Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding Sort ascending 2024-2028 Funding Status
+ CTA CTA Open Fare Payment System - Equipment (Lease) - VENTRA Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
CTA Open Fare Payment System - Equipment (Lease) - VENTRA: funds will provide in part for the principal and interest of the agreement need for the Open Fare Standard equipment, hardware, and software costs.The contractor (Cubic) costs including, but are not limited to, expenses incurred to design, build, finance, operate, maintain, repair and replace the equipment, the software and the Open Standards Fare System, and provide the Services, in accordance with the specifications and performance at the service levels and perform any other obligations pursuant to this Agreement.The capital share of the annual Base component cost is $15 million which provides for necessary design, testing, purchase and installation of assets such as the following: Ventra Vending Machines, Mobile Data Validators (readers), Driver Terminal Displays, retail terminals, and B26all software applications, and back-end hardware.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $30,000,000 $0 $0 $30,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$60,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is for the 2020, 2021, 2022, and 2023 annual equipment lease. The annual 2023 payments for the equipment lease began and will continue to make payments.

Last Updated 12.14.2023

+ Pace Farebox System Replacement Support Facilities & Equipment Bus $0 $0 On Schedule

Project Details

Description
Farebox System Replacement - Over 700 fareboxes on Pace fixed route buses will be replaced, with prior PAYGO funding of $7.5M from 2020 included.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,079,344 $0 $0 $3,079,344

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,500,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
All of the fareboxes were installed on the garages and the project is considered substantially complete. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Homewood Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Additional construction funds are provided to this project to complete the rehabilitation of the Homewood Metra Station and associated intermodal facilities on the Metra Electric (ME) Line. The scope of work may include, but is not limited to, general tunnel rehabilitation, tunnel drainage solutions, elevator and stair improvements, the addition of a pedestrian ramp into the tunnel on the west end of the station, platform improvements, warming shelter, and head house improvements, and improvements to the Pace and Amtrak facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,717,185 $0 $0 $7,717,185

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,461,735
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The parking lot with 53 parking spaces was completed. The 100% station design review was completed in this reporting period by Metra and their PMO. The General Contractor was given NTP in March, and crews have mobilized on site and continued construction on the station. Currently, construction is 48% complete.

Last Updated 12.14.2023

+ Metra Car Rehab - Budd Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project involves the life?extending rehabilitation of up to 85 commuter cars,originally built by the Budd Company between 1974 and 1978, last rehabilitatedbetween 1990 and 1993. The rehab includes, but is not limited to, replacementand/or repair to electrical and control lines, heating and lighting systems,replacement of seats, floors, walls, AC units, overhaul of trucks, replacement of allwindows, door mechanisms, and emergency lighting requirements, etc..
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$31,956,349
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project will improve the overall state of good repair for Metra rolling stock. As with the locomotive rehabilitation projects, vehicles are being removed from service in such a manner as to not disrupt operations. Seventy-four cars completed the rehabilitation continues with the remaining cars as they cycle through the rehabilitation program. The next phase of the rehabilitation work will be installing new AC units into the cars. Additional cars are being completed as a more precise and limited rehab program.

Last Updated 12.14.2023

+ Pace 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,550,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ CTA Green Line Jackson Park Branch Trackwork Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,855,446
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.

Last Updated 12.14.2023

+ CTA 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,930,000 $0 $0 $13,930,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,564,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 12.14.2023

+ Metra 95th Street Station CSU Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed. The station will be made fully accessible with the addition of elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $37,000,000 $0 $0 $37,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this station reached 100%. There were delays on this project associated with the National Environmental Policy Act (NEPA) review process as well as coordination with the Chicago State University and additional scope added to the design. The project is in procurement and is aiming to go out for bids before the end of the year for a General Contractor.

Last Updated 12.14.2023