Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Sort descending Priority Project Mode 2024 Funding 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Pace Paratransit Vehicles - Expansion Bus $0 $0 $13,000,000 $13,000,000

New Dial-a-Ride and ADA vehicles for aging population

+ Pace Paratransit Vehicles - Replacement Bus $1,801,859 $31,094,850 $86,508,000 $55,413,150

Replacement of vehicles reaching useful life

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Electric Paratransit Vehicles Rolling Stock Bus $0 $0

Project Details

Description
This project will fund the purchase of electric paratransit vehicles.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,000 $0 $0 $1,000,000

Last Updated 06.22.2023

+ Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,801,859 $31,094,850 ✔︎

Project Details

Description
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,801,859 $29,292,991 $31,094,850
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,388,134 $1,801,859 $29,292,991 $38,482,984

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$69,991,388
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 152 vehicles and the remaining are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are ongoing and are expected to be executed in Q4-2023 for the community vehicle program.

Last Updated 12.14.2023

+ Pace Pedestrian Infrastructure/Shelters/Signs Bus $0 $0 $30,500,000 $30,500,000

Shelters, pedestrian access, and completion of conversion to posted stops

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,550,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ 2020 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,330,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ 2021 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$600,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 12.14.2023

+ 2022 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 ✔︎

Project Details

Description
Bus Stop Shelters - Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,125,000 $0 $0 $1,125,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$425,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 12.14.2023

+ 2022 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0

Project Details

Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $425,000 $0 $0 $425,000

Last Updated 12.16.2022

+ Pace Pulse Infrastructure Bus $59,141,334 $59,141,334 $82,561,000 $23,419,666

Enhance Pulse service

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Pulse 95th Street Stations & Passenger Facilities Bus $19,567,500 $19,567,500

Project Details

Description
Design and construction of stations of the Pulse 95th Rapid Transit Line. The project corridor is approximately 12.4 miles in length and runs east-west between the CTA Red Line 95th/Dan Ryan Station in Chicago and Moraine Valley Community College in Palos Hills primarily routed along 95th Street, as well as several other roadways in Bridgeview, Chicago Ridge, Hickory Hills, and Palos Hills. The proposed line would include connections to other transit services including the CTA Red Line 95th/Dan Ryan Station and other CTA routes, other Pace bus routes, Metra Rock Island District Line Longwood Station, Metra Southwest Service, and Oak Lawn Patriot Station. As Pace’s third anticipated Pulse line, the 95th Street service will improve connectivity and increase transit service levels through higher frequencies, travel time savings, and station amenities. The Pulse 95th Street Line will connect to the Pulse Halsted Line, and eventually to the Pulse Harlem and Cicero Lines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $15,654,000 $0 $15,654,000
State $0 $3,913,500 $0 $3,913,500
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,464,000 $19,567,500 $0 $21,031,500

Last Updated 12.14.2023

+ Pulse Halsted Stations & Passenger Facilities Bus $39,573,834 $39,573,834

Project Details

Description
Architectural/Engineering Design and Construction of stations, vertical markers, and other elements of the Pulse Halsted Arterial Rapid Transit Line. The project corridor consists of approximately 9 miles of South Halsted Street, from the Pace Harvey Transportation Center to 95th Street, and includes the segment of 95th Street that provides a connection to the CTA Red Line 95th/Dan Ryan station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $32,137,334 $0 $32,137,334
State $0 $7,436,500 $0 $7,436,500
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $500,000 $39,573,834 $0 $40,073,834

Last Updated 12.14.2023

+ Pace Regional Transit Signal Priority (RTSP) Bus $0 $0 $34,685,929 $34,685,929

Expand Transit Signal Priority installations region-wide

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 ✔︎

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,314,071 $0 $0 $4,314,071

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th w

Last Updated 12.14.2023

+ Pace Security, Computer, Software, and Office Systems Upgrades Bus $2,513,505 $10,513,505 $31,936,495 $21,422,990

Upgrade systems to provide enhanced asset protection and business systems

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Computer Systems - Hardware & Software Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with a rebid for the procurement of digital screens for the interior of the buses due to low responses. Additional tasks will be added throughout the duration of this project.

Last Updated 12.14.2023

+ Mobility as a Service Software Support Facilities & Equipment Bus $0 $0

Project Details

Description
Purchase of Mobility as a Service (MaaS) software
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,398,000 $0 $0 $2,398,000

Last Updated 12.14.2023

+ Onboard Digital Screens Support Facilities & Equipment Bus $2,513,505 $10,513,505

Project Details

Description
Purchase and install digital screens inside existing buses to display passenger information, such as next-stop announcements, detour notices, and passenger notices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,513,505 $8,000,000 $10,513,505
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,963,505 $2,513,505 $8,000,000 $12,477,010

Last Updated 12.14.2023

+ Pace Support Equipment/Non-Revenue Vehicles Bus $0 $0 $22,450,000 $22,450,000

Facility and system maintenance equipment and vehicles

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Support Equipment - Non-Revenue Vehicles Support Facilities & Equipment Bus $0 $0

Project Details

Description
Support Equipment/Non-Revenue Vehicles - Projects in 2021 include the purchase of 18 compact SUVs and one minivan with wheelchair ramp.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Pace Uncategorized Projects - Pace Bus $0 $0 $0 $0

These are a miscellaneous set of Capital projects undertaken by Pace

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Transit Asset Management N/A Bus $0 $0

Project Details

Description
Transit Asset Management - Consulting services for TAM Plan updates, including condition assessments of Pace facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Unanticipated Capital N/A Bus $0 $0

Project Details

Description
Contingency funding for existing projects or small new projects
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

Last Updated 12.16.2022

+ Vision Plan Implementation Study N/A Bus $0 $0

Project Details

Description
Vision Plan Implementation Study - Consulting services to include a system-wide market analysis and proposed service restructuring plan that will address the goals and objectives of Pace’s Driving Innovation Strategic Vision Plan.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,000 $0 $0 $1,000,000

Last Updated 12.16.2022

+ Pace Vanpool Vehicles - Replacement Bus $0 $0 $12,640,000 $12,640,000

Replacement of vans reaching useful life

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Purchase 7-passenger Vanpool Vehicles Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Vanpool Vehicles - Pace plans to purchase 164 replacement 17'-20' vans including associated equipment and services (Buy America audit and inspections) for vanpool services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,899,800
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vans will be utilized in the six county Pace service area. To date a total of 25 vans have been ordered, all have been received. Pace has executed a contract to install OEM passenger running boards on the first order of 25 vans. All the running boards have been installed and are in the active fleet. Pace continued to work on an action plan for ordering more vehicles based on projected needs under a separate contract. This will be the final update on this project.

Last Updated 12.14.2023

+ RTA RTA Funding Program(s) System $0 $0 $0 $0

Projects and programs undertaken by RTA

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ RTA TBD Systemwide System $0 $0

Project Details

Description
Projects TBD
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.16.2022