Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Sort ascending Status
+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,930,000 $0 $0 $13,930,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,564,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 12.14.2023

+ CTA Replace Non-Revenue 61st ST. Rail Shop Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
Construct a new non-revenue vehicle maintenance facility for maintenance and repair of non-revenueequipment. Facility will also include covered storage tracks for track maintenance equipment. Thepurpose of the new Non-Revenue Rail Vehicle Maintenance Facility is to provide facilities formaintenance and repair of over 125 pieces of non-revenue equipment used for right-of-way maintenanceand other rail-mounted non-revenue vehicles.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$70,017,063
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 61st rail shop project continued to make headway. The building enclosure erected as well as roof installed. The contractor continues to make headway with procurement and installation of electrical, mechanical, plumbing, and carpentry inside the building. The contractor continues to perform parking lot and landscaping for the facility as well.

Last Updated 12.14.2023

+ Metra Bridge A-32 Reconstruction Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,041,561
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities by completing drilled shafts, forming & pouring bridge piers and abutment walls. The project is 57% complete.

Last Updated 12.14.2023

+ Metra 147th St. - Sibley Station Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project consists of the complete rehabilitation of the 147th St. (Sibley Blvd.) station facility in Harvey along with the Metra Electric (ME) Line in Harvey. The project scope includes renovation of the station entrance, heated warming shelters, a canopy over half of the platform. Additional project elements include, but may not be limited to, lighting, sidewalk, bike facilities, landscape enhancements, and other related work.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,400,000 $0 $0 $9,400,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,862,735
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction activities are ongoing at the station. The contractor is working on installing light fixtures in the platform canopy as well as continued waterproofing on the headhouse and platform canopy. Concrete work continued on the project site as well with forming and pouring of sections. Electrical, mechanical and plumbing connections continue to be installed in the building and platform area as well. Tile installation has begun on the street level in the headhouse.

Last Updated 12.14.2023

+ Metra Zero-Emissions Locomotives Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
Metra investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure locomotives that produce zero mobile emissions. This multi-year, multi-phase project will acquire state-of-the-art technologies and pilot their performance capabilities given Metra’s track profile and the Chicago region’s inclement weather patterns. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxides (NOx) emissions by more than 30 tons per year, thus significantly reducing the agency’s greenhouse gas footprint and greatly improving air quality in the region. Funds programmed in 2022 will finance engineering and design services for yard facilities to prepare for the new technology.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $15,750,000 $0 $0 $15,750,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra put the bid on the street in May 2022 and Metra continues to work on the procurement activities for this project.

Last Updated 12.14.2023

+ CTA 2021 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. Facilities improvements were completed during this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.

Last Updated 12.14.2023

+ Metra 79th St., 87th St, 103rd St. Stations Metra Electric Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project funds the complete rehabilitation of the 79th Street, 87th Street and 103rd Street Stations in Chicago along with the Metra Electric (ME) Line. The project scope includes the repair or replacement of aging shelter enclosures, station lighting upgrades, and platform renovation work. Additional project elements may include but are not limited to, sidewalk repairs, upgraded bike facilities, landscape enhancements, bench repairs, and other related work as needed. The station will be made fully ADA accessible upon completion of the project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $48,900,000 $0 $0 $48,900,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$61,150,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designs for these stations were completed. The Notice to Proceed with construction has been issued in January 2023. The contractor is currently working on 79th St. Station where they finished the earth retention system. The contractor continues to install the foundations and concrete pours for the stairs, as well as elevator shaft. The contractor will then begin to pour the concrete slab for the station headhouse and continue with mechanical, electrical, and plumbing connections.

Last Updated 12.14.2023

+ Pace 2021 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 On Schedule

Project Details

Description
Bus Tracker Signs - Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$600,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activities continued related to the real time signs installed at various transit centers along the Pulse Milwaukee Line with various details on the specifics of screen size. Concurrently, real time bus information signage and electrical connections continued for various project elements. Permitting, installation, and invoicing continued as well.

Last Updated 12.14.2023

+ CTA Tactical Traction Power (Equipment/Cable/Enclosures) Track & Structure Rail $0 $0 On Schedule

Project Details

Description
State of Good Repair projects and replacing obsolete equipment on CTA rail signal system
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,125,768 $0 $0 $2,125,768

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,293,685
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Permits for the project were received in the last reporting period. Currently, the General Contractor is submitting process plans for start of construction and mobilization on site. Delivery of onsite storage containers is ongoing. CTA is working with the contractor to start the first phase of the project, which is the electrical shop equipment relocation.

Last Updated 12.14.2023