Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Sort ascending Status
+ Metra Fiber Optic MED Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
This project consists of the replacement of the coaxial cable and copper cable used to conduct voice and signal data on the Metra Electric District’s Main Line. The fiber optic cable will connect to the recent installation on the South Chicago Branch and Blue Island Branch and extend to the downtown terminal. Existing cable will be replaced with fiber optic cable. New cable will be hung on the catenary structures in a manner similar to the existing cable.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designer reached 100% design completion. The design was submitted and is under review by Metra.

Last Updated 12.14.2023

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,314,071 $0 $0 $4,314,071

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th w

Last Updated 12.14.2023

+ CTA 2020 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Facilities improvements is part of an ongoing program. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. This particular part of the program is completed. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra GPS Train Tracking Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project involves the replacement of the current GPS, which has exceeded its useful life. Metra will replace the GPS, on-board announcement system and signs on the entire fleet. Metra will also install automatic passenger counters and event recorders. The new system will maintain the necessary current functions, while potentially adding video surveillance, customer information displays and an information system. This project will enable Metra to track trains, count passengers and provide information with one system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,192,784 $0 $0 $8,192,784

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,239,830
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project design is 100% complete. The First Article of Inspection and training were completed. All installation work on the MED and RID yards were completed. Station control unit for station announcements installations were completed. Field testing is ongoing. Production installation phase is ongoing for all districts with cab car installation was completed this reporting period. Trailer car installation is at 2% completion.

Last Updated 12.14.2023

+ CTA Forest Park: Phase 1 - Trackwork Halsted to IMD Track & Structure Rail $0 $0 Ahead of Schedul

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to Illinois Medical District (IMD), an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $43,497,351 $0 $0 $43,497,351

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$124,596,980
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor submitted a request for substantial completion for the date of 12/8/23. CTA has performed a walkthrough and generated a punchlist. Contractor continues with punchlist work. Fence enclosure, barrier wall, and downspouts were completed. Fiber optic splicing and testing is ongoing.

Last Updated 04.15.2024

+ Pace Construct Salt Shed Support Facilities & Equipment Bus $0 $0 On Schedule

Project Details

Description
Pace is in need of a stand-alone storage solution and will construct a shed to store and secure up to 10tons of bulk rock salt that is used during the winter season. The construction of the shed will be within thefootprint of Pace's parcel. This shed will allow for accessible use with Pace's skidsteer to load rock saltonto the pickup trucks and distribute it on approximately more than 15,000 square yards of grounds(parking lots and driveways), in addition to sidewalks, in a safe and more efficient manner. CurrentlyPace purchases 50-pound bags of salt that have to be loaded manually which has become very unsafein term of personal injury risk and is very time consuming as it has to be loaded multiple times per day.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$75,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A construction contract was awarded. There were some delays related to the Village code requirements and permits. All activities were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Rehabilitate Blue Line - Kimball Subway Waterproofing Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Subway Waterproofing & Track - Funding will provide for critical waterproofing patchwork needed to continue rail service through the Blue Line O'Hare branch.. Due to funding restrictions CTA cannot move forward with original scope of work to mitigate water infiltration in the Dearborn subway.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $961,000 $0 $0 $961,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,824,710
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work activities under this project are ongoing. The waterproofing and grout injection work is performed by CTA forces whenever single-track access is available.

Last Updated 12.14.2023

+ Metra Crew Facilities Support Facilities & Equipment Rail $0 $0 Behind Schedule

Project Details

Description
This project includes, but is not limited to, renovation of existing crew facilities or construction of new crew facilities at existing yard locations across the Metra system. Work may include design of and renovations to interior spaces such as office spaces, locker rooms, and training facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$16,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra will build a new crew facility at Fox Lake Station on the Milwaukee North District Line. The design for this location is 90% complete and the 100% design is expected in July 2023. The designs for the Western Ave and Elgin facilities are 25% complete. Design activities are ongoing.

Last Updated 12.14.2023

+ CTA Replace Non-Revenue 61st ST. Rail Shop Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
Construct a new non-revenue vehicle maintenance facility for maintenance and repair of non-revenueequipment. Facility will also include covered storage tracks for track maintenance equipment. Thepurpose of the new Non-Revenue Rail Vehicle Maintenance Facility is to provide facilities formaintenance and repair of over 125 pieces of non-revenue equipment used for right-of-way maintenanceand other rail-mounted non-revenue vehicles.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$70,017,063
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 61st rail shop project continued to make headway. The building enclosure erected as well as roof installed. The contractor completed the bulk of scope for the project and requested substantial completion during this reporting period. The request is under review by CTA as of this reporting period.

Last Updated 04.15.2024

+ Pace Joliet Gateway Center - Bus Stop Improvements Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
The City of Joliet is redeveloping the existing publicly owned Joliet Union Depot and nearby publicproperties as a Multi-Modal Transportation Center to be owned by the City. As part of this redevelopmentthe City of Joliet has partnered with Pace to construct a new Bus Station and turn-around for public andinter-city transit which will include parking improvements and the construction of new vehicular andpedestrian access and circulation system. The new Bus Station is south of New Street, north of MarionStreet and west of the BNSF/Union Pacific Railroad. The bus station will have 13 berths, with Pacehaving exclusive use of 11 berths, passenger loading islands with canopies and shelters, signage andlandscaping. There will also be a widening of the St. Louis Street, Pace bus operator and public toilets ata location immediately northeast of the existing Pace Heritage Division garage, and ADA accessiblesidewalks.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,509,500
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The City of Joliet and Pace entered into an Intergovernmental Grant Agreement for this project. The overall Joliet Gateway Terminal project is being managed by the City of Joliet. The City of Joliet prepared 100% design and bid the larger Intermodal Transportation Project, of which the Bus Turnaround Component is a part of. A construction contract was awarded, notice to proceed was issued in February, and construction began in March. Substantial completion and beneficial occupancy for the depot building was achieved in December 2021, after a walk?through inspection of depot building. The Scott Street pedestrian tunnel was completed in April 2022. Punch list items on building, passenger platforms and site landscaping were completed in June 2022.

Last Updated 12.14.2023