Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status Sort descending
+ Metra CREATE - P2 Rock Island District Connection Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project will provide engineering for the 75th Street Corridor Improvement Project (CIP) that will relieve rail congestion by separating freight and passenger rail lines. Bottlenecks will be eliminated, and train idling will be reduced.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$23,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is currently in design. The 60% design has been completed. Design development activities continue to progress to 90% design. Procurement process for Rightof- Way acquisition is ongoing.

Last Updated 12.14.2023

+ Metra Cybersecurity Systems N/A Rail $955,000 $955,000 On Schedule

Project Details

Description
The goal of this project is to enhance Metra's cybersecurity and implement Metra’s cybersecuritystrategy. The objectives of this strategy are to implement vulnerability risk management, institute patchautomation, establish security operations sharing, and counter emerging threats through detection andresponse.This project will fund the purchase and installation of equipment and software for scanning,prioritization, and remediation of vulnerabilities. This also includes the purchase of hardware andsoftware for multiple networks and segments including IT systems, positive train control (PTC),SCADA infrastructure, and signal, telecom, and camera networks. The purchased equipment will covervulnerability scanning and prioritization, patch automation and remediation, Security Information andEvent Management (SIEM), and endpoint detection and response (EDR).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $955,000 $0 $955,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,700,000 $955,000 $0 $2,655,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Contracts for asset management and message broadcast software were awarded and software installation completed for 6 contracts. Procurement activities are in process for cybersecurity risk mitigation, anti-malware, and SharePoint architect.

Last Updated 12.14.2023

+ Metra Seeger Interlocking Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
This project will provide funds for the replacement of the Seeger Interlocking on Metra’s Union PacificNorthwest line (MP 18.5). The layout of the control point only allows 30 mph crossover speeds forcommuter trains. The goal of this upgrade, in addition to updating the equipment, would be to increasethe train speeds to 40 mph, and upgrade the switch layouts to meet current railroad designspecification.The existing signal system is approximately 50 years old and requires replacement due to age andcondition. The signal system has had malfunction issues that have caused delays. The replacementequipment will include a modern, solid state control point and an upgraded switch machine.By renewing the signal infrastructure with the latest technologies, Metra can increase operationalefficiency, enhance safety, reduce delays, and have a life expectancy of additional twenty plus years.FY2020 PAYGO funds will be used to implement this project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The status for this project is completed and final bills remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,314,071 $0 $0 $4,314,071

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th w

Last Updated 12.14.2023

+ CTA 2020 - Facilities Maintenance - Systemwide Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Facilities improvements is part of an ongoing program. The preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. This particular part of the program is completed. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,030,427
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Fiber Optic MED Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
This project consists of the replacement of the coaxial cable and copper cable used to conduct voice and signal data on the Metra Electric District’s Main Line. The fiber optic cable will connect to the recent installation on the South Chicago Branch and Blue Island Branch and extend to the downtown terminal. Existing cable will be replaced with fiber optic cable. New cable will be hung on the catenary structures in a manner similar to the existing cable.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designer reached 100% design completion. The design was submitted and is under review by Metra.

Last Updated 12.14.2023

+ Pace Fixed Route Electric Buses Rolling Stock Bus $0 $78,009,128 On Schedule

Project Details

Description
Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $72,614,500 $72,614,500
State $0 $0 $5,394,628 $5,394,628
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $26,192,311 $0 $78,009,128 $104,201,439

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$28,810,673
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace executed a change order to purchase an additional two buses, bringing the total to 22 electric buses. Delivery of charging equipment began this quarter.

Last Updated 12.14.2023

+ Metra Morgan Interlocking Electrical, Signal & Communications Rail $1,500,000 $1,500,000 On Schedule

Project Details

Description
This project will provide design and construction funds for the replacement of the Morgan Street Interlocking on Metra’s Milwaukee C&M subdivision, the signal system infrastructure between Canal Street and A-2 interlocking. The Morgan St. Interlocker and crossings were originally installed in the early 1960’s. The signal system is also affected by the extreme weather conditions common to the Chicago region. It has become extremely difficult in recent years to get parts to make repairs to keep the system operational.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,500,000 $0 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,870,000 $1,500,000 $0 $5,370,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$11,320,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Morgan Non-Vital 60% design was completed. The Morgan Vital work has a 60% preliminary design submittal which was submitted and under review. An IGA with CDOT was executed and CDOT is reviewing the civil drawings. Once approved and comments addressed, the civil drawings before the designer can proceed to the 90% design submittal.

Last Updated 12.14.2023

+ Metra Elmhurst Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project will fund Metra’s portion of a larger station renovation/expansion in Elmhurst. It will leverage CMAQ funds obtained by the Village of Elmhurst to construct a larger station to accommodate the growing ridership.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Preliminary engineering and NEPA process were completed. The Village of Elmhurst is leading the design with their consultant. The designer achieved the 60% design milestone and continues to proceed to 90% design.

Last Updated 12.14.2023