Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the December 2023 Project Management Oversight report.
Agency | Project Title | Asset Category | Mode | 2024 Funding | 2024-2028 Funding | Status | |||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | CTA | Life Extending Bus Overhaul - 430 Standard (1000 Series) | Rolling Stock | Bus | $6,737,430 | $6,737,430 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses. This project is essential to meet availability requirements for CTA. These buses were purchased in 2006-2007 and this life extension is essential to maintaining peak availability requirements at all 7 bus garages.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The CTA Team drafted technical specs and project scope are under review as of this reporting period. The team completed testing the pilot Haldex air dryers on two buses and the buses were put back in service. The Team continues to complete the project independent cost estimate and release the updated specifications to the Purchasing Department to start the bid review/release process.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Platform Improvements | Stations & Passenger Facilities | Rail | $5,820,000 | $19,300,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project is part of Metra’s ongoing effort to bring commuter rail stations into compliance with therequirements of the Americans with Disabilities Act (ADA) of 1990. The project will focus onplatform and platform access routes, as necessary.Wherever platform work is undertaken, the existing platforms will be rehabilitated in order to allowdeteriorated tactile surfaces to be replaced with new ADA-compliant “truncated dome” type surfaces.FY 2020 Federal funds and 2020 Illinois PAYGO funds will be used for construction of new platforms,ADA access improvements, ADA building improvements, and related work at sites to be determined.The West Hinsdale Station on the BNSF Line has been identified as a priority location for platformrehabilitation. However, this project may also include the Oak Lawn Station (SouthWest Service) andthe River Forest Station (Union Pacific West Line). Note that this is a preliminary list of stationsidentified for platform rehabilitation and other locations may be added.FY 2020 PAYGO and Federal funds will be used for construction. Future funding may be required.This project is necessary to bring Metra’s system into compliance with the 1990 ADA.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Platform work at Chicago-Ridge, Willow Springs, Mundelein, Jefferson Park, Barrington Station, Franklin Park, New Lenox, and West Hinsdale were completed. Work continued at 103rd Street station platform and is at 40% complete. Work also begun at the Oak Lawn station and is at 15% complete.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Smart Gates | Electrical, Signal & Communications | Rail | $4,000,000 | $7,500,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves upgrades to protected grade crossings to improve safety and reliability of grade crossing protections. Metra has approximately 300 active grade crossings with warning devices. This project will fund upgrades of circuitry at these grade crossings to the latest technology. Metra will install monitors to remotely check the condition of the grade crossing protection system. When a monitor detects an anomaly, the system will send notice to the back office and dispatch a signal maintainer to perform repairs.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra has executed a contract with a software vendor in January 2023. Currently, the 14 locations are being updated with remote monitoring. The software vendor is also working on the user interface. The construction at grade crossings is ongoing and will be completed at all locations this summer along with complete software installations and training.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | IT Components & Services | N/A | Rail | $3,100,000 | $5,800,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Purchases various pieces of equipment that will be utilized at Metra Headquarters and outlying Metra facilities. Purchases may include, but are not limited to, replacement of obsolete information technology infrastructure, upgrade network switches, computers and printers, copiers, new and replacement servers, financial system software, and other software.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This is a multiple year and multiple project type of capital project. Purchase orders have been awarded for various computer hardware and software. Hardware has been delivered and installed. Purchase Order Releases for computer hardware and software continue in process and deliveries will continue over the next several years.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | CREATE EW-2 Bridge Lift | Track & Structure | Rail | $3,040,000 | $3,040,000 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves lifting a bridge between 78th Street and 79th Street on Metra’s Rock Island Line. The bridge spans over three sets of railroad tracks owned by The Belt Railway of Chicago and Norfolk Southern in Chicago at milepost 8.7. This project is a necessary component of the new Auburn Park station project.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The design for the project has been completed. Metra advertised the construction procurement and received only one bid. The proposed cost exceeded the allocated construction budget for the project. Metra made a decision to re-design the project to reduce the risk off of the potential contractor and attract more bids. A change order has been issued to the designer and the re-design is 90% complete.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Stoney Creek Bridge- SWS | Track & Structure | Rail | $2,830,000 | $2,830,000 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is in the design phase. There are some delays related to the National Environmental Policy Act (NEPA) process and the Illinois State Historic Preservation Office (SHPO) review. The 30% design has been completed. Once the NEPA and SPHO process is complete, work will continue on the design to advance to 60%.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Elevator Replacement | Stations & Passenger Facilities | Rail | $2,520,000 | $48,020,000 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will replace or renovate elevators at various stations across the Metra system.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra continued the preparation of the final design Architectural and Engineering task orders for elevator replacement. The Randolph St. elevator has NEPA issues to resolve. The two other elevators at Grand & Cicero are at 90% and proceeding to 100% design completion. A systemwide elevator inspection and assessment is in progress as well.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Vehicles & Equipment | Support Facilities & Equipment | Rail | $2,330,000 | $15,410,930 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project provides for the purchase of fleet vehicles and equipment utilized by Metra’s various departments to help service and maintain the system. This project includes, but is not limited to, vehicles used for supervision of fieldwork, small pickup trucks, construction equipment, and other vehicles. Project funds will replace and retire vehicles and equipment in Metra's current fleet that has surpassed its useful life.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Procurement activities are in progress. Metra is waiting on delivery of vehicles, including 23 highway vehicles, 48V service carts, two electric vans, police vehicles, and service vehicles.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Car and Locomotive Cameras | Rolling Stock | Rail | $2,000,000 | $10,000,000 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves the purchase of a digital video recording (DVR) system. The system will replace the 12-year old, obsolete system currently running on Metra’s rolling stock. The new system will allow for video recording of railroad signal aspects and incidents and includes inward-facing cameras and outward-facing, dual-lens cameras.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The new technology allows recording at a faster frame rate and higher resolution, allowing slowing down the recording to less than real time rates without distortion, blurring, or loss of resolution. Currently, the DVR system is being installed by Metra Forces and passenger cameras are being installed by a vendor. All prototype installations were completed with them running with no issues. The full-scale installation began, and kits started delivery in October 2022. In total, 71 cars were completed, and the project is on-going and continuing installation activities.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | 5000 Series Rail Car Quarter Life Overhaul | Rolling Stock | Rail | $1,899,057 | $41,619,579 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
As of the end of March 2024, 418 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.
Last Updated 04.15.2024 |