Planning Programs and Projects

This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus. 

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

?

This search filters based on details within the Planning Project. The search box below allows users to search by Planning Project name.

Year Project Title Program Sort descending Project Type Project Partner Budget Funding Source(s) Status
+ Midlothian Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Midlothian $980,000
  • RTA
  • Federal
Completed

Project Details

Related Reports

Not Available

Description

This project consisted of access improvements in the Midlothian Metra station area including removal and replacement of 8,542 square feet of sidewalk, installation of 1,268 feet of crosswalks, installation of ADA handicapped panels/ detectable warnings at 68 locations, and pedestrian lighting improvements on 147th Street from Pulaski to Central Park.

Current Activities

Construction of this project is complete.

Funding Amounts by Source
Source Amount
RTA $196,000
Federal $784,000

Last Updated 01.10.2022

+ Melrose Park Metra Station and Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Melrose Park $374,000
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will add various pedestrian improvements to the Broadway Avenue corridor, north of the Melrose Park Metra Station, which is served by Pace Route 303. Pace Routes 309 and 313 also intersect the corridor at Lake Street. Improvements that include high-visibility crosswalks and decorative-marked intersections will be installed at three intersections with one of the intersections also receiving curb bump-outs and relocation of a bus stop along with bus shelters at Main and Broadway. Bike parking will also be added at the Metra station.

Current Activities

 Construction is complete. Working on getting closeout documentation from IDOT.

Funding Amounts by Source
Source Amount
RTA $18,700
Local $56,100
Federal $299,200

Last Updated 01.09.2024

+ Niles Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Niles $795,721
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct sidewalk infill along Golf Road and Milwaukee Avenue in Niles, near the Golf Mill Shopping center, a major transfer center for Pace. Both Golf Road and Milwaukee Avenue are principal arterials currently without complete sidewalks and the new sidewalk will vary in width between 5 and 7 feet. The section of Golf Road will complete sidewalks from Milwaukee Avenue going east and will comprise nearly 4,000 linear feet in new sidewalk. The Milwaukee Avenue sidewalk improvements will be from Golf Road going southwest and will comprise nearly 2,400 feet of sidewalk infill. A new crosswalk with pedestrian signal and push button will be also installed across Milwaukee Avenue at the Golf Mill main entrance.

Current Activities

IDOT has approved the engineering agreements and scheduled a letting in January 2024.

Funding Amounts by Source
Source Amount
RTA $79,572
Local $79,572
Federal $636,577

Last Updated 01.09.2024

+ La Grange Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit La Grange $385,100
  • RTA
  • Federal
Completed

Project Details

Related Reports

Not Available

Description

This project provides improvements to the La Grange, Stone Avenue station on the BNSF commuter rail line that include ADA-accessible pathways to platforms, crosswalks on surrounding streets, improved accessibility to commuter parking, added bicycle parking, and improved kiss-and-ride areas.

Current Activities

This project is complete.

Funding Amounts by Source
Source Amount
RTA $77,000
Federal $308,100

Last Updated 02.15.2021

+ Northlake Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Northlake $229,920
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will repair a gap in the sidewalk connectivity along Wolf Road near North Avenue. Repairs will allow pedestrians to directly cross the intersection of Wolf Road and an access driveway to a shopping center. This section of Wolf Road is served by Pace Route 309 and Routes 318 and 320 operate nearby on North Avenue. Two bus shelters will also be constructed at the stops just to the south of this intersection as part of the project.

Current Activities

Consultant has been selected to complete Phase II Engineering. Waiting for IDOT to approve the engineering agreement.

Funding Amounts by Source
Source Amount
RTA $11,496
Local $34,488
Federal $183,936

Last Updated 04.20.2023

+ Calumet Park Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Calumet Park $264,126
  • RTA
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct bicycle facilities along 124th Street to better facilitate safe access between bus transit services along Halsted Street to the Ashland Metra station at Ashland Avenue. Additional improvements include completing a sidewalk gap on 124th Street between Laflin and Bishop Streets and pedestrian improvements to the intersection of 124th Street and Laflin Street.

Current Activities

After a period of delays, the Phase II engineering has resumed.

Funding Amounts by Source
Source Amount
RTA $52,825
Federal $211,301

Last Updated 11.15.2023

+ Evanston Pace and CTA Route Access Improvements Access to Transit Program Pedestrian Access to Transit Evanston $300,481
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will convert all of the bus stops in the City of Evanston from flagged to posted stops and include the installation of ADA compliant bus stop pads. In addition, this project will install shelters, pedestrian signals, truncated domes, and new and replaced sidewalk to further enhance the new bus stops. Shelters are proposed for stops with 20 average daily boardings.

Current Activities

The RTA is working on drafting an IGA amendment to reflect the change in scope of the project. Consultant has been selected, the project has been awarded and work has begun on Phase II Engineering.

Funding Amounts by Source
Source Amount
RTA $30,048
Local $30,048
Federal $240,385

Last Updated 03.29.2024

+ Aurora Transportation Center Access Improvements Access to Transit Program Pedestrian Access to Transit Aurora $995,283
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will create various pedestrian and access improvements to and around the Aurora Transportation Center including entrance modifications at the intersection of Spring Street and the creation of a Kiss and Ride area for passenger drop off. Other improvements include the installation of real time message boards on the platform to indicate train departure/arrival time and track location, installation of bike shelters on the east side of the Metra tracks and at the existing bike racks located along the west side of the platform, and installation of decorative monument signs at the Spring Street and Broadway Avenue entrances. Finally, four commuter transit shelters with heaters will be installed on the platforms and bike lanes along Spring Street, running east and west will be installed to improve access for people using bicycles to access the station.

Current Activities

Last quarter Aurora completed the punchlist items. The shelter lighting is the only outstanding item to complete the job. Lighting expected to be delivered in mid-April.

Funding Amounts by Source
Source Amount
RTA $99,528
Local $99,528
Federal $796,227

Last Updated 03.29.2024

+ Franklin Park Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Franklin Park $890,196
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct bicycle and pedestrian improvements along two corridors in the community: an east-west bicycle route and a north-south pedestrian route that connect the Village’s two Metra stations and three Pace Bus routes to its three industrial areas. Improvements to the bike network will include the installation of eight-foot multi-use paths, on road sharrows, on road dedicated bike lanes, and installation of new signage and path widening along existing paths. The proposed sidewalk improvements on 25th Avenue will provide safe connections from the downtown train stations to the southern industrial area without forcing pedestrians to navigate gaps in the sidewalk network. Employees taking the Pace 303 bus will also benefit from these improvements.

Current Activities

Franklin Park has continued to coordinate with IDOT to get Phase I Engineering approved. All of IDOT's comments have been addressed and approval is pending.

Funding Amounts by Source
Source Amount
RTA $63,169
Local $114,870
Federal $712,157

Last Updated 03.29.2024

+ Palos Heights Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Palos Heights $620,190
  • RTA
  • Federal
Completed

Project Details

Related Reports

Not Available

Description

The project improved access to Pace Routes #383 and #386 by providing new sidewalks and infill sidewalks, crosswalks, and pedestrian signal heads. These improvements provide connections to existing sidewalk networks, a recreational center, and residential, commercial, and office land uses.

Current Activities

The project was completed in summer of 2017.

Funding Amounts by Source
Source Amount
RTA $124,000
Federal $496,190

Last Updated 05.18.2021