Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Sort descending Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ CTA Green Line - Lake Street Bridge Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs.This funding would support track improvements on both sides of the Lake Street Bridge, which isscheduled to be completely replaced by the Chicago Department of Transportation in 2023. The scopeof the project will include: improve the curve geometry on the east side of the bridge; replace thetimber ties and rail fasteners, install new gauge planking, replace equipment at both the east and westturnouts, and replace structural steel framing for the three side platforms adjacent to the track.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,025,296
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for the designer was issued in February 2022. The design activities are nearing completion. Coordination efforts with CDOT are ongoing. Once the CTA design is completed it will be on hold until CDOT finishes their portion of the design in order to align the timeline for construction activities.

Last Updated 12.14.2023

+ CTA Green Line Jackson Park Branch Trackwork Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,855,446
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.

Last Updated 12.14.2023

+ Metra Gresham Area Bridges Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution. Both bridges are named after the Chicago street over which they cross, carry two main line tracks, and will be replaced with resilient concrete bridges.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $17,000,000 $0 $0 $17,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$31,816,250
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Design work for the Vincennes Ave. Bridge #98 and Morgan St. Bridge #S-102 were completed. City land swap negotiations are ongoing. Metra is proceeding without the property swap and is investigating the original elevation ordinance for the legal right to construct on City property. The 100% drawings were completed, and vendor selected. The contractor was given the Notice to Proceed in August and kick-off meeting was held at the beginning of October. The contractor is working on submittals and long lead time items.

Last Updated 12.14.2023

+ CTA Harlem Bus Bridge Track & Structure Bus $0 $0 Behind Schedule

Project Details

Description
This project will replace the Harlem Bus Bridge at our O'Hare Line Harlem Station. The bridge removaland reconstruction limits are from the north end of the bridge expansion joint to the south limits of thebridge expansion joint. The work includes all removal and reconstruction of the existing bridge structurewith a new superstructure galvanized steel and bearing assemblies, concrete bridge deck, concretesidewalks, approach slabs, curb and gutters, drainage, expansion joint assemblies, guard rails, trashenclosures, pedestrian shelters, electrical I LED lighting, signage, pavement stripping, and curb lanepainting.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$39,982,424
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed in October 2022. CTA has developed a construction procurement package and it is currently out for bid.

Last Updated 12.14.2023

+ Metra Harvey Transportation Center - Metra Stations & Passenger Facilities Rail $23,770,000 $24,080,000 On Schedule

Project Details

Description
Metra is partnering with Pace to create the Harvey Transportation Center on the Metra Electric line. Metra will utilize funds for platform reconstruction and to construct other enhancements that will make the station ADA accessible, improve the commuter environment, and facilitate intermodal transfers between Pace and Metra.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $310,000 $310,000
State $0 $0 $0 $0
RTA $0 $23,770,000 $0 $23,770,000
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $23,770,000 $310,000 $26,080,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$45,250,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The National Environmental Policy Act (NEPA) process has been completed. The design is progressing and is currently at 30% completion. Pace and Metra held an open house in January to get the community’s feedback on the design alternatives for the new Transportation Center. Community engagement is ongoing.

Last Updated 12.14.2023

+ Metra Homewood Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Additional construction funds are provided to this project to complete the rehabilitation of the Homewood Metra Station and associated intermodal facilities on the Metra Electric (ME) Line. The scope of work may include, but is not limited to, general tunnel rehabilitation, tunnel drainage solutions, elevator and stair improvements, the addition of a pedestrian ramp into the tunnel on the west end of the station, platform improvements, warming shelter, and head house improvements, and improvements to the Pace and Amtrak facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,717,185 $0 $0 $7,717,185

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,461,735
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The parking lot with 53 parking spaces was completed. The 100% station design review was completed in this reporting period by Metra and their PMO. The General Contractor was given NTP in March, and crews have mobilized on site and continued construction on the station. Currently, construction is 48% complete.

Last Updated 12.14.2023

+ Pace Intelligent Bus System (IBS) Electrical, Signal & Communications Bus $0 $0 Behind Schedule

Project Details

Description
Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,250,000 $0 $0 $2,250,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,250,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace began activity of this project during this reporting period. This will be for automatic passenger counters on fixed route buses. Activities have just started and expected to ramp up in Q1-2024.

Last Updated 12.14.2023

+ CTA Irving Park Station - Escalator and Canopy Replacement Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
Platform canopies and escalators will be replaced at Irving Park station on the O'Hare Blue Line. This project will address safety and state of good repair needs by replacing the worn and damaged platformcanopies at this station. Platform canopies that are in a state of disrepair allow water infiltration, which can cause damage to additional building materials and equipment and pose a safety risk to bothcustomers and employees. The scope of work for the station canopies includes the demolition and replacement of deteriorated canopy corrugated metal roofs, and repair and modification of the supportingsteel structure. Furthermore, escalators will be replaced at Irving Park Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,782,125
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction work has been completed. The escalators have been installed and the canopy work has reached substantial completion. Activities on final punch list items are ongoing. The project is in the close out phase.

Last Updated 12.14.2023

+ Metra IT Components & Services N/A Rail $3,100,000 $5,800,000 On Schedule

Project Details

Description
Purchases various pieces of equipment that will be utilized at Metra Headquarters and outlying Metra facilities. Purchases may include, but are not limited to, replacement of obsolete information technology infrastructure, upgrade network switches, computers and printers, copiers, new and replacement servers, financial system software, and other software.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $2,700,000 $2,700,000
State $0 $3,100,000 $0 $3,100,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $750,000 $3,100,000 $2,700,000 $6,550,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,059,193
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This is a multiple year and multiple project type of capital project. Purchase orders have been awarded for various computer hardware and software. Hardware has been delivered and installed. Purchase Order Releases for computer hardware and software continue in process and deliveries will continue over the next several years.

Last Updated 12.14.2023

+ Pace Joliet Gateway Center - Bus Stop Improvements Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby publicproperties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopmentthe City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public andinter-city transit which will include parking improvements and the construction of new vehicular andpedestrian access and circulation system. The new Bus Station is south of New Street, north of MarionStreet and west of the BNSF/Union Pacific Railroad. The bus station will have 13 berths, with Pacehaving exclusive use of 11 berths, passenger loading islands with canopies and shelters, signage andlandscaping. There will also be a widening of the St. Louis Street, Pace bus operator and public toilets ata location immediately northeast of the existing Pace Heritage Division garage, and ADA accessiblesidewalks.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,509,500
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk?through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.

Last Updated 12.14.2023