Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode Sort descending 2024 Funding 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Elevated Track and Structure Systemwide Rail $9,595,891 $38,383,564 $380,000,000 $341,616,436

Preform elevated track and structure maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.

Last Updated 12.14.2023

+ 2020 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure work was completed, and final billing remains. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ 2023 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas:Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system.Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work.

Last Updated 12.14.2023

+ 2024 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $9,595,891 $38,383,564

Project Details

Description
Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $9,595,891 $28,787,673 $38,383,564
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $9,595,891 $28,787,673 $38,383,564

Last Updated 12.14.2023

+ CTA Railcar Purchase Rail $187,816,008 $421,404,494 $1,166,014,395 $744,609,901

Replacement of 2600- and 3200-series rail cars

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Purchase Rail Cars - 7000 Series (Base Order 400) Rolling Stock Rail $61,950,715 $77,284,911 ✔︎

Project Details

Description
Purchase Rail Cars - 7000' Series (Base Order 400) - Program funds will provide for the continued cash needs and obligation provisions as identified in the contract documents for the 7000' series rail car Base contract order of 400 cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $46,950,715 $15,334,196 $62,284,911
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $15,000,000 $0 $15,000,000
Total $99,186,582 $61,950,715 $15,334,196 $176,471,493

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$713,703,634
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Status conferences continued with CRRC to address/track various items. Revenue service testing ended and production deliveries begun in this reporting period. CTA inspection personnel continue working in China and continue to conduct welded subassembly checks and production car body shell inspections for production cars. There are approximately 62 car body shells in various states of assembly. Final assembly continues on 74 cars in the US. CTA has accepted 48 of the cars thus far for revenue service.

Last Updated 12.14.2023

+ Purchase Rail Cars - 9000 Series Rolling Stock Rail $110,493,337 $211,711,351

Project Details

Description
Funding to acquire new 9000-Series rail cars, CTA anticipates the contract will consist of a Base Order to purchase 300 cars and option(s) for an additional 246 cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $103,093,337 $80,688,996 $183,782,333
State $0 $7,400,000 $20,529,018 $27,929,018
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $101,506,663 $110,493,337 $101,218,014 $313,218,014

Last Updated 12.14.2023

+ Purchase Rail Cars - 7000 Series Options Rolling Stock Rail $15,371,956 $132,408,232

Project Details

Description
Provides for initial cash needs and obligation anticipated for the Option(s) order to procure up to an additional 256 new 7000' series rail cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $15,371,956 $78,969,503 $94,341,459
State $0 $0 $38,066,773 $38,066,773
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $15,371,956 $117,036,276 $132,408,232

Last Updated 12.14.2023

+ CTA Railcar Overhauls Rail $11,899,057 $198,594,174 $491,053,968 $292,459,794

Quarter-life overhaul of 5000-series rail cars and life-extending overhauls of older 2600 and 3200-series rail cars

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $1,899,057 $41,619,579 ✔︎

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $21,831,629 $21,831,629
State $0 $0 $17,888,893 $17,888,893
RTA $0 $0 $0 $0
Service Board / Local $0 $1,899,057 $0 $1,899,057
Total $31,335,000 $1,899,057 $39,720,522 $72,954,579

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the end of mid-October 2023, 344 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 12.14.2023

+ Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation ofthe propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed inAugust 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery ofmaterial is expected to arrive in May 2021 and the overhaul is expected to take place in the first half of 2022.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,314,552
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 12.14.2023

+ Life extending Overhaul 2600/3200 Series Rolling Stock Rail $0 $136,974,595

Project Details

Description
Life extending overhaul on the 258 3200 Series and 300 2600 Series cars. Work on these cars will focus on major systems starting with the proplusion/powering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $104,665,377 $104,665,377
State $0 $0 $32,309,218 $32,309,218
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $136,974,595 $136,974,595

Last Updated 12.14.2023

+ Replace video system 3200 and 5000-Series railcars Rolling Stock Rail $10,000,000 $20,000,000

Project Details

Description
Replace the existing video system on the 5000-series rail cars which is obsolete and no longer supported by the vendor. Replace existing video system on the 3200-series rail cars with a more reliable system. Useable components removed from the 3200s will be re-used to support the same system on the 2600-seriese rail cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $10,000,000 $10,000,000 $20,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,100,000 $10,000,000 $10,000,000 $25,100,000

Last Updated 12.14.2023

+ CTA Rail Car Maintenance Activities Rail $0 $0 $300,000,000 $300,000,000

Preform rail car maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2022 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,106,390 $0 $0 $18,106,390

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$18,106,390
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.

Last Updated 12.14.2023

+ 2021 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.

Last Updated 12.14.2023

+ 2020 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$27,074,655
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Replacement Bus Purchase (4300 series) - Electric Buses Rail $0 $0 $140,000,000 $140,000,000

Ongoing need to replace diesel articulated buses as they age with electric buses.

+ CTA Blue Line (O'Hare) Traction Power Capacity & Track Improvements Rail $0 $0 $215,740,272 $215,740,272

Upgrades and State of Good Repair projects along the O'Hare Branch of the Blue Line

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ Blue Line Traction Power - Barry, Damen and Canal Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (atBarry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on theBlue Line. These assets will support increasing ridership demands as well as the power needed tosupport 5000 and 7000 series rail cars. The location of the tie house and substations were determinedby the Blue Line Load Flow study, which identified areas that were likely to experience traction powerissues.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,200,191 $0 $0 $2,200,191

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$122,417,171
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction ongoing at Canal Tie House, Damen, Barry and Haymarket Stations. Contractor has begun applying for CDOT general occupancy permits and sewer permits. Factory Testing has resumed and is on schedule.

Last Updated 12.14.2023

+ Blue Line O'Hare Branch - Special Trackwork Track & Structure Rail $0 $0

Project Details

Description
Funds provide for the replacement of stock rails, switch points, frogs, switch ties, and plates on the O’Hare Line that are no longer in a state of good repair and require concentrated maintenance by CTA forces to ensure service. The component replacement will take place between the Jefferson Park interlocking and the O’Hare terminal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,013,674 $0 $0 $2,013,674

Last Updated 12.16.2022

+ Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,030,427
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Old Mannheim Replacement Foot walk Track & Structure Rail $0 $0

Project Details

Description
Restore footwalk at Old Manheim on the O'Hare Line.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $250,000 $0 $0 $250,000

Last Updated 12.16.2022

+ CTA Blue Line Forest Park Modernization - Phase 1 Rail $0 $0 $131,245,158 $131,245,158

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Forest Park: Phase 1 - Trackwork Halsted to IMD Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to Illinois Medical District (IMD), an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $43,497,351 $0 $0 $43,497,351

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$158,423,800
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The extended line cut was completed in this reporting period. The concrete slab was poured as well. The contractor will continue to work on sub-ballast, installation of sewer structures, underdrains and downspouts, building the track as well as CTA tamping the track.

Last Updated 12.14.2023

+ Forest Park: Phase 1 - Racine Station and Morgan Substation & Hermitage Traction Power Improvements Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $67,471,237 $0 $0 $67,471,237

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$97,080,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. A Notice to Proceed for construction has been issued in May 2023. The contractor is currently working on the required submittals.

Last Updated 12.14.2023

+ Forest Park: Phase 1 - Advance Utility Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch.This project will provide for new trackwork from Halsted to IMD, an accessible station at Racine,advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. Thiswork will enhance service quality via speed, reliability, and comfort, and improve operational efficiency onthe Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,396,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractors for all four surveys completed their work during this reporting period and two are in final comments. Invoicing continues and all four contracts are considered to be in financial closeout. This will be the last update on this project.

Last Updated 12.14.2023

+ CTA Blue Line Forest Park Modernization - Phase 2 Rail $0 $0 $653,077,000 $653,077,000

Track improvements to address the most immediate critical track needs on the Forest Park Branch to enable its continued operation

+ CTA Green Line Improvements Rail $0 $0 $645,293,069 $645,293,069

Track, structural, station, and power improvements

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Green Line Improvements - Station Repairs to Green West and South Track & Structure Rail $0 $0

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs.This funding will improve Green line infrastructure including track, substations, traction power cable replacements, stations, and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,447,966 $0 $0 $1,447,966

Last Updated 12.16.2022

+ Green Line Jackson Park Branch Trackwork Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,855,446
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.

Last Updated 12.14.2023

+ Green Line - Lake Street Bridge Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs.This funding would support track improvements on both sides of the Lake Street Bridge, which isscheduled to be completely replaced by the Chicago Department of Transportation in 2023. The scopeof the project will include: improve the curve geometry on the east side of the bridge; replace thetimber ties and rail fasteners, install new gauge planking, replace equipment at both the east and westturnouts, and replace structural steel framing for the three side platforms adjacent to the track.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,025,296
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for the designer was issued in February 2022. The design activities are nearing completion. Coordination efforts with CDOT are ongoing. Once the CTA design is completed it will be on hold until CDOT finishes their portion of the design in order to align the timeline for construction activities.

Last Updated 12.14.2023

+ Green Line Improvements - 59th Junction Track & Structure Rail $0 $0

Project Details

Description
Replacement of special track work and adjacent mainline trackwork at Green Line 59th Junction. Rehab of track surves over the Dan Ryan Expressway, and rehabilitation of track on adjacent bridges over the Norfolk Southern and Metra Train lines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $21,911,108 $0 $0 $21,911,108

Last Updated 03.15.2023

+ Lake Street Line (Track and Structure) Track & Structure Rail $0 $0

Project Details

Description
Track renewal work focusing on the Lake Street elevated tracks from Ada Street to the Abutment West of Laramie Avenue. This work builds upon the recent track renewal work completed from Harlem to Laramie Avenue.The specific area of work within this segment of track will be determine based on funding availability and the condition of track. This provides for the initial installment of funds that are required for a significantly larger investment to complete work. Additional phased funding will be required to complete the entire segment of Track.Scope includes replacement of ties, fasteners, timber guards, contact rail chairs, footwalks, handrails, track planking, selective running and contact rail, including at special trackwork and the middle track locations. The scope also includes improved curve geometry, running rail grinding, and incidental signal/traction power work. Lake Street
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,408,000 $0 $0 $11,408,000

Last Updated 12.16.2022

+ Englewood Racine Green Line Station Feasibilty Study (EPI) Track & Structure Rail $0 $0

Project Details

Description
Study to determine the possiblity of reopening the Green Line Racine Station in Englewood
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,778,500 $0 $0 $2,778,500

Last Updated 12.14.2023

+ CTA Red Line Improvements Rail $0 $0 $396,400,000 $396,400,000

Upgrades and State of Good Repair projects along the Red Line