Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode 2024 Funding 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Pace IBS Replacement & Onboard Digital Screens Bus $0 $0 $32,150,000 $32,150,000

Equipment for bus tracking, communications, and data

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Intelligent Bus System (IBS) Electrical, Signal & Communications Bus $0 $0 ✔︎

Project Details

Description
Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,250,000 $0 $0 $2,250,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,250,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace began activity of this project during this reporting period. This will be for automatic passenger counters on fixed route buses. Activities have just started and expected to ramp up in Q1-2024.

Last Updated 12.14.2023

+ Pace Improve Passenger Facilities - Park-n-Ride Lots Bus $0 $0 $6,250,000 $6,250,000

Updates and repairs to Park-n-Ride lots

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Bolingbrook Park-n-Ride Stations & Passenger Facilities Bus $0 $0

Project Details

Description
This project will provide for improvements at the Bolingbrook Park-n-Ride
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,200,000 $0 $0 $1,200,000

Last Updated 12.14.2023

+ I-55 Park-n-Rides Stations & Passenger Facilities Bus $0 $0

Project Details

Description
I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,750,000 $0 $0 $6,750,000

Last Updated 12.16.2022

+ Pace Improve Passenger Facilities - Transportation Centers Bus $0 $0 $67,150,000 $67,150,000

Improvements to Transportation and Transfer Facilities

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Harvey Transportation Center - Pace Stations & Passenger Facilities Bus $0 $0

Project Details

Description
Pace is partnering with Metra, the City of Harvey, and IDOT with the intent to move the transportation center and combine it with the Metra station.The elements of the construction may include pavement, lighting, platforms, shelters, restrooms, structures and systems and may have a taxi release area to create a multimodal facility.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $30,850,000 $0 $0 $30,850,000

Last Updated 12.16.2022

+ Improve Passenger Facilities Stations & Passenger Facilities Bus $0 $0

Project Details

Description
Improve Passenger Facilities - Fabrication of a new Ventra machine for the O'Hare multimodal facility in 2021. Future renovations are being evaluated for Burr Ridge & Hillside Park-n-Rides, Chicago Heights Transfer Center, Riverdale Bus Turnaround, and Gurnee Mills Transportation Center.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $120,000 $0 $0 $120,000

Last Updated 12.16.2022

+ Joliet Gateway Center - Bus Stop Improvements Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby publicproperties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopmentthe City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public andinter-city transit which will include parking improvements and the construction of new vehicular andpedestrian access and circulation system. The new Bus Station is south of New Street, north of MarionStreet and west of the BNSF/Union Pacific Railroad. The bus station will have 13 berths, with Pacehaving exclusive use of 11 berths, passenger loading islands with canopies and shelters, signage andlandscaping. There will also be a widening of the St. Louis Street, Pace bus operator and public toilets ata location immediately northeast of the existing Pace Heritage Division garage, and ADA accessiblesidewalks.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,509,500
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk?through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.

Last Updated 12.14.2023

+ CTA Mid-Life Bus Overhaul (4300 series) Bus $0 $0 $0 $0

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Mid-Life Bus Overhaul 4300 Series Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Overhauls of the 4300 articulated buses to maintain vehicles, ensure reliability and enable to perform through full useful life
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,615,472 $0 $0 $9,615,472

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,327,057
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The milestones related to accepting the two pilot buses was completed in November 2023. Work on Milestone 3 continues but is behind schedule. The CTA is waiting for NFI to submit a new Recovery Schedule that will demonstrate how the schedule will make up for the delays to the project to get it back on schedule. A new Recovery Schedule is expected by the next reporting period.

Last Updated 04.15.2024

+ CTA New Control and Training Center System $0 $0 $0 $0

Construct new CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ New Control & Training Center Support Facilities & Equipment System $0 $0 ✔︎

Project Details

Description
CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations. This project consolidates training functions across the agency within a centralized facility. Currently training is dispersed throughout the CTA system at various garages, yards, and offices due to space limitations. Thousands of CTA operating and maintenance employees use these facilities for employee training, instruction programs, and employee engagement. The primary rail and maintenance training is performed at a leased space and lacks all components necessary for proper training.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $317,270,670 $0 $0 $317,270,670

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$239,988,009
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 30% Schematic Design submittal was submitted on 01/24/2024. The 60% Detailed Design submittal was submitted on 03/4/24. CTA is working with the contractor for items related to that design submittal. The 100% advance work package for earthwork was submitted to DoR on 3/8/24 and continues to have the contractor working on it to address comments. The 90% design submittal is expected to be submitted to CTA in mid-May and the 100% design submittal is expected to be submitted in September 2024.

Last Updated 04.15.2024

+ Pace Paratransit Vehicles - Expansion Bus $0 $0 $13,000,000 $13,000,000

New Dial-a-Ride and ADA vehicles for aging population

+ Pace Pedestrian Infrastructure/Shelters/Signs Bus $0 $0 $30,500,000 $30,500,000

Shelters, pedestrian access, and completion of conversion to posted stops

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,550,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ 2020 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,330,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ 2021 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$600,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 12.14.2023

+ 2022 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,125,000 $0 $0 $1,125,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$425,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 12.14.2023

+ 2022 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0

Project Details

Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $425,000 $0 $0 $425,000

Last Updated 12.16.2022

+ CTA Program Management System $0 $0 $66,064,000 $66,064,000

Provide for Program Management

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Program Management Contingencies and Administration System $0 $0

Project Details

Description
Professional services to manage implementation of the CTA's Capital Construction Program. Funds provide for a construction program management consultant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,212,750 $0 $0 $13,212,750

Last Updated 12.14.2023

+ CTA Radio System Upgrade Rail $0 $0 $64,500,000 $64,500,000

Replacement of obsolete radio system

+ CTA Rail Car Maintenance Activities Rail $0 $0 $300,000,000 $300,000,000

Preform rail car maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2020 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$27,074,655
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.

Last Updated 12.14.2023

+ 2022 - Rail Car Maintenance Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle. When certain maintenance tasks are needed to repair or replace a component before it reaches its end of useful life and fails with an increased frequency, specific component campaign work is conducted.The major systems that must be maintained on CTA’s rail cars include the following:Propulsion, Safety, HVAC, Braking, Battery/Charging, Signage, Doors, Windows, Traction Power, RCA, Lighting, Automatic Train Control, Communication , Suspension, Car body/Structure. CTA’s Rail Terminal Shops are responsible for the maintenance that may result in replacement of a variety of components such as: traction motors, HVAC components and packages, lights, public address system components, trucks, wheels assemblies, hydraulic units, couplers, drawbars, and numerous other mechanical and electrical components. CTA’s Heavy Maintenance Shop is responsible for the rebuild/repair/manufacture of components for the railcar fleet such as wheel assemblies, truck assemblies, traction motors, air comfort units, electronic devices, control units, and associated devices including solid state and microprocessor-controlled units.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,106,390 $0 $0 $18,106,390

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$18,106,390
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.

Last Updated 12.14.2023