel and bearing assemblies, concrete bridge deck, concretesidewalks, approach slabs, curb and gutters, drainage, expansion joint assemblies, guard rails, trashenclosures, pedestrian shelters, electrical I LED lighting, signage, pavement stripping, and curb lanepainting.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$39,982,424
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed in October 2022. CTA has developed a construction procurement package and it is currently out for bid.

Last Updated 12.14.2023

+ Infrastructure State of Good Repair Program Track & Structure System $0 $100,000,000

Project Details

Description
Project funds will be targeted to Safety and State of Good Repair projects throughout CTA’s right-of-way infrastructure. All work planned and performed will maintain the asset(s) in proper condition through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset. Funding will provide for the replacement of ties, running rail and third rail on the elevated structure systemwide. Beyond track renewal, work will focus on key deficient structural elements that have been identified through structural inspections.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $90,100,000 $90,100,000
State $0 $0 $9,900,000 $9,900,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $100,000,000 $100,000,000

Last Updated 12.14.2023

+ CTA Subway Life Safety Improvements Rail $0 $18,000,000 $604,309,000 $586,309,000

Upgrade to existing subway ventilation equipment

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Subway Life Safety Track & Structure Rail $0 $18,000,000

Project Details

Description
Further planning and assesment is needed, but will use Call for Projects as basis to detailing specific plan. Some items to assess with budget are, but not limited to:• Ventilation improvements• Vent shaft grate replacements• Subway pumps and controls rehabilitation• Subway emergency egress footwalks• LED lighting improvements• Emergency Light Feed (ELF) upgrades• Subway sewer restoration
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $18,000,000 $18,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $18,000,000 $21,000,000

Last Updated 12.14.2023

+ Subway Underground Underwater Emergency Exit Track & Structure Rail $0 $0

Project Details

Description
The vision for this project is to secure CTA’s underground and underwater tunnel subway system and emergency exits by leveraging technology to fill the security deficiencies in the physical tunnel infrastructure that otherwise would be prohibitively expensive and improbable to achieve with humans. The goal is to create a comprehensive yet sustainable solution that ultimately prevents, detects, tracks, authorizes, and responds to all human activity in the restricted, non-public areas of the tunnels.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,874,906 $0 $0 $1,874,906

Last Updated 12.14.2023