Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Sort descending Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ Metra Gresham Area Bridges Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution. Both bridges are named after the Chicago street over which they cross, carry two main line tracks, and will be replaced with resilient concrete bridges.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $17,000,000 $0 $0 $17,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$31,816,250
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Design work for the Vincennes Ave. Bridge #98 and Morgan St. Bridge #S-102 were completed. City land swap negotiations are ongoing. Metra is proceeding without the property swap and is investigating the original elevation ordinance for the legal right to construct on City property. The 100% drawings were completed, and vendor selected. The contractor was given the Notice to Proceed in August and kick-off meeting was held in October. The contractor is working on submittals and long lead time items as well as working on permits for the project.

Last Updated 04.15.2024

+ Metra Central Warehousing Support Facilities & Equipment Rail $0 $9,775,000 On Schedule

Project Details

Description
Metra acquired an existing warehouse facility to develop a centralized warehouse for materials that support the activities of the commuter railroad system. The central warehouse will combine 4 existing buildings that are overcrowded and create efficiencies by allowing Metra to buy in bigger quantities and lower freight delivery costs. Renovations will continue as part of a multi-year, phase-funded project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $9,775,000 $9,775,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,700,000 $0 $9,775,000 $33,475,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$18,700,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The property acquisition, environmental site assessment and interior demolition were previously completed. Roof rehabilitation work has been ongoing and is scheduled to be completed at the end of May. Interior build out work, lighting and fencing will be completed by Metra forces after the roof work is finished.

Last Updated 12.14.2023

+ Metra Traction Power System Augmentation - MED Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
Converting the tie stations into substations and installing a new substation willincrease capacity and reliability on the Metra Electric District. Construction wasperformed moving from north to south. Construction was completed at 31stStreet and 51st Street. Design for 95th Street and Riverdale are 100% complete.Bids were received and contract was awarded for both 95th St. and Riverdalesubstation construction. The contractor was issued an NTP in October 2018 andreached substantial completion this reporting period. This will be the final updateon this project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$32,264,285
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Converting the tie stations into substations and installing a new substation will increase capacity and reliability on the Metra Electric District. Construction was performed moving from north to south. Construction was completed at 31st Street and 51st Street. Design for 95th Street and Riverdale are 100% complete. Bids were received and contract was awarded for both 95th St. and Riverdale substation construction. The contractor was issued an NTP in October 2018 and reached substantial completion this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Remanufactured Locomotive Purchase Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project involves the purchase of up to forty-two (42) remanufactured diesel locomotives. Thecontract has a base order of fifteen (15) locomotives with three (3) Options to order nine (9) additionallocomotives each. Metra ancipicates these locomotives to have increased horsepower, lower emissions,and greater fuel efficiency than the current fleet average.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$186,463,879
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The bsae order of fifteen locomotives were delivered to Metra. Metra executed option #1 for additional (9) locomotives and work has begun on them. Of the new locomotives, four have been added to the rebuild schedule.

Last Updated 04.15.2024

+ Metra Stoney Creek Bridge- SWS Track & Structure Rail $2,830,000 $2,830,000 Behind Schedule

Project Details

Description
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $2,830,000 $0 $2,830,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $2,830,000 $0 $2,830,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$8,500,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. There are some delays related to the National Environmental Policy Act (NEPA) process and the Illinois State Historic Preservation Office (SHPO) review. The 30% design has been completed. Once the NEPA and SPHO process is complete, work will continue on the design to advance to 60%.

Last Updated 12.14.2023

+ Metra CREATE EW-2 Bridge Lift Track & Structure Rail $3,040,000 $3,040,000 Behind Schedule

Project Details

Description
This project involves lifting a bridge between 78th Street and 79th Street on Metra’s Rock Island Line. The bridge spans over three sets of railroad tracks owned by The Belt Railway of Chicago and Norfolk Southern in Chicago at milepost 8.7. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,040,000 $0 $3,040,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $3,040,000 $0 $7,040,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$8,404,189
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the project has been completed. Metra advertised the construction procurement and received only one bid. The proposed cost exceeded the allocated construction budget for the project. Metra made a decision to re-design the project to reduce the risk off of the potential contractor and attract more bids. A change order has been issued to the designer and the re-design is 90% complete.

Last Updated 12.14.2023

+ Metra Chicago Union Station Interlockers Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project involves the modernization and upgrading of outmoded interlockings at the north and south ends of Chicago Union Station (CUS). The project will include, but not be limited to, new rail, ties, ballast cleaning or replacement, upgrades to signal infrastructure, replacement of switches and components, and other related work as needed. Amtrak contributes funds towards a portion of the project work.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,500,000 $0 $0 $8,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,096,850
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Amtrak identified scope of work for 2023 and has executed with Metra a Fixed Facility Agreement to complete the project. The project has started where Amtrak began the replacement and upgrades of switches, signal and rail at Harrison St and Taylor St of the North and South end of CUS.

Last Updated 12.14.2023

+ Metra Revenue Accounting System N/A Rail $0 $0 On Schedule

Project Details

Description
Metra will implement a new and updated revenue accounting system and will alsoprovide funding for Metra to scope and release an RFP to integrate its currentfinancial system into an Enterprise Resource Planning (ERP) system that will becompliant with current best practices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$16,205,776
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Phase 4 of the Financial System Replacement, the Review Accounting module, went live as of October 2020 and final elements were executed in October of this year. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Zero-Emissions Trainsets Rolling Stock Rail $0 $78,604,137 On Schedule

Project Details

Description
Metra's investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure multiple-unit car that produce zero mobile emissions. This multi-year, multi-phase project will acquire battery-electric trainsets. Metra will be among the first passenger rail transit agencies to purchase and operate self-propelled trainsets that will not require the construction and maintenance of wayside power. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxides (NOx) emissions by more than 30 tons per year, thus significantly reducing the agency’s greenhouse gas footprint and greatly improving air quality in the region.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $29,024,137 $29,024,137
State $0 $0 $49,580,000 $49,580,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $78,604,137 $78,604,137

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra put the bid on the street in May 2022 and Metra continues to work on the procurement activities for this project.

Last Updated 12.14.2023

+ Metra Bridge 86 - 78th St Entrance Track & Structure Rail $0 $33,160,000 On Schedule

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $33,160,000 $33,160,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $0 $33,160,000 $48,140,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the bridge and entrance continued to 90% completion. Design is expected to be complete by Q1-2024.

Last Updated 12.14.2023