Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the December 2023 Project Management Oversight report.
Agency | Project Title | Asset Category | Mode | 2024 Funding | 2024-2028 Funding | Status Sort descending | |||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Metra | Platform Improvements | Stations & Passenger Facilities | Rail | $5,820,000 | $19,300,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project is part of Metra’s ongoing effort to bring commuter rail stations into compliance with therequirements of the Americans with Disabilities Act (ADA) of 1990. The project will focus onplatform and platform access routes, as necessary.Wherever platform work is undertaken, the existing platforms will be rehabilitated in order to allowdeteriorated tactile surfaces to be replaced with new ADA-compliant “truncated dome” type surfaces.FY 2020 Federal funds and 2020 Illinois PAYGO funds will be used for construction of new platforms,ADA access improvements, ADA building improvements, and related work at sites to be determined.The West Hinsdale Station on the BNSF Line has been identified as a priority location for platformrehabilitation. However, this project may also include the Oak Lawn Station (SouthWest Service) andthe River Forest Station (Union Pacific West Line). Note that this is a preliminary list of stationsidentified for platform rehabilitation and other locations may be added.FY 2020 PAYGO and Federal funds will be used for construction. Future funding may be required.This project is necessary to bring Metra’s system into compliance with the 1990 ADA.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Platform work at Chicago-Ridge, Willow Springs, Mundelein, Jefferson Park, Barrington Station, Franklin Park, New Lenox, and West Hinsdale were completed. Work continued at 103rd Street station platform and is at 40% complete. Work also begun at the Oak Lawn station and is at 15% complete.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Purchase 40' Diesel Buses | Rolling Stock | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | 2020 - Elevated Track and Structure Maintenance Systemwide | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Track and structure work was completed, and final billing remains. This will be the final update on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | IT Components & Services | N/A | Rail | $3,100,000 | $5,800,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Purchases various pieces of equipment that will be utilized at Metra Headquarters and outlying Metra facilities. Purchases may include, but are not limited to, replacement of obsolete information technology infrastructure, upgrade network switches, computers and printers, copiers, new and replacement servers, financial system software, and other software.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This is a multiple year and multiple project type of capital project. Purchase orders have been awarded for various computer hardware and software. Hardware has been delivered and installed. Purchase Order Releases for computer hardware and software continue in process and deliveries will continue over the next several years.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Purchase 15-passenger Paratransit Vehicles | Rolling Stock | Bus | $1,801,859 | $31,094,850 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 152 vehicles and the remaining are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are ongoing and are expected to be executed in Q4-2023 for the community vehicle program.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | 2021 - Elevated Track and Structure Maintenance Systemwide | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Station Displays (TROI Net) | Stations & Passenger Facilities | Rail | $7,900,000 | $13,948,200 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The TROI-Net Station Displays Project is the design and rollout of the next generation of Metra's VIS Signs as they reach the end of their useful life and require replacement. Instead of one VIS Sign per station, TROI-Net Station Displays will be installed at more than one location at most stations. To meet accessibility requirements and like the current VIS Signs, TROI-Net Station Displays will provide the visual part of Metra's Audio/Visual announcements at stations. TROI-Net Station Displays will also provide live train tracking information, customer information messages, and emergency messages to Metra’s customers.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Displays were ordered for stations and are waiting to be received. Once the displays are delivered, Metra forces will begin the installation.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Car Rehab (Nippon Sharyo Highliners) | Rolling Stock | Rail | $21,022,000 | $129,067,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project funds the continued rehabilitation of self-propelled electric cars used on the Metra Electric. The cars delivered between 2005 and 2007. This first rehabilitation may include, but is not limited to, repair of the car body structure, interior components, and overhaul of propulsion control systems.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is progressing with procurements for materials and parts ongoing. Four cars have completed the rehab activities, and four cars are almost completed waiting on seats. Two more have just started work under this program. Additional cars will continue with the rehabilitation process.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Green Line Jackson Park Branch Trackwork | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.