Planning Programs and Projects

This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus. 

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

?

This search filters based on details within the Planning Project. The search box below allows users to search by Planning Project name.

Year Project Title Program Project Type Project Partner Budget Funding Source(s) Status
+ Calumet Park Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Calumet Park $264,126
  • RTA
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct bicycle facilities along 124th Street to better facilitate safe access between bus transit services along Halsted Street to the Ashland Metra station at Ashland Avenue. Additional improvements include completing a sidewalk gap on 124th Street between Laflin and Bishop Streets and pedestrian improvements to the intersection of 124th Street and Laflin Street.

Current Activities

After a period of delays, the Phase II engineering has resumed.

Funding Amounts by Source
Source Amount
RTA $52,825
Federal $211,301

Last Updated 11.15.2023

+ Evanston Pace and CTA Route Access Improvements Access to Transit Program Pedestrian Access to Transit Evanston $300,481
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will convert all of the bus stops in the City of Evanston from flagged to posted stops and include the installation of ADA compliant bus stop pads. In addition, this project will install shelters, pedestrian signals, truncated domes, and new and replaced sidewalk to further enhance the new bus stops. Shelters are proposed for stops with 20 average daily boardings.

Current Activities

The RTA is working on drafting an IGA amendment to reflect the change in scope of the project. Consultant has been selected, the project has been awarded and work has begun on Phase II Engineering.

Funding Amounts by Source
Source Amount
RTA $30,048
Local $30,048
Federal $240,385

Last Updated 03.29.2024

+ Franklin Park Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Franklin Park $890,196
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct bicycle and pedestrian improvements along two corridors in the community: an east-west bicycle route and a north-south pedestrian route that connect the Village’s two Metra stations and three Pace Bus routes to its three industrial areas. Improvements to the bike network will include the installation of eight-foot multi-use paths, on road sharrows, on road dedicated bike lanes, and installation of new signage and path widening along existing paths. The proposed sidewalk improvements on 25th Avenue will provide safe connections from the downtown train stations to the southern industrial area without forcing pedestrians to navigate gaps in the sidewalk network. Employees taking the Pace 303 bus will also benefit from these improvements.

Current Activities

Franklin Park has continued to coordinate with IDOT to get Phase I Engineering approved. All of IDOT's comments have been addressed and approval is pending.

Funding Amounts by Source
Source Amount
RTA $63,169
Local $114,870
Federal $712,157

Last Updated 03.29.2024

+ Harvard Pace Route Access Improvements - Marengo Rd and Ayer St. - Phase I Access to Transit Program Pedestrian Access to Transit Harvard $47,000
  • RTA
Completed

Project Details

Related Reports

Not Available

Description

This project completed Phase I engineering necessary for future pedestrian access improvements along US Rte. 14, IL Route. 173, Marengo Road, and Ayer Street. The future improvements will include new sidewalks, ADA improvements, crosswalks, and a Pace Bus shelter. These improvements will better connect residents to the Harvard Metra Station and the Pace Bus Route 808.

Current Activities

Phase I Engineering Complete and the RTA awarded Harvard funding for Phase II engineering and construction in 2023.

Funding Amounts by Source
Source Amount
RTA $47,000

Last Updated 01.09.2024

+ Hoffman Estates Pace Barrington Road Station Improvements Access to Transit Program Pedestrian Access to Transit Hoffman Estates $675,000
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct a new off-road shared-use path on the north side of Central Road from the existing Paul Douglas Forest Preserve path system to the Pace Park-n-Ride at Barrington Road. The path will be 10 feet wide located generally along the right of way on the north side of Central Road. Destination and distance signing along with traffic controls for intersection and driveway crossings are included. Signal upgrades and modifications at the Central Road / Huntington Boulevard intersection will be made for bicycle and pedestrian users.

Current Activities

 Phase II Engineering has been kicked off and is nearing completion. Cook County DOTH is now the project sponsor.

Funding Amounts by Source
Source Amount
RTA $67,500
Local $67,500
Federal $540,000

Last Updated 03.29.2024

+ Northbrook Pace Route and Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit Northbrook $200,863
  • RTA
  • Local
  • Federal
Completed

Project Details

Description

This project funded the installation of new shared lane markings (AKA sharrows), allowing the Village to implement low-cost recommendations from its Master Bicycle and Pedestrian Plan. The project included the installation of covered bike parking and wayfinding at the Northbrook Metra station.

Current Activities

Construction of the improvements was completed in 2023. 

Funding Amounts by Source
Source Amount
RTA $20,086
Local $20,086
Federal $160,691

Last Updated 04.26.2024

+ Prospect Heights Pace and Metra Improvements Access to Transit Program Pedestrian Access to Transit Prospect Heights $1,870,123
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will construct new sidewalk on the east side of Wolf Road between the Prospect Heights Metra station and Willow Road. This will connect to a previous phase of the multi-use path on Wolf Road that goes north from Willow Road to Palatine Road. The project also includes the installation of pedestrian signals at Camp McDonald Road.

Current Activities

The project has been let by IDOT. Coordination with utilities and Pace continue.

Funding Amounts by Source
Source Amount
RTA $89,347
Local $284,678
Federal $1,496,098

Last Updated 03.29.2024

+ Sauk Village Pace Route Access Improvements Access to Transit Program Pedestrian Access to Transit Sauk Village $50,000
  • RTA
In Progress

Project Details

Related Reports

Not Available

Description

This project will fund Phase I engineering necessary for sidewalk, crosswalk, and other intersection improvements along Sauk Trail and Torrence Avenue. Future improvements will fill sidewalk gaps and make ADA and safety related improvements at key intersections along Pace Bus Route 358.

Current Activities

Phase I Engineering consultant has been selected and work is underway.

Funding Amounts by Source
Source Amount
RTA $50,000

Last Updated 11.19.2023

+ University Park Metra Station Access Improvements Access to Transit Program Pedestrian Access to Transit University Park $50,000
  • RTA
Completed

Project Details

Related Reports

Not Available

Description

This project will fund Phase I engineering needed for a side path that will connect the University Park Metra Station to the I-57 Industrial Corridor. This project will complete a multimodal connection between transit and a growing employment center, making it easier and more safe for workers to access jobs via transit.

Current Activities

Project is complete

Funding Amounts by Source
Source Amount
RTA $50,000

Last Updated 11.19.2023

+ Aurora Transportation Center Access Improvements Access to Transit Program Pedestrian Access to Transit Aurora $995,283
  • RTA
  • Local
  • Federal
In Progress

Project Details

Related Reports

Not Available

Description

This project will create various pedestrian and access improvements to and around the Aurora Transportation Center including entrance modifications at the intersection of Spring Street and the creation of a Kiss and Ride area for passenger drop off. Other improvements include the installation of real time message boards on the platform to indicate train departure/arrival time and track location, installation of bike shelters on the east side of the Metra tracks and at the existing bike racks located along the west side of the platform, and installation of decorative monument signs at the Spring Street and Broadway Avenue entrances. Finally, four commuter transit shelters with heaters will be installed on the platforms and bike lanes along Spring Street, running east and west will be installed to improve access for people using bicycles to access the station.

Current Activities

Last quarter Aurora completed the punchlist items. The shelter lighting is the only outstanding item to complete the job. Lighting expected to be delivered in mid-April.

Funding Amounts by Source
Source Amount
RTA $99,528
Local $99,528
Federal $796,227

Last Updated 03.29.2024