Capital Projects

Regional Capital Program

Download Capital Dataset

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measure which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Project Mode 2023 Funding 2023-2027 Funding 10 Year Funding Neededsort descending 10 Year Unfunded Need
+ Pace Community Vehicles - Expansion Bus $0 $0 $3,000,000 $3,000,000

Description:

New Community and Call-n-Ride vehicles

No Results Found

+ CTA Program Development System $525,000 $2,625,000 $6,250,000 $3,625,000

Description:

Provide for Program Development

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Program Development - UWP Contingencies and Administration System $525,000 $2,625,000

PROJECT DETAILS

Description:

Develop and refine CTA's capital programs for inclusion into five year regional Transportation Improvement Program. Provide support as required to finalize the current TIP. Analyze project proposals for potential inclusion in the Authority's Capital Program, presentations to the public, CTA Board and Regional Transportation Authority (RTA).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$420,000
$1,680,000
$2,100,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$105,000
$420,000
$525,000
Total
$625,000
$525,000
$2,100,000
$3,250,000

Last Updated 12.16.2022

+ Pace Improve Passenger Facilities - Park-n-Ride Lots Bus $0 $0 $7,450,000 $7,450,000

Description:

Updates and repairs to Park-n-Ride lots

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-55 Park-n-Rides Stations & Passenger Facilities Bus $0 $0

PROJECT DETAILS

Description:

I-55 Park-n-Rides: A/E design and expansion of existing (Bolingbrook, Burr Ridge, Romeoville) and/or construction of new park-n-ride facility.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,750,000
$0
$0
$6,750,000

Last Updated 12.16.2022

+ Pace Vanpool Vehicles - Replacement Bus $0 $0 $12,640,000 $12,640,000

Description:

Replacement of vans reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase 7-passenger Vanpool Vehicles Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Vanpool Vehicles - Pace plans to purchase 164 replacement 17'-20' vans including associated equipment and services (Buy America audit and inspections) for vanpool services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$13,899,800

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2019

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

To date a total of 25 vans have been ordered, all have been received. Pace has executed a contract to install OEM passenger running boards on the first order of 25 vans. All the running boards have been installed and are in the active fleet. Pace continued to work on an action plan for ordering more vehicles based on projected needs. The vans will be utilized in the six county Pace service area.

Last Updated 06.22.2023

+ Pace Paratransit Vehicles - Expansion Bus $0 $0 $13,000,000 $13,000,000

Description:

New Dial-a-Ride and ADA vehicles for aging population

No Results Found

+ Pace Bus on Shoulder (BoS) Infrastructure Bus $0 $17,025,000 $17,025,000 $0

Description:

Passenger facilities for Bus on Shoulder service

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ I-294 Stations & Park-n-Rides Stations & Passenger Facilities Bus $0 $17,025,000

PROJECT DETAILS

Description:

I-294 Stations and Park-n-Rides : The Illinois Tollway is planning to add a Flex Lane on 22 miles of I-294, and infrastructure is needed to make connections to the transit system. Pace is currently conducting market analysis and workshops for this project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$17,025,000
$17,025,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$17,025,000
$17,025,000

Last Updated 12.16.2022

+ Pace Community Vehicles - Replacement Bus $0 $4,830,000 $17,955,000 $13,125,000

Description:

Replacement of buses reaching useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Community Transit/On-Demand Vehicles Rolling Stock Bus $0 $4,830,000

PROJECT DETAILS

Description:

Community Transit/On Demand Vehicles - Pace plans to purchase 89 replacement vehicles (17'-20' vans and 21'-23' cutaways) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for Community Transit and On Demand services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$4,830,000
$4,830,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$4,830,000
$4,830,000

Last Updated 12.16.2022

+ Pace Intelligent Bus System (IBS) Replacement Bus $0 $3,650,000 $18,150,000 $14,500,000

Description:

Equipment for bus tracking, communications, and data

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Intelligent Bus System (IBS) Electrical, Signal & Communications Bus $0 $3,650,000

PROJECT DETAILS

Description:

Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$3,650,000
$3,650,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,250,000
$0
$3,650,000
$5,900,000

PMO:

Total Project Budget^

$625,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Dec 2020

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace completed the scope of work for IBS services and transit master software upgrades related to IBS servicers and new servers were installed with software upgrades ongoing.

Last Updated 06.22.2023

+ CTA Life-Extending Bus Overhaul 430 (1000 series) Bus $10,195,422 $16,932,852 $19,567,505 $2,634,653

Description:

Overhauls to maintain sufficient fleet until the first order of replacement buses is received

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Life Extending Bus Overhaul - 430 Standard (1000 Series) Rolling Stock Bus $10,195,422 $16,932,852

PROJECT DETAILS

Description:

Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$10,195,422
$6,737,430
$16,932,852
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$14,905,007
$10,195,422
$6,737,430
$31,837,859

PMO:

Total Project Budget^

$1,893,610

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2022

End Date

Oct 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The CTA Team drafted technical specs and project scope were completed and under review as of this reporting period. The team tested a new pilot Haldex air dryers on two buses.

Last Updated 06.22.2023

+ CTA Tactical Signal Improvements Rail $2,125,768 $2,125,768 $21,630,000 $19,504,232

Description:

State of Good Repair projects and replacing obsolete equipment on CTA rail signal system

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Tactical Traction Power (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $2,125,768 $2,125,768

PROJECT DETAILS

Description:

State of Good Repair projects and replacing obsolete equipment on CTA rail signal system

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,125,768
$0
$2,125,768
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$2,125,768
$0
$2,125,768

PMO:

Total Project Budget^

$10,293,685

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2022

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Permits for the project were received in the last reporting period. Currently, the General Contractor is submitting process plans for start of construction and mobilization on site. Delivery of onsite storage containers is ongoing. CTA is working with the contractor to start the first phase of the project, which is the electrical shop equipment relocation.

Last Updated 06.22.2023