Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Sort ascending Status
+ CTA 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $1,899,057 $41,619,579 Behind Schedule

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $33,591,710 $33,591,710
State $0 $0 $6,128,812 $6,128,812
RTA $0 $0 $0 $0
Service Board / Local $0 $1,899,057 $0 $1,899,057
Total $31,335,000 $1,899,057 $39,720,522 $72,954,579

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the end of March 2024, 418 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 04.15.2024

+ Metra Bridge 86 - 78th St Entrance Track & Structure Rail $0 $33,160,000 On Schedule

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $33,160,000 $33,160,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $0 $33,160,000 $48,140,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the bridge and entrance continued to 90% completion. Design is expected to be complete by Q1-2024.

Last Updated 12.14.2023

+ Pace Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,801,859 $31,094,850 On Schedule

Project Details

Description
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,801,859 $29,292,991 $31,094,850
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,388,134 $1,801,859 $29,292,991 $38,482,984

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$69,991,388
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 152 vehicles and the remaining are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are ongoing and are expected to be executed in Q4-2023 for the community vehicle program.

Last Updated 12.14.2023

+ Metra Van Buren St. Station Stations & Passenger Facilities Rail $28,500,000 $28,500,000 On Schedule

Project Details

Description
A complete renovation of the downtown Chicago terminal station will rehabilitate the existing historic waiting rooms, replace the roof assembly while maintaining the green roof, and will replace the pedestrian tunnel in the park. A new 'pop-up' entrance in Grant Park will add a new access stair case and elevator and add an ADA-compliant ramp connecting to the pedestrian bridge. The pedestrian tunnel under Michigan Ave will be waterproofed and a new elevator will be added to the Jackson Blvd platform. The scope of work includes rehabilitation of the stair enclosures and elevator west of Michigan Avenue, replacement of the platforms, new full-length platform canopies, heated warming shelters, construction of a new vendor space at lower level, and all new mechanical, electrical, and plumbing throughout the station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $28,500,000 $0 $28,500,000
Service Board / Local $0 $0 $0 $0
Total $0 $28,500,000 $0 $28,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$48,126,300
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra awarded the consultant contract for station concept design. The concept design is at 15% completion and on hold pending completion of lakefront ordinance protection, NEPA, and environmental processes. Documents are being prepared to be submitted for lakefront ordinance for approval. Environmental and NEPA work is ongoing. The Memorandum of Understanding should be fully executed in Q1 of 2024.

Last Updated 12.14.2023

+ Metra Harvey Transportation Center - Metra Stations & Passenger Facilities Rail $23,770,000 $24,080,000 On Schedule

Project Details

Description
Metra is partnering with Pace to create the Harvey Transportation Center on the Metra Electric line. Metra will utilize funds for platform reconstruction and to construct other enhancements that will make the station ADA accessible, improve the commuter environment, and facilitate intermodal transfers between Pace and Metra.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $310,000 $310,000
State $0 $0 $0 $0
RTA $0 $23,770,000 $0 $23,770,000
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $23,770,000 $310,000 $26,080,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$45,250,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The National Environmental Policy Act (NEPA) process has been completed. The design is progressing and is currently at 30% completion. Pace and Metra held an open house in January to get the community’s feedback on the design alternatives for the new Transportation Center. Community engagement is ongoing.

Last Updated 12.14.2023

+ Metra A-20 (Techny) Interlocker Electrical, Signal & Communications Rail $0 $23,005,000 On Schedule

Project Details

Description
This project provides engineering and construction funds to modernize the A-20 Interlocking near Techny Road in Northbrook on the Milwaukee District North Line. The scope of work includes improving two grade crossings (Shermer and Techny Road), modernizing signals, and improving track between the Morton Grove Station and Deerfield Station. Under this project, work may include adding rail, switches, signals, crossovers, and renewal of track and signal circuits and cables. The project will implement a signal control system that is PTC compatible.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $10,900,000 $10,900,000
State $0 $0 $12,105,000 $12,105,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,690,000 $0 $23,005,000 $31,695,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$19,258,610
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Preliminary engineering work is near completion and a construction Invitation for Bid (IFB) package is ongoing. Once completed, it will be submitted and advertised after the railroad cost sharing agreement is executed and potential grants are awarded.

Last Updated 12.14.2023

+ Metra Platform Improvements Stations & Passenger Facilities Rail $5,820,000 $19,300,000 On Schedule

Project Details

Description
This project is part of Metra’s ongoing effort to bring commuter rail stations into compliance with therequirements of the Americans with Disabilities Act (ADA) of 1990. The project will focus onplatform and platform access routes, as necessary.Wherever platform work is undertaken, the existing platforms will be rehabilitated in order to allowdeteriorated tactile surfaces to be replaced with new ADA-compliant “truncated dome” type surfaces.FY 2020 Federal funds and 2020 Illinois PAYGO funds will be used for construction of new platforms,ADA access improvements, ADA building improvements, and related work at sites to be determined.The West Hinsdale Station on the BNSF Line has been identified as a priority location for platformrehabilitation. However, this project may also include the Oak Lawn Station (SouthWest Service) andthe River Forest Station (Union Pacific West Line). Note that this is a preliminary list of stationsidentified for platform rehabilitation and other locations may be added.FY 2020 PAYGO and Federal funds will be used for construction. Future funding may be required.This project is necessary to bring Metra’s system into compliance with the 1990 ADA.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $5,820,000 $8,760,000 $14,580,000
State $0 $0 $4,720,000 $4,720,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,300,000 $5,820,000 $13,480,000 $30,600,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Platform work at Chicago-Ridge, Willow Springs, Mundelein, Jefferson Park, Barrington Station, Franklin Park, New Lenox, and West Hinsdale were completed. Work continued at 103rd Street station platform and is at 40% complete. Work also begun at the Oak Lawn station and is at 15% complete.

Last Updated 12.14.2023

+ Metra 16th St. Interlocker Electrical, Signal & Communications Rail $12,910,000 $15,660,000 On Schedule

Project Details

Description
This project will replace the 16th Street interlocking with a modern solid-state automated electronic system at a junction with tracks owned by Canadian National (CN) near 16th Street in Chicago. The 16th Street interlocking plant consists of an obsolete manual interlocking with two outdated hand lever machines built in 1901 and 1929. There are no manufacturers of spare or replacement equipment for these machines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $2,750,000 $2,750,000
State $0 $0 $0 $0
RTA $0 $12,910,000 $0 $12,910,000
Service Board / Local $0 $0 $0 $0
Total $66,590,000 $12,910,000 $2,750,000 $82,250,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,055,507
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preliminary design was completed, and CN is waiting on drawings. Bid package documents were developed and design proposals were submitted. The award for the interlocking track and signal upgrades were awarded in October 2022 and activities for signal upgrades design continue.

Last Updated 12.14.2023

+ Metra Vehicles & Equipment Support Facilities & Equipment Rail $2,330,000 $15,410,930 On Schedule

Project Details

Description
This project provides for the purchase of fleet vehicles and equipment utilized by Metra’s various departments to help service and maintain the system. This project includes, but is not limited to, vehicles used for supervision of fieldwork, small pickup trucks, construction equipment, and other vehicles. Project funds will replace and retire vehicles and equipment in Metra's current fleet that has surpassed its useful life.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $2,330,000 $13,080,930 $15,410,930
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,000,000 $2,330,000 $13,080,930 $24,410,930

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Procurement activities are in progress. Metra is waiting on delivery of vehicles, including 23 highway vehicles, 48V service carts, two electric vans, police vehicles, and service vehicles.

Last Updated 12.14.2023

+ Metra Station Displays (TROI Net) Stations & Passenger Facilities Rail $7,900,000 $13,948,200 On Schedule

Project Details

Description
The TROI-Net Station Displays Project is the design and rollout of the next generation of Metra's VIS Signs as they reach the end of their useful life and require replacement. Instead of one VIS Sign per station, TROI-Net Station Displays will be installed at more than one location at most stations. To meet accessibility requirements and like the current VIS Signs, TROI-Net Station Displays will provide the visual part of Metra's Audio/Visual announcements at stations. TROI-Net Station Displays will also provide live train tracking information, customer information messages, and emergency messages to Metra’s customers.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $4,455,200 $6,455,200
State $0 $5,900,000 $0 $5,900,000
RTA $0 $0 $1,593,000 $1,593,000
Service Board / Local $0 $0 $0 $0
Total $7,899,917 $7,900,000 $6,048,200 $21,848,117

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$5,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Displays were ordered for stations and are waiting to be received. Once the displays are delivered, Metra forces will begin the installation.

Last Updated 12.14.2023