Capital Projects

Regional Capital Program

Download Capital Dataset

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measure which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Projectsort ascending Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Pace Paratransit Vehicles - Expansion Bus $0 $0 $13,000,000 $13,000,000

Description:

New Dial-a-Ride and ADA vehicles for aging population

No Results Found

+ CTA Non-Revenue Vehicle Replacement Program System $2,494,359 $10,944,359 $81,741,905 $70,797,546

Description:

Replacement of vehicles needed for maintenance and operations support

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Non-Revenue Vehicles - Diesel Locomotives Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Equipment and Non-Revenue Vehicles (Diesel Locomotives): Funding will provide for the replacement of CTA's diesel locomotive snow fighters. The self-propelled locomotives with special attachments to remove snow and ice during severe winter weather conditions are able to operate and clear system track, so that CTA can safely power up the system to restore/provide service. When traction power is down, this equipment will also be used to move rolling stock to secure locations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,333,095
$0
$0
$3,333,095

PMO:

Total Project Budget^

$22,731,013

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Aug 2020

End Date

May 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The structural design was approved by the CTA. The project is in full production mode and the contractor managed to start the first engine skid during this reporting period. The first locomotive is beginning the final assembly including all of the wiring, hoses, connection plates, and controls between various parts. CTA and the contractor are coordinating a site visit for when the load testing will be performed by the contractor. If the load test passes, the contractor will commission vehicle #1 and continue the assembly of the remaining vehicles.

Last Updated 06.22.2023

+ Non-Revenue Utility Vehicle Replacement Support Facilities & Equipment System $1,225,000 $3,675,000

PROJECT DETAILS

Description:

Heavy-Duty Vehicles to support routine infrastructure maintenance, emergency repairs, and recovery operations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,225,000
$2,450,000
$3,675,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,225,000
$1,225,000
$2,450,000
$4,900,000

Last Updated 05.18.2023

+ Equipment and Non-Revenue Vehicles Program Support Facilities & Equipment System $1,269,359 $7,269,359

PROJECT DETAILS

Description:

CTA plans to invest funds annually to fund the phased replacement of aged equipment and vehicles used by CTA maintenance groups that include Bus, Rail, Power & Way, and Facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,269,359
$6,000,000
$7,269,359
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,269,359
$6,000,000
$7,269,359

Last Updated 05.18.2023

+ CTA New Control and Training Center System $175,000,000 $175,000,000 $0 $0

Description:

Construct new CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ New Control & Training Center Support Facilities & Equipment System $175,000,000 $175,000,000

PROJECT DETAILS

Description:

CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$175,000,000
$0
$175,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$142,270,670
$175,000,000
$0
$317,270,670

Last Updated 03.15.2023

+ CTA Mid-Life Bus Overhaul (7900 series) Rail $0 $74,151,466 $80,488,850 $6,337,384

Description:

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Overhaul - Mid-Life 450 Nova (7900 Series) Rolling Stock Bus $0 $74,151,466

PROJECT DETAILS

Description:

Funding will provide for the mid-life overhaul of the CTA Nova buses 7900 Series. Buses placed into service between 2014 and 2017 will receive a bus overhaul and will be returned to a state of good repair. This scheduled Mid-Life Bus Overhaul Program will allow for safe, effective operation of the buses throughout their standard estimated life of 15 years.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$74,151,466
$74,151,466
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$74,151,466
$74,151,466

Last Updated 05.18.2023

+ CTA Mid-Life Bus Overhaul (4300 series) Bus $0 $0 $0 $0

Description:

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Mid-Life Bus Overhaul 4300 Series Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Overhauls of the 4300 articulated buses to maintain vehicles, ensure reliability and enable to perform through full useful life

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$9,615,472
$0
$0
$9,615,472

PMO:

Total Project Budget^

$9,615,472

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2022

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Production meetings with the contractor begun during this reporting period and continue to happen. The setup for the first two pilot buses is ongoing and expected to be received in the next reporting period.

Last Updated 06.22.2023

+ CTA Maintenance Facilities Rehabilitation System $12,000,000 $60,000,000 $200,000,000 $140,000,000

Description:

Perform facilities maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Facilities - Substation Roof Repairs Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

Program would address the most immediate critical needs at CTA facilities systemwide to enable their
safe and reliable operation. The goal would be to have an annual appropriation in the CIP that would
be solely dedicated toward addressing this Program. Transit service safety and reliability is affected by
out-of-date rail, bus, and maintenance facilities.
The project will complete roof replacements at five CTA substations: Calvary, Lotus, Des Plaines,
Ashland, and O’Hare. The project will also complete exterior façade repair at the O’Hare Substation,

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,628,767
$0
$0
$3,628,767

PMO:

Total Project Budget^

$3,628,767

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Nov -0001

End Date

Nov -0001

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Design has been completed by CTA’s in-house engineering staff. The Notice to Proceed for construction was issued in March 2023. The contractor is currently working through the submittal process and getting ready to mobilize for field work.

Last Updated 06.22.2023

+ 2023 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $12,000,000 $60,000,000

PROJECT DETAILS

Description:

Maintenance Facilities Rehabilitation:

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$12,000,000
$48,000,000
$60,000,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$12,000,000
$48,000,000
$60,000,000

Last Updated 12.16.2022

+ 2022 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$12,000,000
$0
$0
$12,000,000

PMO:

Total Project Budget^

$12,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2021

End Date

Sep 2024

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements are ongoing. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures.

Last Updated 06.22.2023

+ 2021 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$20,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements are ongoing. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures.

Last Updated 06.22.2023

+ 2020 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$12,000,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Dec 2021

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Facilities improvements is part of an ongoing program. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. This particular part of the program is completed. This will be the final update on this project.

Last Updated 07.10.2022

+ CTA Life-Extending Bus Overhaul 430 (1000 series) Bus $10,195,422 $16,932,852 $19,567,505 $2,634,653

Description:

Overhauls to maintain sufficient fleet until the first order of replacement buses is received

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Life Extending Bus Overhaul - 430 Standard (1000 Series) Rolling Stock Bus $10,195,422 $16,932,852

PROJECT DETAILS

Description:

Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$10,195,422
$6,737,430
$16,932,852
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$14,905,007
$10,195,422
$6,737,430
$31,837,859

PMO:

Total Project Budget^

$1,893,610

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2022

End Date

Oct 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The CTA Team drafted technical specs and project scope were completed and under review as of this reporting period. The team tested a new pilot Haldex air dryers on two buses.

Last Updated 06.22.2023

+ Pace Intelligent Bus System (IBS) Replacement Bus $0 $3,650,000 $18,150,000 $14,500,000

Description:

Equipment for bus tracking, communications, and data

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Intelligent Bus System (IBS) Electrical, Signal & Communications Bus $0 $3,650,000

PROJECT DETAILS

Description:

Intelligent Bus System - Project includes replacement Automatic Passenger Counter equipment (450), routers (600), Apollo cameras (650), IBS servers (8) & software, Storage Area Networks (2), dispatch radios (22), mobile radios (70), Integrated Vehicle Logic Unit Mobile Data Terminals (800), Tate data radios (800), Motorola voice radios (800), and data tower Radio Network Controller equipment (11).

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$3,650,000
$3,650,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,250,000
$0
$3,650,000
$5,900,000

PMO:

Total Project Budget^

$625,000

Budget Status

On Budget

Schedule Status

Behind Schedule

Start Date

Dec 2020

End Date

Jun 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Pace completed the scope of work for IBS services and transit master software upgrades related to IBS servicers and new servers were installed with software upgrades ongoing.

Last Updated 06.22.2023

+ CTA Information Technology Rail $8,661,703 $49,261,703 $124,100,000 $74,838,297

Description:

Improvement of business processes and systems

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Upgrade Office Computer Systems Miscellaneous System $1,700,000 $1,700,000

PROJECT DETAILS

Description:

Funding will provide for the hardware needed for any business-requested upgrades to major IT applications, which may include but not be limited to MMIS, Filemaker Pro, Hyperion, and QuickTrack. This project will also provide for the continued upgrade/replacement of desktop computers, printers servers, software, and associated peripherals.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,700,000
$0
$1,700,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,700,000
$0
$1,700,000

Last Updated 12.16.2022

+ Upgrade Computer Systems - (TOPS, Enterprise Systems) Miscellaneous System $0 $0

PROJECT DETAILS

Description:

To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$1,700,000
$0
$0
$1,700,000

Last Updated 12.16.2022

+ Transit Cyber Security Support Facilities & Equipment System $0 $0

PROJECT DETAILS

Description:

This project calls for the implementation of a comprehensive Transit Cyber Security and Risk Mitigation Project within the Chicago Transit Authority (CTA). Project will include the upgrade, modernization, and hardening of CTA’s core firewall and network infrastructure, adding cyber security tools and services to identify, protect, detect, respond, and recover from and against cyber threats and vulnerabilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,912,000
$0
$0
$3,912,000

Last Updated 12.16.2022

+ Rail Station Video Management Support Facilities & Equipment Rail $0 $0

PROJECT DETAILS

Description:

This project identifies needs for the complete upgrade and cyber security mitigation of CTA’s CCTV video management system across the rail system. Recent cyber security threat and vulnerability assessment (TVA) findings determined the existing video system has significant cyber vulnerabilities with the operating systems, is beyond useful life and is no longer supported. It is necessary to upgrade the video capture and storage infrastructure at over 200 rail facilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$4,913,000
$0
$0
$4,913,000

Last Updated 12.16.2022

+ Information Technology - TOPS Upgrade II Miscellaneous System $0 $1,500,000

PROJECT DETAILS

Description:

To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$1,500,000
$1,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$1,500,000
$1,500,000

Last Updated 12.16.2022

+ Information Technology - Technology Upgrades Rail Engineering & Maintenance Rolling Stock Rail $100,000 $300,000

PROJECT DETAILS

Description:

Various Technology upgrades, such as: Replace RETS engineer computers with ones similar to Infrastructure Engineering at 567 be able to run CAD including using 3D modeling software (SolidWorks, CATIA, Polyworks). Needed for new car programs for which vendors increasingly are providing files in these formats. Improve Skokie server capacity for storage of larger files related to new car/overhaul programs, incident investigations.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$100,000
$200,000
$300,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$100,000
$200,000
$300,000

Last Updated 12.16.2022

+ Information Technology - MMIMS Upgrade Miscellaneous System $0 $2,500,000

PROJECT DETAILS

Description:

The MMIS application is used for managing repairs and issuing parts to the CTA Bus and Rail fleet. The last upgrade of this application started in 2016 with target completion of 2018. By 2022, this version of the MMIS product will no longer be supported by Trapeze, the vendor of the MMIS application. This request is for the next anticipated major upgrade for this mission critical software.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$2,500,000
$2,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$2,500,000
$2,500,000

Last Updated 12.16.2022

+ Information Technology - IVN3/IVN4 Replacement Miscellaneous Bus $861,703 $8,061,703

PROJECT DETAILS

Description:

The purpose of this project is to perform a technological refresh of the IVNs (Intelligent Vehicle Network) computer system on bus to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2023 to have hardware replaced and start refresh project. To provide a technology refresh cycle all IVN (Intelligence Vehicle Network)computers on board the CTA Bus Fleet currently active in the Bus transportation field operations with new IVN5 models.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$7,200,000
$7,200,000
State
$0
$0
$0
$0
RTA
$0
$861,703
$0
$861,703
Service Board / Local
$0
$0
$0
$0
Total
$0
$861,703
$7,200,000
$8,061,703

Last Updated 06.22.2023

+ Information Technology - Hastus Upgrade Miscellaneous System $0 $1,000,000

PROJECT DETAILS

Description:

The purpose of this project is to upgrade to Hastus Version 2022 (or later) to ensure bus and rail scheduling utilizes the advanced scheduling tools Hastus provides to provide 24/7 transit service to CTA riders. This scheduling software utilizes customized rules based on CTA's union rules and also current transit industry trends. Target October 2022 to have hardware in place and start software upgrade project. The current Hastus contract with vendor GIRO requires CTA to begin the update project in Oct 2022 by providing a notice to proceed order in Q4 2022.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$1,000,000
$1,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$1,000,000
$1,000,000

Last Updated 12.16.2022

+ Information Technology - Bus Router Replacements (MP070's) Miscellaneous Bus $0 $4,200,000

PROJECT DETAILS

Description:

The purpose of this project is to perform a technological refresh of the bus routers to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2024 to have hardware replaced and start refresh project. To provide the CTA transit buses entirely new communications router and management platform by transitioning to

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$4,200,000
$4,200,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$4,200,000
$4,200,000

Last Updated 12.16.2022

+ Implement Security Projects - HLS Program Support Facilities & Equipment System $6,000,000 $30,000,000

PROJECT DETAILS

Description:

Implement Security Projects (HLS Program):

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$6,000,000
$24,000,000
$30,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$647,520
$6,000,000
$24,000,000
$30,647,520

Last Updated 12.16.2022

+ Pace Improve Support Facilities Bus $49,750,000 $188,492,000 $237,322,483 $48,830,483

Description:

Improvements to garage facilities including underground storage tanks

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Southwest Division Electrification/Expansion Support Facilities & Equipment Bus $0 $94,142,000

PROJECT DETAILS

Description:

The facilities will be built on a 22-acre site that is situated next door to Pace’s South
Division Garage in Markham and owned by Pace. The purpose of this project is to consolidate certain
operational functions currently operating at each garage into one location. This will improve productivity
and control costs by eliminating duplication. The original plan was to construct three separate buildings:
1) an Active Transit Management Center to accommodate Central Dispatching; 2) a new Central Stores

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$61,000,000
$61,000,000
State
$0
$0
$33,142,000
$33,142,000
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$94,142,000
$94,142,000

Last Updated 12.16.2022

+ North Shore Division Expansion Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

North Shore Division Expansion - A/E design and construction to renovate and expand Pace's North Shore Division bus garage.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$20,000,000
$0
$0
$20,000,000

Last Updated 12.16.2022

+ North Division Electrification/Expansion Support Facilities & Equipment Bus $49,000,000 $77,600,000

PROJECT DETAILS

Description:

Renovation and expansion of North Division Garage located in Waukegan, including installation of charging capabilities for electric buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$49,000,000
$28,600,000
$77,600,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$49,000,000
$28,600,000
$77,600,000

Last Updated 12.16.2022

+ Headquarters Renovation Support Facilities & Equipment Bus $750,000 $16,750,000

PROJECT DETAILS

Description:

Paint and carpet replacement at Administrative Office in Arlington Heights. HQ is currently 2 floors of employees with the building capable of a 3rd floor structure. Adding a third floor we would incorporate high efficient heating and cooling with hospital grade filters update the colors and carpet and workspace on the first and second floor to match the third floor.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$750,000
$16,000,000
$16,750,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$750,000
$16,000,000
$16,750,000

Last Updated 12.16.2022

+ Fire Loop System Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Replacement of underground loop, piping, valves, and pump for fire suppression.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$2,050,000
$0
$0
$2,050,000

Last Updated 12.16.2022

+ Construct Salt Shed Support Facilities & Equipment Bus $0 $0

PROJECT DETAILS

Description:

Pace is in need of a stand-alone storage solution and will construct a shed to store and secure up to 10
tons of bulk rock salt that is used during the winter season. The construction of the shed will be within the
footprint of Pace's parcel. This shed will allow for accessible use with Pace's skidsteer to load rock salt
onto the pickup trucks and distribute it on approximately more than 15,000 square yards of grounds
(parking lots and driveways), in addition to sidewalks, in a safe and more efficient manner. Currently

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$75,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2021

End Date

Mar 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

A construction contract was awarded. There were some delays related to the Village code requirements and permits. All activities were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023