Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Projectsort descending Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Program Management System $6,606,375 $33,031,875 $66,064,000 $33,032,125

Description:

Provide for Program Management

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Program Management Miscellaneous System $6,606,375 $33,031,875

PROJECT DETAILS

Description:

Professional services to manage implementation of the CTA's Capital Construction Program. Funds provide for a construction program management consultant.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$6,606,375
$26,425,500
$33,031,875
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,606,375
$6,606,375
$26,425,500
$39,638,250

Last Updated 12.16.2022

+ Metra PTC - systemwide Rail $4,250,000 $6,190,000 $0 $0

Description:

Install federally-mandated rail operational safety system

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ PTC Program Management Electrical, Signal & Communications Rail $1,000,000 $1,000,000

PROJECT DETAILS

Description:

This project will be to facilitate a vendor who can provide Program Management of the entire PTC system and ongoing projects. These projects include, Next Generation Office, CTC over ITCM, ITCM support, PTC Data Distallation Tool, Wabtec Master Service Agreement, and PTC Hardware Renewal. The scope of this work will also include document control, TPCQMP compliance, and movement of all PTC documentation to ProjectWise. The scope also includes FTA, RTA and IDOT monthly PTC progress reporting.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$0
$1,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$0
$1,000,000

Last Updated 06.22.2023

+ PTC Renewal (Engineering) Electrical, Signal & Communications Rail $2,000,000 $2,690,000

PROJECT DETAILS

Description:

This project will fund the second phase of Positive Train Control (PTC). Project funds will update back office equipment, components, hardware, software, and other equipment that is necessary to maintain safe and consistent operations of Metra’s interoperable PTC system. This project will fund the purchase, installation, and training of a modern, streamlined PTC system to replace the current PTC back office before the end of its useful life. This new system will have an advanced user interface that will provide operational self-checks and will enable safer operations

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,000,000
$690,000
$2,690,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,000,000
$2,000,000
$690,000
$7,690,000

Last Updated 12.16.2022

+ PTC- Renewal (Mechanical) Rolling Stock Rail $1,250,000 $2,500,000

PROJECT DETAILS

Description:

This project will fund the second phase of Positive Train Control (PTC). Project funds will update onboard equipment and parts in locomotives and cab cars that communicate with the guideway PTC system.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,250,000
$1,250,000
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,800,000
$1,250,000
$1,250,000
$5,300,000

Last Updated 12.16.2022

+ Pace Pulse Infrastructure System $1,464,000 $21,031,500 $84,525,000 $63,493,500

Description:

Enhance Pulse service

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Pulse 95th Street Design and Construction Stations & Passenger Facilities Bus $1,464,000 $21,031,500

PROJECT DETAILS

Description:

Design and construction of stations of the Pulse 95th Rapid Transit Line. The project corridor is approximately 12.4 miles in length and runs east-west between the CTA Red Line 95th/Dan Ryan Station in Chicago and Moraine Valley Community College in Palos Hills primarily routed along 95th Street, as well as several other roadways in Bridgeview, Chicago Ridge, Hickory Hills, and Palos Hills.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,464,000
$15,654,000
$17,118,000
State
$0
$0
$3,913,500
$3,913,500
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,464,000
$19,567,500
$21,031,500

Last Updated 12.16.2022

+ CTA Radio System Upgrade Rail $0 $0 $35,000,000 $35,000,000

Description:

Replacement of obsolete radio system

No Results Found

+ CTA Rail Car Maintenance Activities Rail $0 $60,000,000 $300,000,000 $240,000,000

Description:

Preform rail car maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 2020 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$27,074,655

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2020

End Date

Sep 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities with this funding were completed in this reporting period. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ 2021 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$10,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities are ongoing. Major elements include, but not limited to, rail car inspection and engineering; vehicle wiring; and body work. The project budget has been decreased via a grant amendment for a bus maintenance project.

Last Updated 06.22.2023

+ 2022 - Rail Car Maintenance Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$18,106,390
$0
$0
$18,106,390

PMO:

Total Project Budget^

$18,106,390

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2022

End Date

Jun 2027

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Rail car maintenance activities for this project are on hold until prior year projects are completed. Major elements will include, but are not limited to, rail car inspection and engineering, vehicle wiring, and body work.

Last Updated 06.22.2023

+ 2023 - Rail Car Maintenance Rolling Stock Rail $0 $60,000,000

PROJECT DETAILS

Description:

Rail Car Maintenance Activities - CTA will continue investing in the rail car fleet maintenance program. This program is intended to correct critical defects and operational deficiencies discovered during inspections of rail cars. CTA’s scheduled maintenance program consists of planned work to maintain rail car performance. While major overhaul work is performed on a quarterly and mid-life cycle basis, additional focused maintenance work is required at certain intervals of the car’s life, outside of the overhaul cycle.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$60,000,000
$60,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$60,000,000
$60,000,000

Last Updated 12.16.2022

+ CTA Rail Shops Improvements Rail $31,007,124 $89,807,124 $255,900,000 $166,092,876

Description:

Provide repair and replacement to worn components at rail maintenance shops

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 63rd Shop - Non-Revenue Equipment and Service Support Facilities & Equipment Rail $3,000,000 $3,000,000

PROJECT DETAILS

Description:

Purchase of equipment associated with 63rd Shop operations moving from Skokie to 63rd. Also, contracts for movement of existing equipment/material. This is necessary to allow use of the new shop as planned.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,000,000
$0
$3,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$3,000,000
$0
$3,000,000

Last Updated 12.16.2022

+ Improve Facilities - Diesel Locomitve Storage Shed Support Facilities & Equipment Rail $11,000,000 $11,000,000

PROJECT DETAILS

Description:

The purpose of this project is to support the expansion of CTA’s diesel-powered snow fighter locomotives via the construction of three sheds, one at each of the following locations: 98th, Midway, and Rosemont Yards to house the four new snow fighter locomotives. The sheds will fully enclose the locomotives. Work at each location provides for a pre-engineered insulated metal building structure, overhead coiling doors, plumbing, mechanical, electrical, fire alarms system, and tie-ins for sewer and electrical service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$11,000,000
$0
$11,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$11,000,000
$0
$12,000,000

Last Updated 12.16.2022

+ Midway Shop - Wheel Truing Machine Bldg. Extension and Access Track. Support Facilities & Equipment Rail $0 $13,800,000

PROJECT DETAILS

Description:

Provide railcar access from the north yard. Both cars of a railcar unit will be able to be trued without removing the unit from the shop to turn around. Allows for increased wheel truing activity, improves ride quality, and extends wheel life and track life.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$13,800,000
$13,800,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$13,800,000
$13,800,000

Last Updated 12.16.2022

+ Non-Revenue Rail Vehicle Equipment - Replacement Support Facilities & Equipment Rail $5,507,124 $15,507,124

PROJECT DETAILS

Description:

Replace various rail-borne non-revenue vehicles that have exceeded their useful lives. Repairs and spare parts have become increasingly difficult which raises maintenance costs and increases duration of downtime of this critical equipment. Equipment includes: car movers, rail borne sewer vacuum, subway washer vehicle, rail profile grinder, rail cranes, 2 locomotive crane 22 ton, 2 tie cranes w/ close clearance tie replacement head, sky trim tree trimmer, tie inserters, MKVI tamper and stabilizer.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,507,124
$10,000,000
$15,507,124
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,507,124
$10,000,000
$15,507,124

Last Updated 12.16.2022

+ Rail Car Facility Maintenance Support Facilities & Equipment Rail $1,000,000 $15,000,000

PROJECT DETAILS

Description:

Replacement of various shop facility heavy equipment that is ending their useful lives. Equipment includes: carbody hoists at Harlem, spin jacks at Rosemont and Wheel truing machine at 54th (replace with 4-axle), office space at Harlem above classroom, security gates at Kimball/54th for when rollup doors are raised, 2 man gates at DesPlaines.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$14,000,000
$15,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$14,000,000
$15,000,000

Last Updated 12.16.2022

+ Replace Non-Revenue 61st Rail Shop Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Construct a new non-revenue vehicle maintenance facility for maintenance and repair of non-revenue
equipment. Facility will also include covered storage tracks for track maintenance equipment. The
purpose of the new Non-Revenue Rail Vehicle Maintenance Facility is to provide facilities for
maintenance and repair of over 125 pieces of non-revenue equipment used for right-of-way maintenance
and other rail-mounted non-revenue vehicles.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$70,017,063

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Mar 2021

End Date

Nov 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The 61st rail shop project had most site planning activities completed. The foundations were poured, and the building enclosure erected as well as roof installed. The contractor continues to make headway with procurement of equipment related to installation of utilities such as transformers for the electrical requirements of the facility and plumbing elements. The contractor is working on design work packages for the parking lot and landscaping for the facility.

Last Updated 06.22.2023

+ Skokie Clean Room - Bench Test Equipment Miscellaneous System $0 $0

PROJECT DETAILS

Description:

Skokie Clean Room - Bench Test Equipment:
The scope of work provides for modifications to the CTA Skokie Shop (Heavy Maintenance Facility) to accommodate the addition of clean rooms. All of the necessary architectural and MEP systems would be reworked and reactivated in the expanded / modified spaces.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,400,000
$0
$0
$4,400,000

Last Updated 12.16.2022

+ Skokie Shops - Railcar Hoists Support Facilities & Equipment Rail $5,000,000 $20,000,000

PROJECT DETAILS

Description:

Construct two new Rail car body hoists where the non-revenue unit is currently situated. This unit is to move to new facility in late 2023 or early 2024. Additional space with new hoists increases the capacity to overhaul series cars. Over the next five years, CTA will need to continue the overhaul of the 5000 Series, while also addressing life extending work on existing 2600 and 3200 Series expected to remain in fleet until replacement cars are available from a future order.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,000,000
$15,000,000
$20,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,000,000
$15,000,000
$20,000,000

Last Updated 12.16.2022

+ Skokie Shops - Wheel truing machine replacement Support Facilities & Equipment Rail $4,500,000 $9,000,000

PROJECT DETAILS

Description:

Design and install new wheel truing machine.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$4,500,000
$4,500,000
$9,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$4,500,000
$4,500,000
$9,000,000

Last Updated 12.16.2022

+ Skokie Shops Improvements Other Support Facilities & Equipment Rail $1,000,000 $2,500,000

PROJECT DETAILS

Description:

Various shop improvements, including: Repurpose truck wash machine area to HVAC/truck wash, fill in truck transfer pit and install truck hi-line, add truck hi-line positions (and lighting, hose reels) in truck storage area, additional air operated 2-ton crane in Paint Booth, engineering lab, additional crane in truck shop on existing rails.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$1,500,000
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,000,000
$1,500,000
$2,500,000

Last Updated 12.16.2022

+ Metra Rail Station Improvements Rail $295,524,917 $485,490,576 $747,272,085 $261,781,509

Description:

Rehabilitation and upgrades to station buildings, platforms, and parking lots

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 103rd Street - Washington Heights Station Stations & Passenger Facilities Rail $0 $415,000

PROJECT DETAILS

Description:

Rehabilitate Depot, Rehab Stair and Ramp and Handrails, Peel and Pave outbound Platform, add 181' new Timber Box Platform for 510' length platform (6-Car). Demolish Inbound Platform and replace with new 510' Timber Box Platform. (1) New Shelter. Grind and resurface south parking and Replace North Parking and Drive Aisle. SIte Amenities including VIS, Signs, Wayfinding, benches and lighting

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$415,000
$415,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$415,000
$415,000

Last Updated 12.16.2022

+ 107th St. (Beverly Hills) Station Stations & Passenger Facilities Rail $600,000 $600,000

PROJECT DETAILS

Description:

This project will provide design engineering funds for the 107th St. (Beverly Hills) station on the Rock Island (RI) Line in the Beverly Hills neighborhood of Chicago. Rehabilitation of the existing station warming shelter that is appropriate for the historic neighborhood will be completed in future phases of the project. Project activities may include, but are not limited to, parking lot renovations, ADA improvements, new lighting around the station, additional shelters and bicycle parking, and other activities as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$600,000
$0
$600,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$600,000
$0
$1,600,000

Last Updated 12.16.2022

+ 111th St. Station / Pullman Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will fund the rehabilitation of the 111th Street / Pullman Station on the Metra Electric District Line in Chicago. The project elements may include the replacement and/or rehabilitation of
station platforms, new lighting, gatehouse/head house rehabilitation, replacement of leaking roofs, installation of new warming shelters, new platform amenities, and other related work. The project may
also include wayfinding signage or other station identifiers.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$20,750,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

May 2020

End Date

Dec 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this station is 40% complete. The design is currently on hold until the National Environmental Policy Act (NEPA) review process is complete. Coordination with the State Historic Preservation Office (SHPO) is required as part of the NEPA process since the station is located in a historic district.

Last Updated 06.22.2023

+ 115th St Station Stations & Passenger Facilities Rail $6,000,000 $6,000,000

PROJECT DETAILS

Description:

This project will provide design engineering funds for the 115th St. (Morgan Park) station on the Rock Island (RI) Line in the Morgan Park neighborhood of Chicago. A new station warming shelter will be constructed with distinctive architectural elements and materials that are appropriate for the historic neighborhood. The project scope includes parking lot renovations, ADA improvements, the installation of shelters, bicycle parking, and landscaping improvements.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$6,000,000
$0
$6,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$870,000
$6,000,000
$0
$6,870,000

Last Updated 03.16.2023

+ 147th St. - Sibley Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project consists of the complete rehabilitation of the 147th St. (Sibley Blvd.) station facility in Harvey along with the Metra Electric (ME) Line in Harvey. The project scope includes renovation of the station entrance, heated warming shelters, a canopy over half of the platform. Additional project elements include, but may not be limited to, lighting, sidewalk, bike facilities, landscape enhancements, and other related work.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,400,000
$0
$0
$9,400,000

PMO:

Total Project Budget^

$20,862,735

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2022

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Construction activities are ongoing at the station. The contractor is working on preparations for the elevator installation by forming and placing rebars at the headhouse and elevator walls. Forming, rebar placing, and electrical conduit work is ongoing at the ground level station entrance walls. Contractor is also working on assembling and installing north and south platform and canopy structural steel. Procurement of major equipment such as transformers and platform panels has been completed.

Last Updated 06.22.2023

+ 59th/60th ST. Station (U. of Chicago) Stations & Passenger Facilities Rail $68,630,000 $78,100,000

PROJECT DETAILS

Description:

This project consists of the complete rehabilitation of the 59th/60th Street (U. of Chicago) station facility in Chicago along the Metra Electric Line. As part of the project, the 60th Street entrance will be reopened. Additional project elements include, but may not be limited to, lighting, sidewalk, bike facilities, landscape enhancements and other related work. The project will leverage $2,500,000 from the University of Chicago.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$37,600,000
$9,470,000
$47,070,000
State
$0
$12,000,000
$0
$12,000,000
RTA
$0
$17,030,000
$0
$17,030,000
Service Board / Local
$0
$2,000,000
$0
$2,000,000
Total
$0
$68,630,000
$9,470,000
$78,100,000

Last Updated 06.22.2023

+ 63rd Street Station Stations & Passenger Facilities Rail $0 $100,000

PROJECT DETAILS

Description:

This project will study potential improvements to the station which may include but are not limited to restoration of the viaduct, replacement of staircases, the potential addition of an elevator, design of a new gatehouse and platform head house, the feasibility of extending the boarding platforms, and consideration of a platform-length canopy.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$100,000
$100,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$100,000
$100,000

Last Updated 12.16.2022

+ 79th St., 87th St, 103rd St. Stations Metra Electric Stations & Passenger Facilities Rail $37,900,000 $37,900,000

PROJECT DETAILS

Description:

This project funds the complete rehabilitation of the 79th Street, 87th Street and 103rd Street Stations in Chicago along with the Metra Electric (ME) Line. The project scope includes the repair or replacement of aging shelter enclosures, station lighting upgrades, and platform renovation work. Additional project elements may include but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, bench repairs, and other related work as needed. The station will be made fully ADA accessible upon completion of the project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$37,900,000
$0
$37,900,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$11,000,000
$37,900,000
$0
$48,900,000

PMO:

Total Project Budget^

$61,150,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2020

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The designs for these stations have been completed. The Notice to Proceed with construction has been issued in January 2023. The contractor is currently working on permitting.

Last Updated 06.22.2023

+ 83rd Street (South Chicago) Station Stations & Passenger Facilities Rail $0 $225,000

PROJECT DETAILS

Description:

The project may include but is not limted to repairing wind break shelters, the rehabilitation or replacement of the station depot and canopy shelter, addition of a new staircase, handrails, and an ADA ramp (if feasible) at the intersection of 82nd and Commercial. Site Amenities, signage and wayfinding

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$225,000
$225,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$225,000
$225,000

Last Updated 12.16.2022

+ 91st Street-Beverly Station Stations & Passenger Facilities Rail $0 $700,000

PROJECT DETAILS

Description:

The project may include but is not limted to restoration of the Historic Depot, including insulating the walls and ceiling, and adding new windows, improving the waiting room, and other interior improvements. A new shelter and a reconstructed parking lot may be considered and may require land aquisition or land swap with the city of Chicago. Improvements to the foundation may including raising a portion of the building to eliminate the existing ramp to platform.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$700,000
$700,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$700,000
$700,000

Last Updated 12.16.2022

+ 95th Street Station CSU Stations & Passenger Facilities Rail $34,000,000 $34,000,000

PROJECT DETAILS

Description:

This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$29,000,000
$0
$29,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$5,000,000
$0
$5,000,000
Total
$3,000,000
$34,000,000
$0
$37,000,000

PMO:

Total Project Budget^

$53,000,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

May 2020

End Date

Dec 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this station is 95% complete and the 100% design submittal is expected in July 2023. There were delays on this project associated with the National Environmental Policy Act (NEPA) review process as well as coordination with the Chicago State University and additional scope added to the design.

Last Updated 06.22.2023

+ Arlington Park Station-Parking Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Metra intends to exercise a clause in the lease contract to purchase the parking lot area for the Arlington Park station on the Union Pacific Northwest (UP-NW) Line. Metra has leased a 9.3-acre parking lot from the owners of the Arlington Park Racecourse since 2002. It was announced in 2021 that the horse racing track would close, and the property will be sold off. Metra seeks to purchase the land to avoid annual rent costs, which will result in significant savings, and to allow flexibility for long-range planning of the station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$6,237,000
$0
$0
$6,237,000

Last Updated 12.16.2022

+ Ashland Station Stations & Passenger Facilities Rail $0 $126,659

PROJECT DETAILS

Description:

This project will rehabilitate the aged timber deck platform, and add new lighting around the station facility. The project may include a new warming shelter, staircase improvements, and the installation of a new ADA Ramp to platform. Enhanced customer amenities may include a new station amenities, wayfinding, signage, benches, and parking lot improvements.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$126,659
$126,659
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$126,659
$126,659

Last Updated 12.16.2022

+ Auburn Park New Station Stations & Passenger Facilities Rail $2,000,000 $4,200,000

PROJECT DETAILS

Description:

The new station in the Auburn Park neighborhood of Chicago will feature a platform-length canopy and heated headhouse with two elevators. The station will include a center boarding platform with a staircase down to street level entrance tunnel, a landscaped plaza with benches, canopy, bicycle parking, and a vendor space Metra will lease. A parking lot will include 79 parking stalls, 5 ADA parking spaces, and a passenger drop-off lane. The new station will be fully ADA accessible.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$2,000,000
$2,200,000
$4,200,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,300,000
$2,000,000
$2,200,000
$8,500,000

PMO:

Total Project Budget^

$37,300,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Dec 2021

End Date

Oct 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The new station will increase transit accessibility for the surrounding neighborhood. Benefits of this new station will reduce congestion on the Dan Ryan Expressway. The contractor is working on submittals. This project has encountered delays with the permits. The contractor is working on resolving issues related to permitting.

Last Updated 06.22.2023

+ Bicycle Parking Stations & Passenger Facilities Rail $85,000 $85,000

PROJECT DETAILS

Description:

Metra was awarded CMAQ grants for the purchase and installation of bicycle parking facilities at stations across the system. Specific locations are to be determined

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$85,000
$0
$85,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$76,500
$85,000
$0
$161,500

Last Updated 12.16.2022

+ Blue Island Transfer Facility Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project includes, but is not limited to, the complete rehabilitation of the RID Vermont Street
station in Blue Island. Work for this project will include, but not be limited to, historic rehabilitation,

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$983,006
$0
$0
$983,006

Last Updated 12.16.2022

+ Clarendon Hills Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project redevelops the Clarendon Hills Station on the Metra BNSF line. The station improvements include new platrofm canopies, enclosed shelters, benches, and covered bike parking. The shelters will feature green roofs. The parking lot improvements will feature kiss‐and‐ride areas on both sides of the tracks. Landscaping improvements will also be included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$3,750,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Mar 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Metra entered into an Intergovermental Agreement (IGA) with the Village of Clarendon Hills for the reconstruction of the station. This project is part of the Village of Clarendon Hills downtown revitalization project. The Village procured a contractor and led the construction project. The substantial completion was reached in the first quarter of 2022. This is the final update on this project.

Last Updated 07.10.2022

+ Clybourn Station Stations & Passenger Facilities Rail $0 $100,000

PROJECT DETAILS

Description:

Replace and Widen west platform to 510' x 24' to accomodate new elevator. Requires realignment of track and replacement of Armitage Road Bridge (single track). Add 3 new headhouses with APTA elevators and new stairs, add (5) additional new stairs for access and egress. Provide (8) new shelters. (4) new 300' by 10' Canopies. Replace remainig platforms with new 510' long platforms. Replace south parking with dual lane turnaround and drop off and replace and reconfigure remaining parking (10+ spots). Replace and Rehab retaining walls. Tunnel rehab and extension. Site amenities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$100,000
$100,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$100,000
$100,000

Last Updated 12.16.2022

+ Congress Park Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will provide construction funds for the rehabilitation of the Congress Park station facility along the BNSF Line. The station will be rehabilitated to be ADA compliant.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$0
$1,000,000

Last Updated 12.16.2022

+ Downtown Public Address System Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

This project consists of purchasing public address (PA) equipment that will be used at various locations in Metra's downtown Chicago terminals. The new PA system will be designed to comply with the Americans with Disabilities Act (ADA).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,800,000
$0
$0
$1,800,000

Last Updated 12.16.2022

+ Downtown Station Signs Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will design, purchase, and install new digital train tracking displays and backlit station identification signs. Video boards will display real-time train tracking and service alerts as well as other visual information. At least one sign is planned to be installed at and or near the primary entrance to Metra's five downtown Chicago terminals. New train tracking displays will improve our communication with the customer and better accommodate ESL and/or non-English speakers and improve ADA compliance.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,530,000
$0
$0
$1,530,000

Last Updated 12.16.2022

+ Elevator Replacement Stations & Passenger Facilities Rail $6,580,000 $15,405,000

PROJECT DETAILS

Description:

This project will replace or renovate elevators at various stations across the Metra system.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$6,580,000
$8,825,000
$15,405,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,450,000
$6,580,000
$8,825,000
$16,855,000

PMO:

Total Project Budget^

$300,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Jan 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Metra continued the preparation of the final design Architectural and Engineering task orders for elevator replacement. The Randolph St. elevator has NEPA issues to resolve. The two other elevators at Grand & Cicero are at 90% and proceeding to 100% design completion.

Last Updated 06.22.2023

+ Elmhurst Station Stations & Passenger Facilities Rail $2,000,000 $2,000,000

PROJECT DETAILS

Description:

This project will fund Metra’s portion of a larger station renovation/expansion in Elmhurst. It will leverage CMAQ funds obtained by the Village of Elmhurst to construct a larger station to accommodate the growing ridership.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$2,000,000
$0
$2,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$2,000,000
$0
$3,000,000

PMO:

Total Project Budget^

$1,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2022

End Date

Mar 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Preliminary engineering and NEPA process were completed. The Village of Elmhurst is leading the design with their consultant and proceeding to the 60% design submittal.

Last Updated 06.22.2023

+ Evanston Davis St. Station Stations & Passenger Facilities Rail $7,000,000 $17,945,000

PROJECT DETAILS

Description:

This project will completely rehabilitate the Evanston (Davis St. station) facility in downtown Evanston. The project scope includes extensive repairs to the station depot and platform shelters, station lighting upgrades, and platform renovation work. Retaining wall sections at intermittent locations along the right-of-way may be repaired as needed. Additional project elements may include, but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, entrance staircase repairs, and other related work as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$1,000,000
$10,945,000
$11,945,000
RTA
$0
$6,000,000
$0
$6,000,000
Service Board / Local
$0
$0
$0
$0
Total
$0
$7,000,000
$10,945,000
$17,945,000

Last Updated 03.16.2023

+ Forest Glen Station Stations & Passenger Facilities Rail $400,000 $400,000

PROJECT DETAILS

Description:

The Forest Glen Station will undergo multi-phase rehabilitation. Phase 1 will replace the inbound and outbound platforms with new heated platforms that will include tactile strips for ADA compliance, reconstruct the entry staircase with heated stairs, and replace the deficient station depot with a temporary shelter. Following design engineering services, Phase 2 will add a new, heated station depot in place of the temporary shelter, new wayfinding signage, and other station identifiers. Upon completion of Phase 3, the station will be made fully ADA-accessible.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$400,000
$0
$400,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$400,000
$0
$400,000

Last Updated 12.16.2022

+ Glen Ellyn Station Stations & Passenger Facilities Rail $0 $4,000,000

PROJECT DETAILS

Description:

This project will fund repairs at the Glen Ellyn station facility. The project scope may include, but not be limited to, depot repairs, entrance stairs repairs, and new signage. Additional project elements may include, but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, bench repairs, station lighting upgrades, and other related work as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$4,000,000
$4,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$4,000,000
$4,000,000

Last Updated 12.16.2022

+ Harvey Transportation Center - Metra Stations & Passenger Facilities Rail $20,850,000 $41,700,000

PROJECT DETAILS

Description:

Metra is partnering with Pace to create the Harvey Transportation Center on the Metra Electric line. Metra will utilize funds for platform reconstruction and to construct other enhancements that will make the station ADA accessible, improve the commuter environment, and facilitate intermodal transfers between Pace and Metra.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$8,100,000
$8,100,000
State
$0
$0
$12,750,000
$12,750,000
RTA
$0
$20,850,000
$0
$20,850,000
Service Board / Local
$0
$0
$0
$0
Total
$2,000,000
$20,850,000
$20,850,000
$43,700,000

PMO:

Total Project Budget^

$45,250,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Aug 2022

End Date

Aug 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is in the design phase. The National Environmental Policy Act (NEPA) process has been completed. The design is progressing and is currently at 30% completion. Pace and Metra held an open house in January to get the community’s feedback on the design alternatives for the new Transportation Center. Community engagement is ongoing.

Last Updated 06.22.2023

+ Hickory Creek Station Stations & Passenger Facilities Rail $0 $6,200,000

PROJECT DETAILS

Description:

This project will rehabilitate the Hickory Creek station in Mokena. The project will fund the repair of the depot an the station facilities. Platform work may be included as needed. Additional project elements may include, but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, station lighting upgrades, and other related work as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$6,200,000
$6,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$6,200,000
$7,200,000

Last Updated 12.16.2022

+ Highlands Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will renovate the Highlands station in Hinsdale. The project scope includes the repair or replacement of aging shelter enclosures, station lighting upgrades, and platform renovation work as needed. Additional project elements may include, but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, and other related work as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$750,000
$0
$0
$750,000

Last Updated 12.16.2022

+ Homewood Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

Additional construction funds are provided to this project to complete the rehabilitation of the Homewood Metra Station and associated intermodal facilities on the Metra Electric (ME) Line. The scope of work may include, but is not limited to, general tunnel rehabilitation, tunnel drainage solutions, elevator and stair improvements, the addition of a pedestrian ramp into the tunnel on the west end of the station, platform improvements, warming shelter, and head house improvements, and improvements to the Pace and Amtrak facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$7,717,185
$0
$0
$7,717,185

PMO:

Total Project Budget^

$23,278,976

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2021

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The parking lot with 53 parking spaces was completed. The 100% station design review was completed in this reporting period by Metra and their PMO. The General Contractor was given NTP in March, and crews have mobilized on site with site prep underway as well as push submittals for long lead time items.

Last Updated 06.22.2023

+ Hubbard Woods Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project includes the rehabilitation of the historic north head house, replacement of the platforms, construction of a pedestrian bridge, installation of elevators to the platforms and platform shelters. Design engineering services for the station rehabilitation is currently underway.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$17,000,000
$0
$0
$17,000,000

Last Updated 12.16.2022

+ Indian Hill Station Stations & Passenger Facilities Rail $0 $1,300,000

PROJECT DETAILS

Description:

New Stair access and New Elevator at East (Inboound). Rehab Tunnel, Rehab Historic Canopies and wind breaks, Rehab Historic Depot for ADA access, tuck point masonry as required, New ADA ramp near Depot, Peel and Pave at Parking (110,000sf)

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$1,300,000
$1,300,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$1,300,000
$1,300,000

Last Updated 12.16.2022

+ Kedzie Station-Retaining Wall Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will fund the repair of a retaining wall and staircase located at the entrance to the Kedzie station on the UP-W Line. The retaining wall is integral to the station and needs to be repaired to improve safety and avoid additional damage to the infrastructure of the station.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$250,000
$0
$0
$250,000

Last Updated 12.16.2022

+ Kenilworth Station Stations & Passenger Facilities Rail $4,000,000 $4,000,000

PROJECT DETAILS

Description:

This project will rehabilitate the Kenilworth station facility. The project scope includes extensive repairs to the station depot, including tuckpointing, masonry restoration, and roof tile repairs. Additional project elements may include but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, entrance staircase repairs, and other related work as needed. This is a multi-year, multi-phase project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$4,000,000
$0
$4,000,000
Service Board / Local
$0
$0
$0
$0
Total
$1,200,000
$4,000,000
$0
$5,200,000

Last Updated 12.16.2022

+ LaGrange Road Station Stations & Passenger Facilities Rail $900,000 $900,000

PROJECT DETAILS

Description:

This project consists of the rehabilitation of the LaGrange Road station facility in LaGrange along the BNSF line. The scope of work may include, but is not limited to, replacing the station depot and windbreak roofs, renovating the station depot heating and ventilations systems, brick and stone repairs and tuckpointing, and refinishing the interior of the station depot. Additional project elements include, but are not limited to, sidewalk accessibility improvements, bicycle facility upgrades, and drainage repairs.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$900,000
$0
$900,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,710,000
$900,000
$0
$2,610,000

Last Updated 12.16.2022

+ Luminous Platform Signs Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

The scope of work would include the design, fabrication, installation, and 3 years of warranty and maintenance of thin panel LED, luminous platform signs at up to six Metra stations. Training for Metra staff for the ongoing troubleshooting and operations of the new signs, and training of Metra staff and forces for the potential installation of future phases of luminous signs would also be included. Limited user testing and customer survey evaluations would also be included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$141
$0
$0
$141

Last Updated 12.16.2022

+ Millennium Station-MEP Upgrades Support Facilities & Equipment Rail $3,400,000 $3,400,000

PROJECT DETAILS

Description:

This project will fund upgrades to the aging Mechanical, Electrical, and Plumbing (MEP) systems at the Millennium Station, which is the downtown Chicago terminal of the Metra Electric (ME) Line. The scope of work may include, but is not limited to, replacement of the boiler system, replacement of the HVAC, upgrading MEP components, the installation of drainage solutions, related engineering design services, and other activities as needed. This is a multi-year, phase-funded project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$3,400,000
$0
$3,400,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$800,000
$3,400,000
$0
$4,200,000

Last Updated 03.16.2023

+ Naperville Station Stations & Passenger Facilities Rail $0 $350,000

PROJECT DETAILS

Description:

This project will fund improvements to the Naperville station facility that also serves as an Amtrak train station. The canopy roof west of station depot is in disrepair and will be replaced with a new cantilevered canopy. The project will also improve or replace stair enclosures based on surveyed conditions. Customer amenities will be enhanced by expanding waiting areas, the installation of additional bicycle racks, and the replacement of the exisiting shelters over the bicycle parking areas.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$350,000
$350,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$350,000
$350,000

Last Updated 12.16.2022

+ Ogilvie Station Tile Replacement Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will replace tile flooring in the Ogilvie Transportation Center concourse. This project will install vapor barriers and replace existing floor tiles with new slip-resistant floor tiles where necessary.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$250,000
$0
$0
$250,000

Last Updated 12.16.2022

+ Olympia Fields Station Stations & Passenger Facilities Rail $7,270,000 $19,670,000

PROJECT DETAILS

Description:

This project will renovate the Olympia Fields station facility, including replacement of aging shelter enclosures, station lighting upgrades, platform renovation work, and pedestrian tunnel painting and sealing as needed. Additional project elements may include, but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, bench repairs, and other related work as needed. The Olympia Fields station will be made fully ADA-compliant.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$12,400,000
$12,400,000
State
$0
$0
$0
$0
RTA
$0
$7,270,000
$0
$7,270,000
Service Board / Local
$0
$0
$0
$0
Total
$0
$7,270,000
$12,400,000
$19,670,000

Last Updated 03.16.2023

+ Parking Lot Improvements Stations & Passenger Facilities Rail $750,000 $4,220,000

PROJECT DETAILS

Description:

This project will fund major parking lot renovations throughout the system. Parking lots have a shorter useful life than stations, therefore, must be overhauled even if the station does not require rehabilitation. Project activities may include but are not limited to, parking surface grinding, asphalt peeling, asphalt resurfacing, blacktop seal coating, patch repairs, new or replacement signage, and the repair or replacement of collection boxes as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$750,000
$3,470,000
$4,220,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$500,000
$750,000
$3,470,000
$4,720,000

Last Updated 12.16.2022

+ Passenger Information Electrical, Signal & Communications Rail $0 $0

PROJECT DETAILS

Description:

The current General Electric announcement system has become outdated and there are no upgrades available. This project will include, but is not limited to, the purchase and installation of LCD displays and associated communications equipment throughout the Metra system. This project will allow for more timely information on arriving trains and allow for improvements including digital LCD displays and automated announcements. The displays could show train(s) arriving at the station, estimated time of arrival, stops made by the train, and any service alerts that may influence service.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,223,788
$0
$0
$1,223,788

Last Updated 12.16.2022

+ Peterson Ridge New Station Stations & Passenger Facilities Rail $2,500,000 $2,500,000

PROJECT DETAILS

Description:

The new station in the Edgewater neighborhood of Chicago will be built to modern standards and feature a platform-length canopy and a heated headhouse. Four ADA-compliant pedestrian ramps and six staircases will provide numerous access points that are accessible to all. A landscaped plaza with benches and bicycle parking will be installed at the station entrance. A passenger drop-off drive aisle, five accessible parking stalls, and 50 parking stalls will be constructed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$2,500,000
$0
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$200,000
$2,500,000
$0
$2,700,000

PMO:

Total Project Budget^

$22,829,765

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jul 2021

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Design for the new station was completed. The contracts for construction management and construction contractor were procured and awarded in June and July 2021, respectively. Notice to Proceeds were issued in June 2021 for the Construction Manager and August 2021 for the Construction Contractor. Construction is in progress and continues with the construction contractor working on platform level mechanical and electrical work, as well as structural work as Union Pacific continues to perform flagging activities for the station construction. The contractor will begin shortly with repairing and reinforcing the overpass next to the station. This includes rehabilitating and/or replacing elements of the Ridge Avenue bridge related to structural and concrete wall elements.

Last Updated 06.22.2023

+ Platform Improvements Stations & Passenger Facilities Rail $6,800,000 $36,960,000

PROJECT DETAILS

Description:

This project is part of Metra’s ongoing effort to bring commuter rail stations into compliance with the
requirements of the Americans with Disabilities Act (ADA) of 1990. The project will focus on
platform and platform access routes, as necessary.
Wherever platform work is undertaken, the existing platforms will be rehabilitated in order to allow
deteriorated tactile surfaces to be replaced with new ADA-compliant “truncated dome” type surfaces.
FY 2020 Federal funds and 2020 Illinois PAYGO funds will be used for construction of new platforms,

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$800,000
$15,650,000
$16,450,000
State
$0
$6,000,000
$14,510,000
$20,510,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,500,000
$6,800,000
$30,160,000
$41,460,000

PMO:

Total Project Budget^

$6,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Sep 2020

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Platform work at Chicago-Ridge, Willow Springs, Mundelein, Jefferson Park, Barrington Station, Franklin Park, New Lenox, and West Hinsdale were completed. Work continued with the 103rd Street station platform and is at 40% complete.

Last Updated 06.22.2023

+ River Forest Station Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will rehabilitate the River Forest station and associated retaining walls that are located along the Union Pacific West (UP-W) Line. The historic station was originally constructed in 1915 and is currently inaccessible. The project scope includes extensive repairs to the entrance ramps, retaining walls, and platforms. Additional project elements may include but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, entrance staircase repairs, and other related work as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$900,000
$0
$0
$900,000

Last Updated 12.16.2022

+ Rogers Park Station Stations & Passenger Facilities Rail $6,250,000 $33,250,000

PROJECT DETAILS

Description:

This project will completely rehabilitate the northern-most Metra station in Chicago. The Rogers Park station is located on the Union Pacific North (UP-N) Line atop a retaining wall section that was originally constructed in 1916. The project scope includes extensive repairs to the station depot and entrance ramps and shelters. Station lighting upgrades and platform renovation work will be completed as needed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$26,130,000
$26,130,000
State
$0
$0
$870,000
$870,000
RTA
$0
$6,250,000
$0
$6,250,000
Service Board / Local
$0
$0
$0
$0
Total
$1,400,000
$6,250,000
$27,000,000
$34,650,000

Last Updated 03.16.2023

+ Round Lake Station Stations & Passenger Facilities Rail $100,000 $1,975,000

PROJECT DETAILS

Description:

To accommodate the Cedar Lake Road Realignment project led by Lake County, portions of the Round Lake station will have to be relocated and reconstructed. The Cedar Lake Road will bisect the station's platform as they are currently located, therefore, the platforms will need to be rebuild due east. Lake County will fund the station infrastructure components that are directly impacted by the project in full. Metra is taking the opportunity to reevaluate the station site plan and to consider Metra-funded improvements. Funds programmed in 2022 will finance engineering and design services.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$100,000
$1,875,000
$1,975,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,500,000
$100,000
$1,875,000
$3,475,000

Last Updated 12.16.2022

+ Shelters Stations & Passenger Facilities Rail $2,000,000 $4,200,000

PROJECT DETAILS

Description:

This project will fund the installation of shelters at stations across the system, which will provide on-demand heat. Specific locations are to be determined, based on existing conditions and demand. Shelters will be pre-fabricated structures and may include on-demand heating elements.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$2,200,000
$2,200,000
State
$0
$2,000,000
$0
$2,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,500,000
$2,000,000
$2,200,000
$6,700,000

PMO:

Total Project Budget^

$3,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2020

End Date

Dec 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Aluminum shelters continue to be installed throughout the system including planned shelters at Morton Grove, Western Ave., 67th St., and 83rd St. stations. The Woodstock station design is at 90% design and proceeding to 100% final design. Design for new station shelters are at 30% design.

Last Updated 06.22.2023

+ Solar Canopies Stations & Passenger Facilities Rail $300,000 $300,000

PROJECT DETAILS

Description:

Metra will investigate the feasibility of erecting solar canopy systems at Metra-owned stations and parking lots. Metra will study the benefits and costs of offering electric vehicle charging stations that utilize power derived from solar canopies positioned above parking stalls. Project activities include but are not limited to feasibility studies, site surveys, professional services, preliminary engineering, and construction activities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$300,000
$0
$300,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$300,000
$0
$300,000

Last Updated 12.16.2022

+ South Shore Station Stations & Passenger Facilities Rail $0 $380,000

PROJECT DETAILS

Description:

This project will provide construction funds to rehabilitate the South Water Street Station access points and station facility along the Metra Electric. The repair work may include, but is not limited to, the replacement of floors and the suspended ceiling in the waiting area, updated lighting fixtures, restroom updates, and upgraded heating and air conditioning.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$380,000
$380,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$380,000
$380,000

Last Updated 12.16.2022

+ South Water St. Station Stations & Passenger Facilities Rail $8,000,000 $8,000,000

PROJECT DETAILS

Description:

This project will provide construction funds to rehabilitate the South Water Street station access points and station facilities along the Metra Electric. The repair work may include, but is not limited to, replacement of floors and the suspended ceiling in the waiting area, updated lighting fixtures, restroom updates, and upgraded heating and air conditioning.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$8,000,000
$0
$8,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$8,000,000
$0
$8,000,000

Last Updated 03.16.2023

+ Station ADA Improvements Stations & Passenger Facilities Rail $1,000,000 $3,110,000

PROJECT DETAILS

Description:

Project funds will be used to assess previously identified site and building conditions that are not compliant with ADA Accessibility codes and regulations. The project will fund the design and construction of corrective solutions.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,000,000
$2,110,000
$3,110,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,300,000
$1,000,000
$2,110,000
$6,410,000

Last Updated 12.16.2022

+ Station Improvements Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

State of good repair (SOGR) deficiencies at Metra stations that have been previously identified will be addressed by this project. Repair costs, labor, and construction materials will be funded by this annual project. Specific activities may include but are not limited to, the repair or replacement of roofs, masonry improvements, and tuck-pointing, door and window replacement, concrete repair work, improvements to interior spaces, replacement or repair of lighting, drainage improvements, and repairs to exterior station elements.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$800,000
$0
$0
$800,000

Last Updated 12.16.2022

+ Systemwide Station Signs Stations & Passenger Facilities Rail $0 $7,500,000

PROJECT DETAILS

Description:

This project will replace all Metra station identification throughout the Metra system. These signs were installed in the early 1980s and are reaching the end of useful life. The new signs will be designed to comply with the Americans with Disabilities Act (ADA).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$7,500,000
$7,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,500,000
$0
$7,500,000
$9,000,000

Last Updated 12.16.2022

+ Ticket Vending Machines Support Facilities & Equipment Rail $33,510,000 $43,250,000

PROJECT DETAILS

Description:

This project is the first phase of installing up to 310 ticket vending machines (TVMs) at selected stations throughout the Metra system to provide added amenities to Metra customers. The TVMs will offer a variety of ticket purchasing options and make purchasing tickets faster, easier, and more convenient for our customers. The TVMs will be fully ADA-accessible and will offer the ability to purchase tickets using contactless cards and mobile wallet applications and will no longer need to insert debit/credit cards into the machine.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$10,710,000
$0
$10,710,000
State
$0
$22,800,000
$9,740,000
$32,540,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$33,510,000
$9,740,000
$43,250,000

PMO:

Total Project Budget^

$12,650,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2022

End Date

Dec 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is currently in the production phase. The manufacturing of the first 100 TVMs is in progress. Two machines were delivered to Metra and System Integration Testing was performed. The next four machines are scheduled to be delivered to Metra by the end of May. Those machines will be used for the pilot deployment at Union Station. Metra work forces are preparing the various site locations for installation of TVMs by performing electrical work and pouring/repairing concrete pads.

Last Updated 06.22.2023

+ TROI - NET Station Displays Support Facilities & Equipment Rail $4,899,917 $5,399,917

PROJECT DETAILS

Description:

The TROI-Net Station Displays Project is the design and rollout of the next generation of Metra's VIS Signs as they reach the end of their useful life and require replacement. Instead of one VIS Sign per station, TROI-Net Station Displays will be installed at more than one location at most stations. To meet accessibility requirements and like the current VIS Signs, TROI-Net Station Displays will provide the visual part of Metra's Audio/Visual announcements at stations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$500,000
$500,000
$1,000,000
State
$0
$3,700,000
$0
$3,700,000
RTA
$0
$699,917
$0
$699,917
Service Board / Local
$0
$0
$0
$0
Total
$3,000,000
$4,899,917
$500,000
$8,399,917

Last Updated 06.22.2023

+ University Park Station-Ramps & Canopies Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project will provide construction funds for the rehabilitation of the University Park station along the Metra Electric (ME) Line. The station will be rehabilitated to be ADA compliant and the existing pedestrian ramps will be renovated. Additional construction funds will be provided in future programs.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,200,000
$0
$0
$1,200,000

Last Updated 12.16.2022

+ Van Buren St. Station Stations & Passenger Facilities Rail $0 $15,624,000

PROJECT DETAILS

Description:

A complete renovation of the downtown Chicago terminal station will rehabilitate the existing historic waiting rooms, replace the roof assembly while maintaining the green roof, and will replace the pedestrian tunnel in the park. A new 'pop-up' entrance in Grant Park will add a new access stair case and elevator and add an ADA-compliant ramp connecting to the pedestrian bridge. The pedestrian tunnel under Michigan Ave will be waterproofed and a new elevator will be added to the Jackson Blvd platform.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$15,624,000
$15,624,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$15,624,000
$15,624,000

PMO:

Total Project Budget^

$48,126,300

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2018

End Date

Dec 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Metra awarded the consultant contract for station concept design. The concept design is at 15% completion and on hold pending completion of lakefront ordinance protection, NEPA, and environmental processes. Documents are being prepared to be submitted for lakefront ordinance for approval. Environmental and NEPA work is ongoing.

Last Updated 06.22.2023

+ Waukegan Station Stations & Passenger Facilities Rail $500,000 $500,000

PROJECT DETAILS

Description:

This project will rehabilitate the inbound and outbound platforms. Platform light poles and fixtures on both platforms will be replaced. New on-platform shelters will be removed and reinstalled. Project activities may also include renovations to the interior of the station depot.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$500,000
$0
$500,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$500,000
$0
$500,000

Last Updated 12.16.2022

+ West Chicago Station Stations & Passenger Facilities Rail $8,400,000 $14,600,000

PROJECT DETAILS

Description:

The project involves the rehabilitation of the West Chicago Station facility. Work to be done may include, but is not limited to, rehabilitation of the access tunnels, stairs, ramps, waiting room, platforms, lighting, retaining wall improvements, and painting. Project funds will be used for construction as design and engineering have been accomplished under a separate project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$450,000
$450,000
State
$0
$0
$5,750,000
$5,750,000
RTA
$0
$8,400,000
$0
$8,400,000
Service Board / Local
$0
$0
$0
$0
Total
$300,000
$8,400,000
$6,200,000
$14,900,000

Last Updated 03.16.2023

+ West Hinsdale Station Stations & Passenger Facilities Rail $0 $5,000,000

PROJECT DETAILS

Description:

This project will provide design engineering funds for platform rehabilitation of the West Hinsdale station facility along the BNSF Line. The station will be rehabilitated to be ADA compliant. Construction funds are provided in later years

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$5,000,000
$5,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$0
$5,000,000
$6,000,000

Last Updated 12.16.2022

+ Western Ave Station BNS Stations & Passenger Facilities Rail $0 $0

PROJECT DETAILS

Description:

This project funds the design and renovation of the Western Avenue station facility in the West Side of Chicago along the BNSF Line. The project scope may include, but is not limited to, the repair or replacement of aging shelter enclosures, station lighting upgrades, and platform renovation work. Additional project elements may include, sidewalk repairs, upgraded bike facilities, landscape enhancements, and other related work as needed. The station will be made fully ADA accessible upon completion of the project.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$300,000
$0
$0
$300,000

Last Updated 12.16.2022

+ Westmont Station Stations & Passenger Facilities Rail $18,900,000 $18,900,000

PROJECT DETAILS

Description:

This project involves installing a new heated-platform technology that the village requested. The heated platform will reduce the amount of snow and ice build-up during winter months, nearly eliminating the need for manual snow removal.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,900,000
$0
$1,900,000
State
$0
$17,000,000
$0
$17,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,000,000
$18,900,000
$0
$19,900,000

Last Updated 03.16.2023

+ CTA Rail Yard Improvements System $6,819,867 $6,819,867 $259,324,412 $252,504,545

Description:

Improvements to CTA Rail Yards

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Facilities Critical Needs ‐ Harlem Yard Water Tower Demolition Support Facilities & Equipment Rail $2,869,867 $2,869,867

PROJECT DETAILS

Description:

Demolotion of the Harlem Water Tower at the Harlem Yard.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$2,869,867
$0
$2,869,867
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$2,869,867
$0
$2,869,867

Last Updated 03.15.2023

+ Rail Facilities (Yards) Support Facilities & Equipment Rail $3,950,000 $3,950,000

PROJECT DETAILS

Description:

Funding will provide for the upgrades to be made to the rail yard system infrastructure including track and associated components, fire suppression, and lighting. Other facility deficiencies will be address including but not limited to: boilers, trash collection systems, roofs, windows, pavement replacement, rail hoist replacement, inspection pit rehabilitation, roof replacements, and heating and ventilation air conditioning systems. Overall this project will allow CTA to address multiple state of good repair needs at rail yard facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$3,950,000
$0
$3,950,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,950,000
$3,950,000
$0
$7,900,000

Last Updated 12.16.2022

+ Rail Facilities - Des Plaines Yard Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

The Rail Facilities State of Good Repair Program focuses on critical improvements at CTA rail yards, which include improvements to the yard infrastructure itself (ties, rail, fasteners, ballast, contact rail etc.) as well as the yard fire suppression systems and lighting. The Des Plaines Yard project will include the reconstruction and reconfiguration of the inner and outer lead tracks, including associated special trackwork. Replacement and reconfiguration of the special trackwork in the east yard storage, including the road crossings to the yard shops will also be completed.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$22,858,137

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Mar 2022

End Date

Feb 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The design for this project has been completed in December 2022. CTA developed a procurement package for construction and it is currently out for bid.

Last Updated 06.22.2023

+ CTA Railcar Overhauls Rail $26,899,057 $214,245,363 $216,027,620 $1,782,257

Description:

Quarter-life overhaul of 5000-series rail cars and life-extending overhauls of older 2600 and 3200-series rail cars

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $21,899,057 $71,172,694

PROJECT DETAILS

Description:

5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter‐Life Overhaul on the 5000‐Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$15,299,632
$15,299,632
State
$0
$20,000,000
$33,974,005
$53,974,005
RTA
$0
$0
$0
$0
Service Board / Local
$0
$1,899,057
$0
$1,899,057
Total
$11,335,000
$21,899,057
$49,273,637
$82,507,694

PMO:

Total Project Budget^

$400,000,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Oct 2020

End Date

Jan 2026

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

As of the end of April 2023, 266 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 06.22.2023

+ Life extending Overhaul 2600/3200 Series Rolling Stock Rail $0 $118,072,669

PROJECT DETAILS

Description:

Life extending overhaul on the 258 3200 Series and 300 2600 Series cars. Work on these cars will focus on major systems starting with the proplusion/powering.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$118,072,669
$118,072,669
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$118,072,669
$118,072,669

Last Updated 12.16.2022

+ Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of
the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in
August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery of

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$25,314,552

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2019

End Date

Mar 2022

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 07.10.2022

+ Replace video system 3200 and 5000-Series railcars Rolling Stock Rail $5,000,000 $25,000,000

PROJECT DETAILS

Description:

Replace the existing video system on the 5000-series rail cars which is obsolete and no longer supported by the vendor. Replace existing video system on the 3200-series rail cars with a more reliable system. Useable components removed from the 3200s will be re-used to support the same system on the 2600-seriese rail cars.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$5,000,000
$20,000,000
$25,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$5,000,000
$20,000,000
$25,000,000

Last Updated 12.16.2022

+ CTA Railcar Purchase Rail $40,029,912 $227,877,010 $1,008,519,862 $780,642,852

Description:

Replacement of 2600- and 3200-series rail cars

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase Rail Cars - 7000 Series (Base Order 400) Rolling Stock Rail $35,429,912 $97,714,823

PROJECT DETAILS

Description:

Purchase Rail Cars - 7000' Series (Base Order 400)
- Program funds will provide for the continued cash needs and obligation provisions as identified in the contract documents for the 7000' series rail car Base contract order of 400 cars.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$20,429,912
$62,284,911
$82,714,823
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$15,000,000
$0
$15,000,000
Total
$78,756,670
$35,429,912
$62,284,911
$176,471,493

PMO:

Total Project Budget^

$713,703,634

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Apr 2016

End Date

May 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Status conferences continued with CRRC to address/track various items. Revenue service testing ended and production deliveries begun in this reporting period. CTA inspection personnel continue working in China and continue to conduct welded subassembly checks and production car body shell inspections for production cars. There are approximately 22 assembled car body shells, and 58 cars total in various stages of completion. Final assembly continues on 48 cars in the US, with the Chicago facility up to car 7094. CTA has accepted 44 of the cars thus far for revenue service.

Last Updated 06.22.2023

+ Rail Cars - 7000 Series Option One (156 cars) Rolling Stock Rail $0 $0

PROJECT DETAILS

Description:

Rail Cars - 7000 Sers Option One 156
- CIP funds provides for initial cash needs and obligation anticipated for the Option One order to procure an additional 156 new 7000' series rail cars.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$294,431,108
$0
$0
$294,431,108

Last Updated 03.15.2023

+ Rail Cars - 7000 Series Option Two (100 cars) Rolling Stock Rail $4,600,000 $130,162,187

PROJECT DETAILS

Description:

CIP funds provides for initial cash needs and obligationanticipated for the Option Two order to procure an additional 100 new 7000' series rail cars.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$4,600,000
$125,562,187
$130,162,187
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$4,600,000
$125,562,187
$130,162,187