Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode Sort descending 2024 Funding 2024-2028 Funding Status
+ Metra Zero-Emissions Locomotives Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
Metra investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure locomotives that produce zero mobile emissions. This multi-year, multi-phase project will acquire state-of-the-art technologies and pilot their performance capabilities given Metra’s track profile and the Chicago region’s inclement weather patterns. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxides (NOx) emissions by more than 30 tons per year, thus significantly reducing the agency’s greenhouse gas footprint and greatly improving air quality in the region. Funds programmed in 2022 will finance engineering and design services for yard facilities to prepare for the new technology.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $15,750,000 $0 $0 $15,750,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra put the bid on the street in May 2022 and Metra continues to work on the procurement activities for this project.

Last Updated 12.14.2023

+ Metra Smart Gates Electrical, Signal & Communications Rail $4,000,000 $7,500,000 On Schedule

Project Details

Description
This project involves upgrades to protected grade crossings to improve safety and reliability of grade crossing protections. Metra has approximately 300 active grade crossings with warning devices. This project will fund upgrades of circuitry at these grade crossings to the latest technology. Metra will install monitors to remotely check the condition of the grade crossing protection system. When a monitor detects an anomaly, the system will send notice to the back office and dispatch a signal maintainer to perform repairs.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $4,000,000 $3,500,000 $7,500,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,500,000 $4,000,000 $3,500,000 $15,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,219,036
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra has executed a contract with a software vendor in January 2023. Currently, the 14 locations are being updated with remote monitoring. The software vendor is also working on the user interface. The construction at grade crossings is ongoing and will be completed at all locations this summer along with complete software installations and training.

Last Updated 12.14.2023

+ Metra Bridge A-32 Reconstruction Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,041,561
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities by completing drilled shafts, forming & pouring bridge piers and abutment walls. The project is 57% complete.

Last Updated 12.14.2023

+ CTA Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation ofthe propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed inAugust 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery ofmaterial is expected to arrive in May 2021 and the overhaul is expected to take place in the first half of 2022.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,314,552
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Clarendon Hills Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project redevelops the Clarendon Hills Station on the Metra BNSF line. The station improvements include new platrofm canopies, enclosed shelters, benches, and covered bike parking. The shelters will feature green roofs. The parking lot improvements will feature kiss?and?ride areas on both sides of the tracks. Landscaping improvements will also be included.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra entered into an Intergovermental Agreement (IGA) with the Village of Clarendon Hills for the reconstruction of the station. This project is part of the Village of Clarendon Hills downtown revitalization project. The Village procured a contractor and led the construction project. The substantial completion was reached in the first quarter of 2022. This is the final update on this project.

Last Updated 12.14.2023

+ Metra Ties & Ballast MWD-W Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Metra’s track renewal crew will rehabilitate dozens of miles of track along the Milwaukee District West (MD-W) Line in 2022. The project will be the most comprehensive investment in track conditions since Metra acquired the MD-W in 1987. Metra forces will Replace ties, clean or replace ballast, and replace switch components to provide smoother, faster, and safer track conditions. Metra partners with the Canadian Pacific Railroad to fund improvements to particular portions of the MD-W as freight train traffic degrade track conditions more rapidly than Metra trains.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,075,000 $0 $0 $10,075,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,075,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include ironworkers; track, signal and utilities work. Canadian Pacific (CP) funded a portion of the costs, and additional locations were added to the project.

Last Updated 12.14.2023

+ Metra Car Rehab - Budd Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project involves the life?extending rehabilitation of up to 85 commuter cars,originally built by the Budd Company between 1974 and 1978, last rehabilitatedbetween 1990 and 1993. The rehab includes, but is not limited to, replacementand/or repair to electrical and control lines, heating and lighting systems,replacement of seats, floors, walls, AC units, overhaul of trucks, replacement of allwindows, door mechanisms, and emergency lighting requirements, etc..
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$31,956,349
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project will improve the overall state of good repair for Metra rolling stock. As with the locomotive rehabilitation projects, vehicles are being removed from service in such a manner as to not disrupt operations. Seventy-four cars completed the rehabilitation continues with the remaining cars as they cycle through the rehabilitation program. The next phase of the rehabilitation work will be installing new AC units into the cars. Additional cars are being completed as a more precise and limited rehab program.

Last Updated 12.14.2023

+ CTA Blue Line Traction Power - Barry, Damen and Canal Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (atBarry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on theBlue Line. These assets will support increasing ridership demands as well as the power needed tosupport 5000 and 7000 series rail cars. The location of the tie house and substations were determinedby the Blue Line Load Flow study, which identified areas that were likely to experience traction powerissues.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,200,191 $0 $0 $2,200,191

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$122,417,171
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor during this reporting worked out of sequence to reduce the delays to the project. Construction continues at Damen, Barry and Canal Tie House. Community notices are being put together for the Haymarket elevated work, which includes installing and testing the grounding system as well as steel mesh installation at track level. ComEd coordination meetings have begun for power sources.

Last Updated 04.15.2024

+ Metra Homewood Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Additional construction funds are provided to this project to complete the rehabilitation of the Homewood Metra Station and associated intermodal facilities on the Metra Electric (ME) Line. The scope of work may include, but is not limited to, general tunnel rehabilitation, tunnel drainage solutions, elevator and stair improvements, the addition of a pedestrian ramp into the tunnel on the west end of the station, platform improvements, warming shelter, and head house improvements, and improvements to the Pace and Amtrak facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,717,185 $0 $0 $7,717,185

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,461,735
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The parking lot with 53 parking spaces was completed. The 100% station design review was completed in this reporting period by Metra and their PMO. The General Contractor was given NTP in March, and crews have mobilized on site and continued construction on the station. Currently, construction is 48% complete.

Last Updated 12.14.2023

+ CTA 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $1,899,057 $41,619,579 Behind Schedule

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $33,591,710 $33,591,710
State $0 $0 $6,128,812 $6,128,812
RTA $0 $0 $0 $0
Service Board / Local $0 $1,899,057 $0 $1,899,057
Total $31,335,000 $1,899,057 $39,720,522 $72,954,579

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the end of March 2024, 418 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 04.15.2024