Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ CTA Skokie Shops - Electronic & Hydraulic Repair Room Expansions Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project will provide for the expansion of four areas that are currently situated in the West Building of Skokie Shops to support the 5000 and 7000-series railcars maintenance cycles. All areas will be upgraded to new “clean” rooms that require the space to be enclosed, well lit, properly grounded, and air conditioned.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,293,685
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Currently, the General Contractor continues to submit process plans for construction and mobilization on site. Delivery of onsite storage containers was completed in this reporting period. CTA continues to coordinate and plan with the contractor for the phasing of the expansion. Concrete removal in one of the areas was completed and the contractor continues to install structures for upgrades to the existing mezzanine. The contractor will work to complete the mezzanine and then work next to the Diagnostic Center.

Last Updated 12.14.2023

+ Pace South Campus Project - Markham Support Facilities & Equipment Bus $0 $0 Behind Schedule

Project Details

Description
This project will provide for construction, project management oversight, project administration, and any associated equipment and services for the Pace South Campus project. New facilities will be built on a 22-acre site that is situated next door to Pace’s South Division (2107 W. 163rd Place) Garage in Markham, Illinois, which is already owned by Pace. The purpose of this project is to consolidate certain operational functions currently operating at each garage into one location.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$35,215,466
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction has been issued in January 2022. Construction activities are in progress. Construction and procurement activities continue. The Acceptance facility gas service is complete. Landscaping services have been scheduled and will start soon. Site lighting wiring is progressing.

Last Updated 04.15.2024

+ Metra Substation Improvements - Matteson Substation Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project is for the replacement of the rectifiers at substations along the Metra Electric Line. The rectifiers are 35 years old and they have long exceeded their useful life. Replacement parts are not available. The Matteson Substation has been identified as a high priority location. Planned work at Matteson includes construction services to replace and add traction power equipment including a 15kv AC switchgear lineup and two?dry type copper?winding traction power transformers. Other locations identifed under this project include Jackson Substation and Homewood Substation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$17,192,751
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Final Design Review meeting for the Matteson Substation project took place in March 2023. Factory Acceptance Testing for the rectifiers and transformers has been completed and procurement of long lead time items such as transfer switches and switch gears is ongoing. Site construction work is scheduled to begin in May. The contractor poured the concrete foundation slab and equipment pads for the Matteson substation. The contractor also reworked temporary power for the project site, performed conduit work in the existing substation vault, and formed & poured equipment pads. The Jackson Substation project is in the design phase. The design for that project is 75% complete.

Last Updated 04.15.2024

+ CTA Systemwide Tactical Traction Power Upgrades (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
Tactical Traction Power (Equipment/Cable/Enclosures) -The purpose of this project is to implement traction power system improvements that will enable the CTA to continue to meet existing traction power needs, increase traction power capacity to meet future demand, and address state of good repair by repairing or replacing worn or obsolete equipment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,864,902 $0 $0 $10,864,902

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,166,629
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor made significant headway during this reporting period and was able to reach substantial completion in July of this year. The contractor was able to finish the final walkthrough inspection and completed all punchlist items and is in contract closeout. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Systemwide Yard Improvements Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project will provide design and construction funds for large-scale yard improvement projects at the various yards utilized by Metra. Sub-projects may include, but may not be limited to, the improvement or replacement of machines and equipment, upgrades to buildings and crew facilities, and the construction of new equipment and systems. Project activities may include, but are not limited to, HVAC and MEP system upgrades, securing hazardous and flammable materials, fire suppression system improvements, track renewal, new crosswalks, and yard platforms, replacing switch machines and components, and other activities. This project will allow for flexibility to implement high-priority yard improvements between districts that are integral to the continuation of Metra’s safe and reliable operations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $19,237,000 $0 $0 $19,237,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction management and construction activities for the CCF project. Procurements for construction services were rebid out for the 47th St. Coach & Diesel Shop project. The Fox Lake cable reel replacement project started construction as well as for the HVAC replacement system for OTC, Van Buren, and Kensington Yards.

Last Updated 12.14.2023

+ CTA Tactical Traction Power (Equipment/Cable/Enclosures) Track & Structure Rail $0 $0 On Schedule

Project Details

Description
State of Good Repair projects and replacing obsolete equipment on CTA rail signal system
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,125,768 $0 $0 $2,125,768

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,293,685
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Permits for the project were received in the last reporting period. Currently, the General Contractor is submitting process plans for start of construction and mobilization on site. Delivery of onsite storage containers is ongoing. CTA is working with the contractor to start the first phase of the project, which is the electrical shop equipment relocation.

Last Updated 12.14.2023

+ Metra Ticket Vending Machines Stations & Passenger Facilities Rail $0 $7,500,000 On Schedule

Project Details

Description
This project is the first phase of installing up to 310 ticket vending machines (TVMs) at selected stations throughout the Metra system to provide added amenities to Metra customers. The TVMs will offer a variety of ticket purchasing options and make purchasing tickets faster, easier, and more convenient for our customers. The TVMs will be fully ADA-accessible and will offer the ability to purchase tickets using contactless cards and mobile wallet applications and will no longer need to insert debit/credit cards into the machine.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $7,500,000 $7,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $33,510,000 $0 $7,500,000 $41,010,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$46,000,090
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is currently in the production phase. The manufacturing of the first 100 TVMs is in progress. Seventy-Seven (77) total TVM’s have been delivered and installed. The extended pilot program continues with the newly installed TVM’s.

Last Updated 04.15.2024

+ Metra Ties & Ballast MED Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,100,000 $0 $0 $9,100,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project included ironworkers; track, signal and utilities work. Track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Ties & Ballast MWD-W Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Metra’s track renewal crew will rehabilitate dozens of miles of track along the Milwaukee District West (MD-W) Line in 2022. The project will be the most comprehensive investment in track conditions since Metra acquired the MD-W in 1987. Metra forces will Replace ties, clean or replace ballast, and replace switch components to provide smoother, faster, and safer track conditions. Metra partners with the Canadian Pacific Railroad to fund improvements to particular portions of the MD-W as freight train traffic degrade track conditions more rapidly than Metra trains.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,075,000 $0 $0 $10,075,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,075,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include ironworkers; track, signal and utilities work. Canadian Pacific (CP) funded a portion of the costs, and additional locations were added to the project.

Last Updated 12.14.2023

+ Metra Ties & Ballast RID Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,200,000 $0 $0 $3,200,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,920,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. Track and structure improvements began during this reporting period. Work is currently on track 2 of Milepost (MP) 0.2 to MP 50.5 and on track 3 of MP 0.3 to MP 1.0.

Last Updated 12.14.2023