Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Sort descending Mode 2024 Funding 2024-2028 Funding Status
+ Pace Joliet Gateway Center - Bus Stop Improvements Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby publicproperties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopmentthe City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public andinter-city transit which will include parking improvements and the construction of new vehicular andpedestrian access and circulation system. The new Bus Station is south of New Street, north of MarionStreet and west of the BNSF/Union Pacific Railroad. The bus station will have 13 berths, with Pacehaving exclusive use of 11 berths, passenger loading islands with canopies and shelters, signage andlandscaping. There will also be a widening of the St. Louis Street, Pace bus operator and public toilets ata location immediately northeast of the existing Pace Heritage Division garage, and ADA accessiblesidewalks.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,509,500
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk?through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.

Last Updated 12.14.2023

+ CTA Irving Park Station - Escalator and Canopy Replacement Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
Platform canopies and escalators will be replaced at Irving Park station on the O'Hare Blue Line. This project will address safety and state of good repair needs by replacing the worn and damaged platformcanopies at this station. Platform canopies that are in a state of disrepair allow water infiltration, which can cause damage to additional building materials and equipment and pose a safety risk to bothcustomers and employees. The scope of work for the station canopies includes the demolition and replacement of deteriorated canopy corrugated metal roofs, and repair and modification of the supportingsteel structure. Furthermore, escalators will be replaced at Irving Park Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,782,125
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction work has been completed. The escalators have been installed and the canopy work has reached substantial completion. Activities on final punch list items are ongoing. The project is in the close out phase.

Last Updated 12.14.2023

+ Metra Elevator Replacement Stations & Passenger Facilities Rail $2,520,000 $48,020,000 Behind Schedule

Project Details

Description
This project will replace or renovate elevators at various stations across the Metra system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $25,610,000 $25,610,000
State $0 $2,520,000 $19,890,000 $22,410,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,030,000 $2,520,000 $45,500,000 $56,050,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,880,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra continued the preparation of the final design Architectural and Engineering task orders for elevator replacement. The Randolph St. elevator has NEPA issues to resolve. The two other elevators at Grand & Cicero are at 90% and proceeding to 100% design completion. A systemwide elevator inspection and assessment is in progress as well.

Last Updated 12.14.2023

+ Metra Peterson Ridge New Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The new station in the Edgewater neighborhood of Chicago will be built to modern standards and feature a platform-length canopy and a heated headhouse. Four ADA-compliant pedestrian ramps and six staircases will provide numerous access points that are accessible to all. A landscaped plaza with benches and bicycle parking will be installed at the station entrance. A passenger drop-off drive aisle, five accessible parking stalls, and 50 parking stalls will be constructed.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,700,000 $0 $0 $2,700,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,329,765
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Design for the new station was completed. The contracts for construction management and construction contractor were procured and awarded in June and July 2021, respectively. Notice to Proceeds were issued in June 2021 for the Construction Manager and August 2021 for the Construction Contractor. The project had a stop work order in place but it was rescinded. Construction continues with the contractor working on concrete ramps and stairs, platform work, and bridge waterproofing. Union Pacific continues to perform flagging activities for the station construction.

Last Updated 12.14.2023

+ Metra Shelters Stations & Passenger Facilities Rail $1,025,000 $3,125,000 On Schedule

Project Details

Description
This project will fund the installation of shelters at stations across the system, which will provide on-demand heat. Specific locations are to be determined, based on existing conditions and demand. Shelters will be pre-fabricated structures and may include on-demand heating elements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $1,025,000 $2,100,000 $3,125,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,500,000 $1,025,000 $2,100,000 $7,625,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$5,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Aluminum shelters continue to be installed throughout the system. Currently, shelter installation is in progress at Morton Grove, Western Ave., 67th St., 83rd St., and the Woodstock station. Procurement packages for the next package of stations is in process.

Last Updated 12.14.2023

+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,930,000 $0 $0 $13,930,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,564,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 12.14.2023

+ CTA All Station Accessibility Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $4,633,224 Behind Schedule

Project Details

Description
Funding will provide for second installment of funds to rehabilitate and/or replace elevators throughout the system. This funding along with the granted Rebuild Illinois funds provide in part for phase one of the program. For the Elevator Replacement Program, complete inspection of an elevator will need to be conducted to identify all deficiencies. Once inspections are complete, the CTA will need to determine whether rehabilitation or replacement is warranted. The individual scope of work for each elevator will vary depending on its condition and elevator type (machine room-less (MRL), geared, gearless, or hydraulic). Inspections of all components of the following systems are required to determine the full scope of work at each individual elevator and to determine whether rehabilitation or replacement is warranted:• Mechanical Systems• Electrical Systems• Material Finishes• Control Systems• Communication Systems• Security Systems• Structural Members• ADA Code Compliance • Municipality Building Code Compliance
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $4,633,224 $4,633,224
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,585,000 $0 $4,633,224 $16,218,224

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,370,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for the designer has been issued in June 2022. The designer is completing site assessments and elevator inspections. An assessment report will be developed to prioritize the elevator replacement or rehabilitation locations. The report will also provide the scope of work needed for each individual elevator. A draft report is expected to be submitted to CTA in June. Once the report is finalized, CTA will issue a procurement for construction based on the priority recommendations from the assessment report.

Last Updated 12.14.2023

+ Metra Van Buren St. Station Stations & Passenger Facilities Rail $28,500,000 $28,500,000 On Schedule

Project Details

Description
A complete renovation of the downtown Chicago terminal station will rehabilitate the existing historic waiting rooms, replace the roof assembly while maintaining the green roof, and will replace the pedestrian tunnel in the park. A new 'pop-up' entrance in Grant Park will add a new access stair case and elevator and add an ADA-compliant ramp connecting to the pedestrian bridge. The pedestrian tunnel under Michigan Ave will be waterproofed and a new elevator will be added to the Jackson Blvd platform. The scope of work includes rehabilitation of the stair enclosures and elevator west of Michigan Avenue, replacement of the platforms, new full-length platform canopies, heated warming shelters, construction of a new vendor space at lower level, and all new mechanical, electrical, and plumbing throughout the station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $28,500,000 $0 $28,500,000
Service Board / Local $0 $0 $0 $0
Total $0 $28,500,000 $0 $28,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$48,126,300
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra awarded the consultant contract for station concept design. The concept design is at 15% completion and on hold pending completion of lakefront ordinance protection, NEPA, and environmental processes. Documents are being prepared to be submitted for lakefront ordinance for approval. Environmental and NEPA work is ongoing. The Memorandum of Understanding should be fully executed in Q1 of 2024.

Last Updated 12.14.2023

+ Metra 95th Street Station CSU Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed. The station will be made fully accessible with the addition of elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $37,000,000 $0 $0 $37,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this station reached 100%. There were delays on this project associated with the National Environmental Policy Act (NEPA) review process as well as coordination with the Chicago State University and additional scope added to the design. The project is in procurement and is aiming to go out for bids before the end of the year for a General Contractor.

Last Updated 12.14.2023

+ Metra Auburn Park New Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The new station in the Auburn Park neighborhood of Chicago will feature a platform-length canopy and heated headhouse with two elevators. The station will include a center boarding platform with a staircase down to street level entrance tunnel, a landscaped plaza with benches, canopy, bicycle parking, and a vendor space Metra will lease. A parking lot will include 79 parking stalls, 5 ADA parking spaces, and a passenger drop-off lane. The new station will be fully ADA accessible.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,300,000 $0 $0 $6,300,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$39,300,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor finished the vendor building foundations and started working on building the walls. Regarding the vendor building construction, the contractor finished the first concrete pour out of five scheduled pours. Construction activities also included retaining wall removal, some ERS work, in addition to drainage structure installation and grading work on the parking lot. The contractor also replaced curbs and driveways on Union Ave.

Last Updated 12.14.2023