Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Sort ascending Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ Metra Chicago Union Station Interlockers Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project involves the modernization and upgrading of outmoded interlockings at the north and south ends of Chicago Union Station (CUS). The project will include, but not be limited to, new rail, ties, ballast cleaning or replacement, upgrades to signal infrastructure, replacement of switches and components, and other related work as needed. Amtrak contributes funds towards a portion of the project work.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,500,000 $0 $0 $8,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,096,850
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Amtrak identified scope of work for 2023 and has executed with Metra a Fixed Facility Agreement to complete the project. The project has started where Amtrak began the replacement and upgrades of switches, signal and rail at Harrison St and Taylor St of the North and South end of CUS.

Last Updated 12.14.2023

+ Metra Revenue Accounting System N/A Rail $0 $0 On Schedule

Project Details

Description
Metra will implement a new and updated revenue accounting system and will alsoprovide funding for Metra to scope and release an RFP to integrate its currentfinancial system into an Enterprise Resource Planning (ERP) system that will becompliant with current best practices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$16,205,776
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Phase 4 of the Financial System Replacement, the Review Accounting module, went live as of October 2020 and final elements were executed in October of this year. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Zero-Emissions Trainsets Rolling Stock Rail $0 $78,604,137 On Schedule

Project Details

Description
Metra's investment in innovative, cleaner energy locomotives will be funded in part by this project which will procure multiple-unit car that produce zero mobile emissions. This multi-year, multi-phase project will acquire battery-electric trainsets. Metra will be among the first passenger rail transit agencies to purchase and operate self-propelled trainsets that will not require the construction and maintenance of wayside power. Metra estimates that replacing one old diesel locomotive with a zero-emission locomotive will reduce nitrogen oxides (NOx) emissions by more than 30 tons per year, thus significantly reducing the agency’s greenhouse gas footprint and greatly improving air quality in the region.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $29,024,137 $29,024,137
State $0 $0 $49,580,000 $49,580,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $78,604,137 $78,604,137

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra put the bid on the street in May 2022 and Metra continues to work on the procurement activities for this project.

Last Updated 12.14.2023

+ Metra Bridge 86 - 78th St Entrance Track & Structure Rail $0 $33,160,000 On Schedule

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $33,160,000 $33,160,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $0 $33,160,000 $48,140,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the bridge and entrance continued to 90% completion. Design is expected to be complete by Q1-2024.

Last Updated 12.14.2023

+ Metra Crew Facilities Support Facilities & Equipment Rail $0 $0 Behind Schedule

Project Details

Description
This project includes, but is not limited to, renovation of existing crew facilities or construction of new crew facilities at existing yard locations across the Metra system. Work may include design of and renovations to interior spaces such as office spaces, locker rooms, and training facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$16,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra will build a new crew facility at Fox Lake Station on the Milwaukee North District Line. The design for this location is 90% complete and the 100% design is expected in July 2023. The designs for the Western Ave and Elgin facilities are 25% complete. Design activities are ongoing.

Last Updated 12.14.2023

+ Metra Consolidated Control Facility (CCF) - Generator & UPS Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
This project funds construction services for the replacement of an existing diesel generator and uninterruptible power supply (UPS) system. The new diesel generator will be powered by natural gas, thereby reducing operating costs and emissions. The system provides an important backup power supply.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,710,000 $0 $0 $1,710,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,263,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra continued to make headway on the project. The generator is 93% complete and expected to be completed by the end of 2023.

Last Updated 12.14.2023

+ Metra UP North Line - South 11 Bridges Track & Structure Rail $117,000,000 $179,216,923 Behind Schedule

Project Details

Description
This project will provide for the reconstruction of bridges and retaining walls on the Union Pacific North Line, and Ravenswood Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $117,000,000 $56,400,000 $173,400,000
State $0 $0 $5,816,923 $5,816,923
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $117,000,000 $62,216,923 $179,216,923

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$162,100,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The 60% design mark was reached during this reporting period and 90% design mark is underway. Benesch is continuing to review and respond to comments from Metra and UPRR as they come in. Once all comments are addressed. Concurrently, a new Existing Facility Protection package will be submitted once a construction contract si awarded.

Last Updated 04.15.2024

+ Metra Elevator Replacement Stations & Passenger Facilities Rail $2,520,000 $48,020,000 Behind Schedule

Project Details

Description
This project will replace or renovate elevators at various stations across the Metra system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $25,610,000 $25,610,000
State $0 $2,520,000 $19,890,000 $22,410,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,030,000 $2,520,000 $45,500,000 $56,050,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,880,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra continued the preparation of the final design Architectural and Engineering task orders for elevator replacement. The Randolph St. elevator has NEPA issues to resolve. The two other elevators at Grand & Cicero are at 90% and proceeding to 100% design completion. A systemwide elevator inspection and assessment is in progress as well.

Last Updated 12.14.2023

+ Metra Car Rehab (Nippon Sharyo P-3) Rolling Stock Rail $0 $0 On Schedule

Project Details

Description
This project funds the continued rehabilitation of self-propelled electric cars used on the Metra Electric. The cars delivered between 2005 and 2007. This first rehabilitation may include, but is not limited to, repair of the car body structure, interior components, and overhaul of propulsion control systems.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$103,383,678
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is currently in phase 8 of 10 of the rehabilitation process. As of the end of March 2024, 227 cars were completed with another three expected to be completed in April. Overhaul activities continue on this project.

Last Updated 04.15.2024

+ Metra Peterson Ridge New Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The new station in the Edgewater neighborhood of Chicago will be built to modern standards and feature a platform-length canopy and a heated headhouse. Four ADA-compliant pedestrian ramps and six staircases will provide numerous access points that are accessible to all. A landscaped plaza with benches and bicycle parking will be installed at the station entrance. A passenger drop-off drive aisle, five accessible parking stalls, and 50 parking stalls will be constructed.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,700,000 $0 $0 $2,700,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,329,765
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Design for the new station was completed. The contracts for construction management and construction contractor were procured and awarded in June and July 2021, respectively. Notice to Proceeds were issued in June 2021 for the Construction Manager and August 2021 for the Construction Contractor. The project had a stop work order in place but it was rescinded. Construction continues with the contractor working on concrete ramps and stairs, platform work, and bridge waterproofing. Union Pacific continues to perform flagging activities for the station construction.

Last Updated 12.14.2023