Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding Sort descending 2024-2028 Funding Status
+ Pace 2020 - Bus Stop Shelters, Benches, Pads & Signs Stations & Passenger Facilities Bus $0 $0 Behind Schedule

Project Details

Description
Engineering drawings, manufacture, and installation of bus stop shelters, concrete pads, and benches, including a heated bus shelter at the Waukegan Metra station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,550,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace issued bids for construction of the pads and shelter installations and was awarded in this reporting period. Installation continues with this project where the previously ordered 10-15 shelters were received. The vendor will continue activities as assigned.

Last Updated 12.14.2023

+ CTA Green Line Jackson Park Branch Trackwork Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The Green Line Improvements project will largely focus on track replacement and structural repairs. FY 2020 funding will improve Green line infrastructure improvements including Track, Substations, Traction Power Cable Replacement and all local traction power cables throughout the line system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,855,446
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Work under this project started in April 2021. The work is being performed by CTA in-house work forces. Activities related to tie replacement, cross grinder and flange replacements are ongoing. Material purchases are also ongoing.

Last Updated 12.14.2023

+ CTA 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,930,000 $0 $0 $13,930,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,564,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 12.14.2023

+ Metra 95th Street Station CSU Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed. The station will be made fully accessible with the addition of elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $37,000,000 $0 $0 $37,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this station reached 100%. There were delays on this project associated with the National Environmental Policy Act (NEPA) review process as well as coordination with the Chicago State University and additional scope added to the design. The project is in procurement and is aiming to go out for bids before the end of the year for a General Contractor.

Last Updated 12.14.2023

+ CTA All Station Accessibility Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $4,633,224 Behind Schedule

Project Details

Description
Funding will provide for second installment of funds to rehabilitate and/or replace elevators throughout the system. This funding along with the granted Rebuild Illinois funds provide in part for phase one of the program. For the Elevator Replacement Program, complete inspection of an elevator will need to be conducted to identify all deficiencies. Once inspections are complete, the CTA will need to determine whether rehabilitation or replacement is warranted. The individual scope of work for each elevator will vary depending on its condition and elevator type (machine room-less (MRL), geared, gearless, or hydraulic). Inspections of all components of the following systems are required to determine the full scope of work at each individual elevator and to determine whether rehabilitation or replacement is warranted:• Mechanical Systems• Electrical Systems• Material Finishes• Control Systems• Communication Systems• Security Systems• Structural Members• ADA Code Compliance • Municipality Building Code Compliance
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $4,633,224 $4,633,224
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,585,000 $0 $4,633,224 $16,218,224

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,370,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for the designer has been issued in June 2022. The designer is completing site assessments and elevator inspections. An assessment report will be developed to prioritize the elevator replacement or rehabilitation locations. The report will also provide the scope of work needed for each individual elevator. A draft report is expected to be submitted to CTA in June. Once the report is finalized, CTA will issue a procurement for construction based on the priority recommendations from the assessment report.

Last Updated 12.14.2023

+ CTA Systemwide Tactical Traction Power Upgrades (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
Tactical Traction Power (Equipment/Cable/Enclosures) -The purpose of this project is to implement traction power system improvements that will enable the CTA to continue to meet existing traction power needs, increase traction power capacity to meet future demand, and address state of good repair by repairing or replacing worn or obsolete equipment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,864,902 $0 $0 $10,864,902

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,166,629
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor made significant headway during this reporting period and was able to reach substantial completion in July of this year. The contractor was able to finish the final walkthrough inspection and completed all punchlist items and is in contract closeout. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Central Warehousing Support Facilities & Equipment Rail $0 $9,775,000 On Schedule

Project Details

Description
Metra acquired an existing warehouse facility to develop a centralized warehouse for materials that support the activities of the commuter railroad system. The central warehouse will combine 4 existing buildings that are overcrowded and create efficiencies by allowing Metra to buy in bigger quantities and lower freight delivery costs. Renovations will continue as part of a multi-year, phase-funded project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $9,775,000 $9,775,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,700,000 $0 $9,775,000 $33,475,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$18,700,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The property acquisition, environmental site assessment and interior demolition were previously completed. Roof rehabilitation work has been ongoing and is scheduled to be completed at the end of May. Interior build out work, lighting and fencing will be completed by Metra forces after the roof work is finished.

Last Updated 12.14.2023

+ CTA New Control & Training Center Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations. This project consolidates training functions across the agency within a centralized facility. Currently training is dispersed throughout the CTA system at various garages, yards, and offices due to space limitations. Thousands of CTA operating and maintenance employees use these facilities for employee training, instruction programs, and employee engagement. The primary rail and maintenance training is performed at a leased space and lacks all components necessary for proper training.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $317,270,670 $0 $0 $317,270,670

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$239,988,009
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 30% Schematic Design submittal was submitted on 01/24/2024. The 60% Detailed Design submittal was submitted on 03/4/24. CTA is working with the contractor for items related to that design submittal. The 100% advance work package for earthwork was submitted to DoR on 3/8/24 and continues to have the contractor working on it to address comments. The 90% design submittal is expected to be submitted to CTA in mid-May and the 100% design submittal is expected to be submitted in September 2024.

Last Updated 04.15.2024