Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the December 2023 Project Management Oversight report.
Agency | Project Title | Asset Category | Mode | 2024 Funding | 2024-2028 Funding | Status | |||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | CTA | Cottage Grove Station | Stations & Passenger Facilities | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
CTA has partnered with the Preservation of Affordable Housing (POAH) to revitalize the southeastcorner of 63rd Street and Cottage Grove Avenue with a new multi-use office/retail space, which willcontain a new Cottage Grove station house. Overall the general design concept relocates the CottageGrove station house within POAH's new Woodlawn Crossing mixed-use development at the southeastcorner of 63rd Street and Cottage Grove Avenue, while the existing platforms and other related railinfrastructure will remain in their current locations. The POAH design concept also adds a newpedestrian bridge and canopy to connect the existing platforms to POAH's Woodlawn Crossing building.The project will dramatically decrease the footprint of the CTA's Cottage Grove station over theintersection of 63rd Street and Cottage Grove, which will provide more natural light at street-level anddirectly respond to community feedback. The project features a number of station enhancements thatwill improve customer experience, including attractive new sculptural canopies, contemporary stationfinishes, a new elevator, and brighter lighting inside the station and on the platform. This funding willprovide for the demolition of the existing station house and canopy, new stationhouse including finisheswithin a new multi-use office/retail space conforming to CTA standards and criteria, platform extensions,new stairs from platform to grade, a new platform canopy, new friction buffer stops and associated trackwork, structural steel girder and stringer repairs, new lighting, new signage, and new train operator'sfacility.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
A contract has been awarded in January 2021 and CTA has issued a notice to proceed. The 60% design has been completed. Negotiations with POAH and City of Chicago Department of Planning and Development (CDPD) on final design for building where station entrance will be located are ongoing. POAH procured their own designer to support this project. Design is currently on hold until an agreement is reached with POAH and CDPD. CTA is exploring the option to continue design on the structural and track component of the project, as this work will be done by CTA internal forces.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | CREATE - P2 Rock Island District Connection | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will provide engineering for the 75th Street Corridor Improvement Project (CIP) that will relieve rail congestion by separating freight and passenger rail lines. Bottlenecks will be eliminated, and train idling will be reduced.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is currently in design. The 60% design has been completed. Design development activities continue to progress to 90% design. Procurement process for Rightof- Way acquisition is ongoing.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Crew Facilities | Support Facilities & Equipment | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project includes, but is not limited to, renovation of existing crew facilities or construction of new crew facilities at existing yard locations across the Metra system. Work may include design of and renovations to interior spaces such as office spaces, locker rooms, and training facilities.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra will build a new crew facility at Fox Lake Station on the Milwaukee North District Line. The design for this location is 90% complete and the 100% design is expected in July 2023. The designs for the Western Ave and Elgin facilities are 25% complete. Design activities are ongoing.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | CTA Open Fare Payment System - Equipment (Lease) - VENTRA | Support Facilities & Equipment | System | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
CTA Open Fare Payment System - Equipment (Lease) - VENTRA: funds will provide in part for the principal and interest of the agreement need for the Open Fare Standard equipment, hardware, and software costs.The contractor (Cubic) costs including, but are not limited to, expenses incurred to design, build, finance, operate, maintain, repair and replace the equipment, the software and the Open Standards Fare System, and provide the Services, in accordance with the specifications and performance at the service levels and perform any other obligations pursuant to this Agreement.The capital share of the annual Base component cost is $15 million which provides for necessary design, testing, purchase and installation of assets such as the following: Ventra Vending Machines, Mobile Data Validators (readers), Driver Terminal Displays, retail terminals, and B26all software applications, and back-end hardware.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is for the 2020, 2021, 2022, and 2023 annual equipment lease. The annual 2023 payments for the equipment lease began and will continue to make payments.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Elmhurst Station | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project will fund Metra’s portion of a larger station renovation/expansion in Elmhurst. It will leverage CMAQ funds obtained by the Village of Elmhurst to construct a larger station to accommodate the growing ridership.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Preliminary engineering and NEPA process were completed. The Village of Elmhurst is leading the design with their consultant. The designer achieved the 60% design milestone and continues to proceed to 90% design.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Metra | Evanston Bridge Repainting | Track & Structure | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project involves the sanding, abatement and repainting of the Dempster Street and Davis Streetbridges in Evanston on the Union Pacific North Line.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The contractor finished painting and applying the protective coating on the bridge in December. Final invoices remain and this will be the final update on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs - Forest Glen Building Demolition | Support Facilities & Equipment | Bus | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The purpose of this project is to eliminate building maintenance costs and security liabilities to CTA associated with the vacant buildings at the Forest Glen Bus Garage (located at 5353 W. Armstrong Avenue and 5601 N. Elston Avenue), as well as to provide additional capacity for bus parking at the Forest Glen Bus Garage. The project scope includes demolition of the buildings at 5353 W. Armstrong Avenue, 5601 N. Elston Avenue, and the existing salt shed (all currently owned by the CTA).
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Both of the vacant buildings have been demolished and the debris has been removed from the site. Fencing has been installed around the vacant lot. This project was significantly delayed due to the extensive environmental abatement process that was not initially anticipated. Final invoicing related to this process is outstanding. This is the final report on this project.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs - Kedzie Bus Garage Façade | Support Facilities & Equipment | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The project will retain a DoR firm to complete a comprehensive assessment of the structure’s exterior envelope to develop remediation and/or replacement plans for concerns regarding the exterior brick veneer delaminating from the backing block. The work will include detailing for caulking, flashing, or other treatments to prevent future similar issues from occurring due to water infiltration. Construction will repair portions of the brick that have fallen from the structure and other repairs to prevent recurrence of the failure.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The design for the project has been completed. Notice to Proceed for construction was issued in February 2023. The general contractor is working on submittals and mobilizing for field work.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | CTA | Facilities Critical Needs- Substation Roof Repairs - Phase II | Support Facilities & Equipment | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Program would address the most immediate critical needs at CTA facilities systemwide to enable theirsafe and reliable operation. The goal would be to have an annual appropriation in the CIP that wouldbe solely dedicated toward addressing this Program. Transit service safety and reliability is affected byout-of-date rail, bus, and maintenance facilities.The project will complete roof replacements at five CTA substations: Calvary, Lotus, Des Plaines,Ashland, and O’Hare. The project will also complete exterior façade repair at the O’Hare Substation,including wall panel and louver replacement, masonry wall and expansion joint repairs, painting, doors,and new surface mounted exterior light fixtures. Design will be completed in-house by CTAengineering staff.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Design has been completed by CTA’s in-house engineering staff. The Notice to Proceed for construction was issued in March 2023. The contractor is currently working through the submittal process and getting ready to mobilize for field work.
Last Updated 12.14.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||
+ | Pace | Farebox System Replacement | Support Facilities & Equipment | Bus | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Farebox System Replacement - Over 700 fareboxes on Pace fixed route buses will be replaced, with prior PAYGO funding of $7.5M from 2020 included.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
All of the fareboxes were installed on the garages and the project is considered substantially complete. Final invoices remain. This will be the final update on this project.
Last Updated 12.14.2023 |