Capital Projects

Regional Capital Program

Download Capital Dataset

 

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects were defined in the Invest in Transit  Regional Transit Strategic Plan and are updated on an annual basis. This page shows details about the funding for each priority project.

The 2023-2027 5-Year Regional Capital Program includes over 300 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2023-2027 Regional Capital Program. Each listing also shows the core requirement(s) and strategic goals that each project helps to address, as defined in the region’s new performance-based capital allocation process.

Notably, the region has committed to dedicating 20% of programmed funds to projects that fulfill the core requirements of improving equity or achieving full accessibility for 2025 and beyond as a part of the new performance-based capital allocation process. 

The Service Boards have met and exceeded the 20% goal for the 2025, 2026 and 2027 budget years. Detailed analysis of the core requirements and strategic goals can be found in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

 

Search More info

Filter

Core Requirement(s) More info

Strategic Goal More info

Agency Priority Projectsort descending Mode 2023 Funding 2023-2027 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Red Line Extension Rail $154,480,519 $339,480,519 $3,541,709,184 $3,202,228,665

Description:

Extension of the Red Line from 95th Street to 130th Street

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Red Line Extension - Planning, Preliminary Engineering Extension Rail $154,480,519 $339,480,519

PROJECT DETAILS

Description:

Red Line Extension Planning, Preliminary Engineering
Funds will provide for planning, program management, and preliminary engineering services for the anticipated extension of the south leg of the Red Line. Funding will allow for the CTA to continue project work through the Project Development phase where the Final Environmental Impact Statement (EIS) and Preliminary Engineering for the project will be completed.
CIP also provides the 30% non-Capital Improvement Grant match ($310M) commitment needed to successfully complete Project Development.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$30,000,000
$30,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$154,480,519
$155,000,000
$309,480,519
Total
$60,240,816
$154,480,519
$185,000,000
$399,721,335

Last Updated 12.16.2022

+ CTA Red Line Improvements Rail $0 $0 $396,400,000 $396,400,000

Description:

Upgrades and State of Good Repair projects along the Red Line

No Results Found

+ CTA Red Purple Modernization Rail $0 $0 $5,956,152,265 $5,956,152,265

Description:

Advancement of the Red and Purple Modernization (RPM) Program, the largest line rebuild and capital improvement project in CTA history

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Red/Purple Modernization - Phase 1 Modernization Rail $0 $0

PROJECT DETAILS

Description:

North Main Line - RPM The purpose of the Red and Purple Modernization (RPM) Program is to expand capacity to meet growing ridership demand; reduce travel times; improve access to job markets and destinations; better utilize existing transit infrastructure; bring the existing infrastructure to a state of good repair; and improve access to the system for patrons with disabilities.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$344,847,735
$0
$0
$344,847,735

PMO:

Total Project Budget^

$2,203,408,226

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Oct 2019

End Date

Jan 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

Precast span erection was completed for the Lawrence to Bryn Mawr Modernization (LBMM) and the contractor continued welding rails along the track as well as prepping for installation of noise walls. Station house construction and steel erection for stairs and platform work at Bryn Mawr began this reporting period and are ongoing. The Clark relay house was set and traction power bracket was installed. The Winona signal racks are currently being installed in the relay room and testing will commence once the rack installation is completed.

Last Updated 06.22.2023

+ Pace Regional Transit Signal Priority (RTSP) System $1,913,378 $7,913,378 $36,599,307 $28,685,929

Description:

Expand Transit Signal Priority installations region-wide

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $1,913,378 $7,913,378

PROJECT DETAILS

Description:

Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,680,000
$6,000,000
$7,680,000
State
$0
$0
$0
$0
RTA
$0
$233,378
$0
$233,378
Service Board / Local
$0
$0
$0
$0
Total
$2,400,693
$1,913,378
$6,000,000
$10,314,071

PMO:

Total Project Budget^

$10,293,685

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Dec 2019

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th.

Last Updated 06.22.2023

+ CTA Replacement Bus Purchase (1000 Series) - 600 Clean Diesel Buses Bus $98,442,904 $207,739,008 $274,459,219 $66,720,211

Description:

Ongoing need to replace buses as they age

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Replace Buses - Options to Purchase Up To 500 of 1,030 Rolling Stock Bus $98,442,904 $207,739,008

PROJECT DETAILS

Description:

The scope of this project will provide for the engineering, purchase, and inspection of fully accessible, air conditioned Clean Diesel buses; including a spare parts inventory. Engineering includes: development of specifications, pre-bid engineering meetings, onsite inspections of prospective bidders and/or their vendors’ plants, inspection of buses during production and acceptance of vehicles after delivery. 5 Year funds will continue funding stream for the Option(s) to replace up to 500 additional buses.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$77,567,904
$85,371,298
$162,939,202
State
$0
$20,875,000
$23,924,806
$44,799,806
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$49,858,165
$98,442,904
$109,296,104
$257,597,173

PMO:

Total Project Budget^

$355,437,001

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jan 2020

End Date

Sep 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

All 100 buses from the base order have been delivered and placed in service. Under Option 1, 63 of the 100 buses have arrived at CTA and 43 have been placed in service. All 100 buses are expected to be delivered by June 1. CTA has also exercised Option 2 for an additional 100 buses. The production of vehicles under Option 2 is expected to begin in June.

Last Updated 06.22.2023

+ CTA Replacement Bus Purchase (4300 series) - Electric Buses Rail $0 $0 $140,000,000 $140,000,000

Description:

Ongoing need to replace buses as they age

No Results Found

+ CTA Replacement Bus Purchase 1000 Series - 430 Electric Buses Rail $0 $0 $459,358,312 $459,358,312

Description:

Ongoing need to replace buses as they age

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase up to 6 Electric Buses with Charging Systems Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Bus funding provides for a future order of up to six 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to six 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$3,496,667
$0
$0
$3,496,667

Last Updated 12.16.2022

+ Purchase up to 70 Electric Buses and up to 9 Charging Stations Rolling Stock Bus $0 $0

PROJECT DETAILS

Description:

Purchase up to 70 Electric Buses and up to nine Chargers
- Bus funding provides for a future order of up to 70 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to 70 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

PMO:

Total Project Budget^

$71,991,905

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

Jun 2018

End Date

May 2025

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

The charging stations were received and installed and reached substantial completion in January 2021. In Q4-2021, seventeen (17) production buses were completed and delivered to CTA. The installation of revenue fare collection systems, communication equipment, network systems were completed in Q2-2022. A total of twenty-three (23) buses were delivered. Nineteen (19) are in service and four are being used at the 74th Garage for operator training. In this reporting period, CTA has exercised an option for an additional twenty-two (22) buses.

Last Updated 06.22.2023

+ CTA Replacement Buses (4000 Series) - Electric Buses Bus $23,493,631 $143,986,783 $287,703,333 $143,716,550

Description:

Ongoing need to replace buses as they age

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Purchase Articulated Electric Buses and Charging Equipment Rolling Stock Bus $23,493,631 $143,986,783

PROJECT DETAILS

Description:

Funding will provide for a new procurement intended to replace 208 articulated 4000-Series buses with the equivalent number of electric buses

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$23,493,631
$111,656,079
$135,149,710
State
$0
$0
$8,837,073
$8,837,073
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$5,843,016
$23,493,631
$120,493,152
$149,829,799

Last Updated 12.16.2022

+ RTA RTA Funding Program(s) System $0 $0 $0 $0

Description:

Projects and programs undertaken by RTA

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ RTA TBD Miscellaneous System $0 $0

PROJECT DETAILS

Description:

Projects TBD

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$0
$0
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$0
$0

Last Updated 12.16.2022

+ Pace Security, Computer, Software, and Office Systems Upgrades Bus $1,963,505 $13,544,635 $47,900,000 $34,355,365

Description:

Upgrade systems to provide enhanced asset protection and business systems

Project Title Asset Category Mode 2023 Funding 2023-2027 Funding PMO
+ Bus Security Cameras Electrical, Signal & Communications Bus $0 $2,000,000

PROJECT DETAILS

Description:

This project purchases security cameras for bues.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$2,000,000
$2,000,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$2,000,000
$2,000,000

Last Updated 12.16.2022

+ Computer Systems - Hardware & Software Support Facilities & Equipment Bus $0 $3,500,000

PROJECT DETAILS

Description:

Computer Systems/Hardware & Software - Projects in 2021 include upgrades, licenses, and training for Hastus route-scheduling software, RideCheck ridership data software, ArcGIS software, and the Pace website. Procurement of digital screens for the interior of buses is also included.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$0
$3,500,000
$3,500,000
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$0
$3,500,000
$3,500,000

PMO:

Total Project Budget^

$1,100,000

Budget Status

On Budget

Schedule Status

On Schedule

Start Date

May 2022

End Date

Dec 2023

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status

This project is underway, and Pace executed a contract for redesigning Pace’s website. Activity continued with a rebid for the procurement of digital screens for the interior of the buses due to low responses. Additional tasks will be added throughout the duration of this project.

Last Updated 06.22.2023

+ Onboard Digital Screens Electrical, Signal & Communications Bus $1,963,505 $8,044,635

PROJECT DETAILS

Description:

Purchase and install digital screens inside existing buses to display passenger information, such as next-stop announcements, detour notices, and passenger notices.

Core Requirement(s)
Maintain and Improve Safety and Reliability
Achieve Full Accessibility
Meet Regulatory Requirements
Improve Equity
Strategic Goal
Deliver Value on Investment
Build on the Strengths of Our Network
Stay Competitive

Funding Amounts by Source:

*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table
Source Previous Funding* 2023 Funding 2024-2027 Funding Total
Federal
$0
$1,963,505
$6,081,130
$8,044,635
State
$0
$0
$0
$0
RTA
$0
$0
$0
$0
Service Board / Local
$0
$0
$0
$0
Total
$0
$1,963,505
$6,081,130
$8,044,635

Last Updated 06.22.2023