Planning Programs and Projects

This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus. 

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

?

This search filters based on details within the Planning Project. The search box below allows users to search by Planning Project name.

Year Project Title Program Sort ascending Project Type Project Partner Budget Funding Source(s) Status
+ Hanover Park Village Center Transit-Oriented Development (TOD) Community Planning Transit-Oriented Development Plan Hanover Park $100,000
  • RTA
  • Local
Completed

Project Details

Description
This project created a transit-oriented development plan for the Village's Metra station area. The station area was designated in the 2010 Village of Hanover Park Comprehensive Plan as the location of the new Village Center and this plan built upon this vision by planning for increased residential density, mixed use retail, and freestanding retail and office space. The plan is anchored on the Village's existing Metra station and also accounts for anticipated land use changes due to a planned boulevard as an approach to the western terminus of the Elgin-O'Hare Expressway. The Village Board formally adopted the Transit-Oriented Development Plan as an amendment to their comprehensive plan in May 2012.
Current Activities
The Village's TOD plan continues to encourage development adjacent to the Hanover Park Metra station. A 126 unit townhome development was completed in 2014 and is located approximately 1/4 mile north and within convenient walking distances of the Metra station and connecting Pace bus services (route 554).

Through the RTA Community Planning Program, the Village participated in a RTA/ULI Developer Discussion Panel to solicit guidance and advice from the development community on ways to attract investment in the TOD area. This panel convened in February 2014 and a summary report of the discussion can be found below in the Study Documents.
Funding Amounts by Source
Source Amount
RTA $80,000
Local $20,000

Last Updated 06.18.2018

+ DuPage Area Transit Plan Community Planning Transit Improvement Plan DuPage Mayors & Managers $277,245
  • RTA
  • Federal
Completed

Project Details

Related Reports
Description

This study was conducted by the DuPage Mayors and Managers Conference in cooperation with DuPage County. The DuPage Area Transit Plan included both a short term and long range transit plan for the County. Throughout the development of the plan stakeholders from the county including elected officials, county and local community staff, and area residents were engaged through an extensive grass roots public involvement process to provide input into the plan. This process resulted in the identification of quality of life issues with respect to the provision and availability of transit service in the County.

Current Activities

The plan was completed in August 2002. The RTA also funded an update to this study. Please visit https://rtams.org/projects/planning/2746 for more information on the updated study. In 2013 the Village of Glen Ellyn was awarded CMAQ program funds, via the RTA's Access to Transit Improvement Program for multi-modal access improvements to Pace Route 301, which was a recommendation made in the DuPage Area Transit Plan.

Funding Amounts by Source
Source Amount
RTA $150,778
Federal $126,467

Last Updated 02.13.2024

+ La Grange Stone Avenue Station Access Improvement Plan Community Planning Pedestrian Access to Transit La Grange $0
  • RTA
Completed

Project Details

Description
The RTA worked with the Village to convene a working group consisting of Village staff, RTA staff, CMAP, Metra, ATA BNSF Railway and the ICC to identify ways to improve pedestrian mobility and access to the Metra Station.
Current Activities
The Village used this document to seek out funding opportunities to fund the recommended improvements. In 2013 CMAP approved the RTA's submittal to fund 80% of the cost for local access to transit capital improvements for the Stone Avenue Metra Station, as recommended in this plan. The RTA has approved the local match as part of the 2014 budget and projects began in mid-2014. The full Access Improvements report can be found below in the Study Documents section below.
Funding Amounts by Source
Source Amount
RTA $0

Last Updated 06.13.2017

+ Skokie-Dempster Station Area Plan Community Planning Transit-Oriented Development Plan Skokie $124,710
  • RTA
  • Local
Completed

Project Details

Description
This project will create a transit-oriented development plan for an approximate ½ mile radius of the future relocated and elevated Skokie-Dempster Station on the CTA Yellow Line. The CTA is currently conducting an Alternatives Analysis to extend the Yellow Line from the current terminus at Skokie-Dempster to Old Orchard Road. If the line is extended, the existing Skokie-Dempster Station will be elevated near its current location. The new elevation presents an opportunity to improve circulation around the station where the at-grade tracks and station currently act as a physical barrier limiting development. The goal of the project is to create a circulation plan, a corresponding market study, and land use analysis for the Skokie-Dempster Station area.
Current Activities
The plan has been finalized. The RTA will offer implementation assistance as needed. In 2015, Skokie received CMAQ program funding, via the RTA's Access to Transit Improvement Program, for pedestrian access improvements and additional bicycle parking at the Dempster Station. In 2016, the Village announced that a Target store will be built on a formerly Village-owned property adjacent to the Dempster station. It is expected to be open in late 2017. As of recent, the following projects are approved/under construction/completed in TOD radius: -A Single-Family Detached Homes project at Floral/Cleveland -Completed in November 2018 -A Mixed-Use Townhomes project at 8163 Lincoln Avenue -Under Construction as of April 2018 -A Retail project at 4844-4852 Main Street -Completed in June 2018 -A Mixed-Use Townhomes project, 'Elmwood Collection' -Under Construction as of April 2018 -A Mixed-Use Apartments project at 8025 Skokie Boulevard -Approved in March 2018 -A Live-Work Townhomes project, 'Luxury on Lincoln' -Under Construction as of Nov 2018 -A Mixed-Use Condo project at 8039 Elmwood Avenue -Under Construction as of June 2019 -'Illinois Science + Technology Park' -Under Construction as of January 2019 -A Commercial Development project, 'Ignite Gaming' -Completed in December 2019
Funding Amounts by Source
Source Amount
RTA $99,768
Local $24,942

Last Updated 09.16.2019

+ Cicero Connections Initiative Community Planning Transit-Oriented Development Plan Cicero $148,129
  • RTA
  • Local
Completed

Project Details

Description

This project created a transit-oriented development and transit improvement plan, focusing on the Town's Metra station, two CTA stations (Cicero and 54th / Cermak) and eleven Pace and CTA bus routes. The plan provides recommendations to improve mobility and connections between transit services, stimulate TOD investment in the Town's transit station areas, and connect dense housing areas with transit, walkable commercial development and job centers.

Current Activities

The Plan was adopted by the Town Board on November 11, 2014. The Town has initiated some implementation efforts by securing technical assistance in 2018 from the RTA to amend the Town Zoning ordinance. 

In 2021 the Chicago Transit Authority was awarded funds for design engineering to improve the at-grade crossing of the Pink Line with Cicero Avenue. As identified in the plan, the condition of the roadway and the protective rubber boots at the crossing have deteriorated over time, creating hazardous conditions for motorists and pedestrians. In addition, the signal system, roadway, and pedestrian gate mechanisms at the grade crossing will be upgraded. The CTA will work with the Illinois Department of Transportation (IDOT) to make these critical system improvements. Changes to this grade crossing are a priority due to several safety incidents at the crossing that have put CTA staff and passengers at potential risk. 

Funding Amounts by Source
Source Amount
RTA $118,503
Local $29,626

Last Updated 09.28.2021

+ Fox River Grove Downtown Redevelopment Plan Community Planning Transit-Oriented Development Plan Fox River Grove $72,500
  • Local
  • Federal
Completed

Project Details

Description
The Fox River Grove Downtown Redevelopment Plan developed a market-based concept plan for the Metra station area. The plan specifically utilized the proximity of the Fox River to the downtown and proposed new commuter rail facilities as a key to redevelopment. Given that the downtown is bisected by a major arterial and the commuter rail line, that are adjacent and parallel to each other, a pedestrian underpass under U.S. Route 14 was recommended to help achieve greater connectivity between the north and south sides of the downtown. The plan was completed in December 2003.
Current Activities
Expanded station facilities opened in summer of 2013 including a second (western) waiting area in December 2013 at Northwest Highway and Lincoln Ave. The Village is exploring development options for the former Grove Residences site at River Road and Route 14.
Funding Amounts by Source
Source Amount
Local $14,500
Federal $58,000

Last Updated 06.15.2018

+ Niles Bus Oriented-Development Plan for Milwaukee Avenue Community Planning Corridor Planning Niles $100,000
  • RTA
  • Local
  • Federal
Completed

Project Details

Description

This plan explored transit oriented development opportunities along Milwaukee Avenue within the Village of Niles. The plan focused on strategies to improve transit facilities and services within the context of an overall effort to improve the function and aesthetics of the Milwaukee Avenue corridor. Improvements to transit facilities, new pedestrian amenities, streetscaping, traffic circulation, access to businesses, and potential redevelopment opportunities are major components addressed in the plan. Coordination with existing Pace service and the Niles Free Bus service was also explored.

Current Activities

This project was initiated in March of 2005 and is now complete. The Niles Village Board approved the Milwaukee Avenue Plan on January 24, 2006.

The Village of Niles continues to implement the BOD Plan recommendations to improve transit-oriented development and increase access to transit. Since 2008, the Village has installed paver crosswalks, decorative fencing, new traffic signal poles with arms, street furniture, sidewalks, pedestrian light poles, and street trees along Milwaukee Avenue. These improvements foster pedestrian and transit environments while spurring community and economic development.

Through the CMAP Local Technical Assistance (LTA) program, a Bicycle and Pedestrian Plan was completed, and adopted by the Village in March 2014. This plan identifies steps the Village can pursue to further develop the pedestrian and bicycle networks throughout the Village.

Pace continues to advance Transit Signal Priority (TSP) and Arterial Rapid Transit (ART) along the corridor. Through an RTA Innovation, Coordination, and Enhancement (ICE) project, Pace will test the integration of transit signal priority technology that will allow CTA and Pace buses to interact with multiple types of traffic signal systems located on the same arterial.

Pace received a CMAQ grant in 2014 to fund the following components of Milwaukee Avenue ART from Jefferson Park to Golf Mill: Phase 1 Engineering, stations, real time information, ART vehicles, and queue jump lanes (where appropriate), which are elements of the Pace TSP Planning for the Milwaukee Avenue Arterial Rapid Transit. Pace held public open houses for its Milwaukee Avenue ART service in 2015 to solicit feedback.

Milwaukee Avenue was the first Pace ART line - now titled Pace Pulse - to be implemented. Construction on shelters and other supporting infrastructure began in the summer of 2017 and the line fully launched in August if 2019. For more information visit the Pace website.

Funding Amounts by Source
Source Amount
RTA $10,000
Local $10,000
Federal $80,000

Last Updated 02.15.2024

+ Crete Downtown and Balmoral Park Station Area Plans Community Planning Transit-Oriented Development Plan Crete $113,850
  • RTA
  • Local
  • Federal
Completed

Project Details

Description
This project developed station area plans for the proposed Downtown Crete and Balmoral Park stations along the proposed Metra Southeast service commuter rail line.
Current Activities
As of the end of 2010, Metra has completed the Alternatives Analysis for the proposed Southeast Service Line. On March 7, 2011, then Governor Quinn signed into law House Bill 1644 which established the Southeast Commuter Rail Transit District which now has authority to acquire rights to use the freight rail line, buy land to build train stations and purchase rail cars.
Funding Amounts by Source
Source Amount
RTA $2,770
Local $20,000
Federal $91,080

Last Updated 06.30.2016

+ Mount Prospect Public Transportation System Plan Community Planning Transit-Oriented Development Plan - Transit Improvement Plan Mount Prospect $124,795
  • Local
  • Federal
Completed

Project Details

Description

This project addressed two elements of public transportation within the Village. The first project component reviewed the current level of local public transportation service and identified connectivity, usage, and service area improvements to destinations within the Village and the region. The second component developed a station area plan for a proposed station within the Village on the proposed Metra STAR Line.

Current Activities

The Final Plan was adopted by the Village Board in October 2009. This project was completed, and a final report published in June 2005.

After completing an Alternatives Analysis for the STAR Line in 2012, Metra chose not to continue to pursue the project due to a variety of factors.

In fall of 2015 the Village was awarded CMAQ funding for covered bicycle parking at the Mount Prospect Metra station through the RTA's Access to Transit Improvement Program.

Funding Amounts by Source
Source Amount
Local $24,959
Federal $99,836

Last Updated 11.08.2021

+ Libertyville TOD Plan Community Planning Transit-Oriented Development Plan Libertyville $100,000
  • RTA
  • Local
Completed

Project Details

Related Reports
Description

This project assisted the Village to plan for mixed use development in their core downtown area surrounding the Libertyville Metra station. The plan details the creation of a livable and walkable downtown area that remains architecturally significant and that will contribute to economic development and transit ridership.

Current Activities

The final report was adopted by the Village Board in November 2017. In July 2018 the Village Board approved $1,289,800 to modify the basic downtown Metra station to add restrooms and upgrade the design to what is considered more in keeping with Libertyville's historic character. Station improvements were completed in 2019.

In 2021 the 116-year old historic building at the southeast corner of School street and Milwaukee Avenue, former home to the La Villa Theatre in downtown Libertyville was renovated to include eight apartments on the upper two floors and the restoration of the building's original features.

In early 2024 the Village of Libertyville completed the installation of five new wayfinding signs throughout the downtown, including one directly outside the Metra station. This was a transportation recommendation in the Downtown TOD Plan.

The RTA will monitor the Village's progress to implement the Plan.

Funding Amounts by Source
Source Amount
RTA $80,000
Local $20,000

Last Updated 04.26.2024