Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the December 2023 Project Management Oversight report. 

?

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Sort descending Status
+ CTA All Station Accessibility Program - Austin Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,930,000 $0 $0 $13,930,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,564,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this project has been completed. The procurement process for the construction general contractor is ongoing with the bids due in June.

Last Updated 12.14.2023

+ Metra 95th Street Station CSU Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project will fund the rehabilitation of the 95th Street / Chicago State University Station on the Metra Electric Line in Chicago. The project elements may include the replacement and/or rehabilitation of station platforms, new lighting, rehabilitation of the headhouse, repair or replacement of roofs, installation of warming shelters, new platform amenities, and other related work. The project may also include wayfinding signage or other station identifiers. A new tunnel entrance will be added and parking facility upgrades will be completed. The station will be made fully accessible with the addition of elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $37,000,000 $0 $0 $37,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,000,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for this station reached 100%. There were delays on this project associated with the National Environmental Policy Act (NEPA) review process as well as coordination with the Chicago State University and additional scope added to the design. The project is in procurement and is aiming to go out for bids before the end of the year for a General Contractor.

Last Updated 12.14.2023

+ CTA Systemwide Tactical Traction Power Upgrades (Equipment/Cable/Enclosures) Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
Tactical Traction Power (Equipment/Cable/Enclosures) -The purpose of this project is to implement traction power system improvements that will enable the CTA to continue to meet existing traction power needs, increase traction power capacity to meet future demand, and address state of good repair by repairing or replacing worn or obsolete equipment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,864,902 $0 $0 $10,864,902

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,166,629
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor made significant headway during this reporting period and was able to reach substantial completion in July of this year. The contractor was able to finish the final walkthrough inspection and completed all punchlist items and is in contract closeout. This will be the final update on this project.

Last Updated 12.14.2023

+ CTA New Control & Training Center Support Facilities & Equipment System $0 $0 On Schedule

Project Details

Description
CTA complex (campus) to include a Control Center and Training Facility. The facility will be equipped with modern state of the art technology, heighten security criteria and redundant power sources. The Control Center portion of campus will include an auditorium, situation room, network operations center, and communication and training rooms. While, the new training facility portion of the campus will contain offices, classrooms, and conference rooms for CTA employee training. The training facility will contain both bus and railcar inspection pits including embedded rail track and testing track for rail operations. This project consolidates training functions across the agency within a centralized facility. Currently training is dispersed throughout the CTA system at various garages, yards, and offices due to space limitations. Thousands of CTA operating and maintenance employees use these facilities for employee training, instruction programs, and employee engagement. The primary rail and maintenance training is performed at a leased space and lacks all components necessary for proper training.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $317,270,670 $0 $0 $317,270,670

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$239,988,009
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 30% Schematic Design submittal was submitted on 01/24/2024. The 60% Detailed Design submittal was submitted on 03/4/24. CTA is working with the contractor for items related to that design submittal. The 100% advance work package for earthwork was submitted to DoR on 3/8/24 and continues to have the contractor working on it to address comments. The 90% design submittal is expected to be submitted to CTA in mid-May and the 100% design submittal is expected to be submitted in September 2024.

Last Updated 04.15.2024

+ Metra Traction Power System Augmentation - MED Electrical, Signal & Communications Rail $0 $0 On Schedule

Project Details

Description
Converting the tie stations into substations and installing a new substation willincrease capacity and reliability on the Metra Electric District. Construction wasperformed moving from north to south. Construction was completed at 31stStreet and 51st Street. Design for 95th Street and Riverdale are 100% complete.Bids were received and contract was awarded for both 95th St. and Riverdalesubstation construction. The contractor was issued an NTP in October 2018 andreached substantial completion this reporting period. This will be the final updateon this project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$32,264,285
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Converting the tie stations into substations and installing a new substation will increase capacity and reliability on the Metra Electric District. Construction was performed moving from north to south. Construction was completed at 31st Street and 51st Street. Design for 95th Street and Riverdale are 100% complete. Bids were received and contract was awarded for both 95th St. and Riverdale substation construction. The contractor was issued an NTP in October 2018 and reached substantial completion this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace 2020 - Bus Tracker Signs Stations & Passenger Facilities Bus $0 $0 On Schedule

Project Details

Description
Production of new electric signs and associated installation costs to provide real-time bus information to riders. In 2021, ten will be replacements for Pulse Milwaukee Line vertical markers, while an additional ten will be for new locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Activity for this project continued in this reporting period with real time bus information signage and electrical connections installed. Additional signs will be installed using other PAYGO funding for additional signs. This will be the final update on this project.

Last Updated 12.14.2023

+ Pace Purchase 7-passenger Vanpool Vehicles Rolling Stock Bus $0 $0 On Schedule

Project Details

Description
Vanpool Vehicles - Pace plans to purchase 164 replacement 17'-20' vans including associated equipment and services (Buy America audit and inspections) for vanpool services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$13,899,800
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vans will be utilized in the six county Pace service area. To date a total of 25 vans have been ordered, all have been received. Pace has executed a contract to install OEM passenger running boards on the first order of 25 vans. All the running boards have been installed and are in the active fleet. Pace continued to work on an action plan for ordering more vehicles based on projected needs under a separate contract. This will be the final update on this project.

Last Updated 12.14.2023

+ Metra Yard Improvements - Western Avenue Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project will provide design and construction funds for yard improvement projects at the yard facilities along the Milwaukee District lines. Upgrades under this project will include, but are not limited to, installation of electric heating elements for switches and the installation of steel grated boardwalks at the Western Avenue yard. Track work would include rail, ties, ballast and switches.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,500,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The diesel shop roof replacement and HVAC rehab has procurement activities in process for the construction contractor and construction management services.

Last Updated 12.14.2023

+ Metra 47th ST Yard Improvements - Heating Support Facilities & Equipment Rail $0 $0 On Schedule

Project Details

Description
This project will replace the heating system for two facility buildings at the 47th Street Yard. The project scope includes the procurement and installation of boilers, piping, fixtures, and other equipment for the Diesel and Car maintenance shops.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,500,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The work for the diesel shop construction, the 12KV distribution system, and sprinkler system reached substantial completion. Metra is in the procurement process for force account activities for Blue Island Yard canopy construction.

Last Updated 12.14.2023

+ Metra Union Pacific West Line Expansion Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project, a Public-Private Partnership between Metra and the Union Pacific Railroad, will constructtwo new segments of third mainline track on the Union Pacific West Line. One of the segments will bebetween the Vale Interlocking at milepost 10.0 in River Forest and the 25th Avenue Interlocking atmilepost 11.8 in Melrose Park. The other segment will be between the Kress Interlocking at milepost32.1 in West Chicago and the Peck Interlocking at milepost 38.4 in Geneva.Improvements are anticipated for all four of the interlockers that bookend the two segments. Additionally,a new interlocker may be constructed at milepost 35.4 between the Kress and Peck interlockers, whichwill increase operational flexibility. The interlocker improvements and additions will be constructed tomeet Positive Train Control requirements.Improvements along both segments will include, but not be limited to, trackwork, earthwork, sub-ballast,structures, signal infrastructure, interlocking upgrades, and all work necessary at highway gradecrossings. Bridge improvements will be needed over both the Des Plaines River and the Fox River toallow for the third mainline track. The project will also include platform relocations and improvements atboth the Maywood and Melrose Park stations, and platform, platform shelter, and parking improvementsat the Geneva station. Lastly, land acquisition may be required at various locations along the twosegments in areas where the right of way is not wide enough to accommodate the third main track withinthe track centers required by the Union Pacific.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$127,477,280
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction for the eastern section reached substantial completion in December 2020. Construction activities on the western section of this project are in progress. The project is approximately 68% complete, and the construction activities during this reporting period included relocating ComEd power lines and retaining walls preparation at various locations along the tracks between Kress Rd. and Peck Rd. The contractor also worked on the installation of steel structural girders on Fox River Bridge and on precast deck panels installation at the same locations. The contractor also performed some roadway and sewer removals work on Route 31st.

Last Updated 04.15.2024