Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode Sort ascending 2024 Funding 2024-2028 Funding Status
+ Pace 2021/2022 - Professional Project Management and Oversight Consulting Services Contingencies and Administration Bus $0 $0 On Schedule

Project Details

Description
Project Management for Priority Capital Projects - Consulting services to assist Pace in the successful delivery of priority capital projects funded by Rebuild Illinois.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor, STV, completed all the work under contract for PMO services Task Order #5, which included e-Builder administration, augmentation of Pace staff, and other consulting services. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ CTA 2021 - Bus Maintenance Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,365,222
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes. Bus maintenance activities were completed in this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Facilities Critical Needs - Forest Glen Building Demolition Support Facilities & Equipment Bus $0 $0 Behind Schedule

Project Details

Description
The purpose of this project is to eliminate building maintenance costs and security liabilities to CTA associated with the vacant buildings at the Forest Glen Bus Garage (located at 5353 W. Armstrong Avenue and 5601 N. Elston Avenue), as well as to provide additional capacity for bus parking at the Forest Glen Bus Garage. The project scope includes demolition of the buildings at 5353 W. Armstrong Avenue, 5601 N. Elston Avenue, and the existing salt shed (all currently owned by the CTA).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$7,366,852
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Both of the vacant buildings have been demolished and the debris has been removed from the site. Fencing has been installed around the vacant lot. This project was significantly delayed due to the extensive environmental abatement process that was not initially anticipated. Final invoicing related to this process is outstanding. This is the final report on this project.

Last Updated 12.14.2023

+ Pace Construct Salt Shed Support Facilities & Equipment Bus $0 $0 On Schedule

Project Details

Description
Pace is in need of a stand-alone storage solution and will construct a shed to store and secure up to 10tons of bulk rock salt that is used during the winter season. The construction of the shed will be within thefootprint of Pace's parcel. This shed will allow for accessible use with Pace's skidsteer to load rock saltonto the pickup trucks and distribute it on approximately more than 15,000 square yards of grounds(parking lots and driveways), in addition to sidewalks, in a safe and more efficient manner. CurrentlyPace purchases 50-pound bags of salt that have to be loaded manually which has become very unsafein term of personal injury risk and is very time consuming as it has to be loaded multiple times per day.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$75,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A construction contract was awarded. There were some delays related to the Village code requirements and permits. All activities were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace Purchase 40' Low-Floor CNG Buses Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Pace will purchase 40FT CNG Buses.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$75,896,625
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace awarded a new contract for the purchase of additional vehicles in March 2022. The first order was a quantity of 47 CNG buses. The production of these vehicles has been put on hold during this reporting period. A portion of these vehicles will be utilized at the Northwest Wheeling Garage, which is an ongoing project. As Pace establishes a construction schedule for the Wheeling Garage, a production scheduled will be developed for the order of 47 buses.

Last Updated 12.14.2023

+ CTA Facilities Critical Needs - Kedzie Bus Garage Façade Support Facilities & Equipment Bus $0 $0 On Schedule

Project Details

Description
The project will retain a DoR firm to complete a comprehensive assessment of the structure’s exterior envelope to develop remediation and/or replacement plans for concerns regarding the exterior brick veneer delaminating from the backing block. The work will include detailing for caulking, flashing, or other treatments to prevent future similar issues from occurring due to water infiltration. Construction will repair portions of the brick that have fallen from the structure and other repairs to prevent recurrence of the failure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,875,813 $0 $0 $1,875,813

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,596,514
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the project has been completed. Notice to Proceed for construction was issued in February 2023. The general contractor is working on submittals and mobilizing for field work.

Last Updated 12.14.2023

+ Pace Purchase 40' Diesel Buses Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Replacement diesel buses (40') - Pace plans to replace 78 diesel buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$41,786,531
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace placed an order for the delivery of a total of 85 buses. To date, all 85 buses have been received and are in service. The buses are expected to service the routes currently serviced by West Division. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace New Northwest Garage - Wheeling Support Facilities & Equipment Bus $0 $0 Behind Schedule

Project Details

Description
Northwest Wheeling Garage - Completion of the renovation of a 430,000 square feet bus storage and maintenance facility in Wheeling that will replace Pace's Northwest Division garage in Des Plaines. This CNG fueling facility will house approximately 133 buses with 17 maintenance bays and administrative offices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$81,129,563
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace has entered into an Intergovernmental Agreement (IGA) with the Village of Wheeling. The improvements to Old Willow Road have been completed. The initial design has been finalized. The project is in the process of being re-scoped to add the electrification component. The design will be updated once Pace’s electrification study is completed to include the additional scope of work.

Last Updated 12.14.2023

+ Pace Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,801,859 $31,094,850 On Schedule

Project Details

Description
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,801,859 $29,292,991 $31,094,850
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,388,134 $1,801,859 $29,292,991 $38,482,984

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$69,991,388
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. Chassis availability has delayed production. As of May, Pace has received the 152 vehicles and the remaining are in the final stages of production and aiming to deliver all buses by end of 2023. The second order of paratransit buses are ongoing and are expected to be executed in Q4-2023 for the community vehicle program.

Last Updated 12.14.2023