Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode 2024 Funding 2024-2028 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ CTA Information Technology System $13,644,678 $48,406,421 $108,565,341 $60,158,920

Improvement of business processes and systems

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Bus Yard Intrusion Detection System Support Facilities & Equipment Bus $0 $0

Project Details

Description
Project calls for a comprehensive intrusion detection system and real-time video surveillance system at each of CTA’s bus garages/yards.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,370,890 $0 $0 $3,370,890

Last Updated 12.14.2023

+ Critical Power Substation Physical Security Hardening Support Facilities & Equipment System $0 $0

Project Details

Description
The goal is to create a comprehensive yet sustainable solution that ultimately prevents, detects, tracks, authorizes, and responds to all human activity around the substations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,989,654 $0 $0 $3,989,654

Last Updated 12.14.2023

+ Cyber Security Network Hardening Support Facilities & Equipment System $0 $0

Project Details

Description
The vision for CTA’s Cyber Security Network Hardening is to operationalize a secure and sustainable program of mitigation and risk reduction for CTA’s critical infrastructure and the control, command, and communications systems that are needed to provide transit services for commuters, tourists, and others depending on CTA every day.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,202,000 $0 $0 $3,202,000

Last Updated 12.14.2023

+ Implement Security Projects - HLS Program Support Facilities & Equipment System $6,000,000 $30,000,000

Project Details

Description
Implement Security Projects (HLS Program): This program provides competitive funding to public transportation agencies to protect critical high-risk surface transportation and the traveling public from acts of terrorism and to increase the resilience of transit infrastructure with eligibility based on daily ridership of transit systems serving key high-threat urban areas. It has identified critical infrastructure assets that are vital to the functionality and continuity of major high risk transit systems and whose incapacitation or destruction would have a debilitating effect on national security, public health, safety, or any combination thereof.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,000,000 $24,000,000 $30,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $647,520 $6,000,000 $24,000,000 $30,647,520

Last Updated 12.14.2023

+ Information Technology - Bus Router Replacements (MP070's) Support Facilities & Equipment Bus $0 $4,200,000

Project Details

Description
The purpose of this project is to perform a technological refresh of the bus routers to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2024 to have hardware replaced and start refresh project. To provide the CTA transit buses entirely new communications router and management platform by transitioning tocommercially available standard and supported hardware. Maintain annual support agreements with vendors solely dedicated to mobile communication providing a longevity and overall support cost savings.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $4,200,000 $4,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $4,200,000 $4,200,000

Last Updated 12.14.2023

+ Information Technology - Hastus Upgrade Support Facilities & Equipment System $1,000,000 $1,000,000

Project Details

Description
The purpose of this project is to upgrade to Hastus Version 2022 (or later) to ensure bus and rail scheduling utilizes the advanced scheduling tools Hastus provides to provide 24/7 transit service to CTA riders. This scheduling software utilizes customized rules based on CTA's union rules and also current transit industry trends. Target October 2022 to have hardware in place and start software upgrade project. The current Hastus contract with vendor GIRO requires CTA to begin the update project in Oct 2022 by providing a notice to proceed order in Q4 2022. Delays may result in change orders by the vendor. The CTA uses Hastus software to optimize the efficiency of bus and rail vehicle and crew schedules. Hastus software has been the agency’s exclusive transit scheduling tool since 1999 and CTA has been upgrading its Hastus version every 4-5 years to keep up with the industry trends and improved practices. Hastus is used for bus schedule changes four times annually, and for rail schedule changes, twice annually. In addition, Hastus is used to generate supplemental schedules associated with school trips and special events. Hastus provides critical interfaces for CTA’s operations, bidding - TOPSsystem, Customer Timetables, Clever works and on other budget functions for external stakeholders. Over the course of the 20 years with Hastus, CTA has made significant investments in customizations with each new version and intends to upgrade to the latest version in 2022 to take advantages of the better algorithms and industry trends available at that time.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,000,000 $0 $1,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $1,000,000 $0 $1,000,000

Last Updated 12.14.2023

+ Information Technology - IVN3/IVN4 Replacement Support Facilities & Equipment Bus $1,094,678 $1,094,678

Project Details

Description
The purpose of this project is to perform a technological refresh of the IVNs (Intelligent Vehicle Network) computer system on bus to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2023 to have hardware replaced and start refresh project. To provide a technology refresh cycle all IVN (Intelligence Vehicle Network)computers on board the CTA Bus Fleet currently active in the Bus transportation field operations with new IVN5 models.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,094,678 $0 $1,094,678
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,561,703 $1,094,678 $0 $3,656,381

Last Updated 12.14.2023

+ Information Technology - IVN3/IVN4 Replacement - CAD Upgrade Support Facilities & Equipment Bus $0 $0

Project Details

Description
The IVN replacement is a part of the overall project where CTA will also implement a Disruption Management System module, acquire Mobile CAD licenses, associated hardware, and provide for project development.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,972,956 $0 $0 $10,972,956

Last Updated 12.14.2023

+ Information Technology - MMIS Upgrade Support Facilities & Equipment System $2,500,000 $2,500,000

Project Details

Description
The MMIS application is used for managing repairs and issuing parts to the CTA Bus and Rail fleet. The last upgrade of this application started in 2016 with target completion of 2018. By 2022, this version of the MMIS product will no longer be supported by Trapeze, the vendor of the MMIS application. This request is for the next anticipated major upgrade for this mission critical software. Without the upgrade CTA will not be entitled to fixes and support of this application and can be in danger of operating this critical software with risk of bugs or failureswithout a means to resolve them. Theexpected length of time for this upgrade is 18 months. This project will be to upgrade the MMIS application, and its related hardware. This includes upgrading the MMIS application, Documoto Cloud application, all various interfaces between the applications and other enterprise applicationslike TOPS, ERP, Clever etc. The hardware infrastructure for the MMIS servers (Dev, Test, Training, PROD) will need to be upgraded. The 256 KIOSKS spread across the various CTA facilities will need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,500,000 $0 $2,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $2,500,000 $0 $2,500,000

Last Updated 12.14.2023

+ Information Technology - Technology Upgrades Rail Engineering & Maintenance Support Facilities & Equipment Rail $50,000 $200,000

Project Details

Description
Various Technology upgrades, such as: Replace RETS engineer computers with ones similar to Infrastructure Engineering at 567 be able to run CAD including using 3D modeling software (SolidWorks, CATIA, Polyworks). Needed for new car programs for which vendors increasingly are providing files in these formats. Improve Skokie server capacity for storage of larger files related to new car/overhaul programs, incident investigations. WiFi at various shops to allow class material to be accessible remotely from various classrooms and shops; live or remote demonstrations via classrooms will assist with troubleshooting and learning. New laptops are needed for instructors to properly address troubleshooting, event recorder and diagnostics. Tablets for repairers connected via WiFi to MMIS to allow easy access to maintenance manuals/bulletins/etc, quick parts ordering and work order updates.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $50,000 $150,000 $200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $50,000 $150,000 $200,000

Last Updated 12.14.2023

+ Information Technology - TOPS Upgrade II Support Facilities & Equipment System $0 $1,500,000

Project Details

Description
To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware. This includes upgrading the TOPS application, Viewpoint application, and the several interfaces with other enterprise applications like TOPS, ERP, Hastus, LMS etc. The hardware infrastructure for the TOPS servers (Dev, Test, Training, PROD) will need to be upgraded along with The Tap / SIT boxes that are spread across the various CTA facilities will also need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $1,500,000 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $1,500,000 $1,500,000

Last Updated 12.14.2023

+ Rail Station Video Management Support Facilities & Equipment Rail $0 $0

Project Details

Description
This project identifies needs for the complete upgrade and cyber security mitigation of CTA’s CCTV video management system across the rail system. Recent cyber security threat and vulnerability assessment (TVA) findings determined the existing video system has significant cyber vulnerabilities with the operating systems, is beyond useful life and is no longer supported. It is necessary to upgrade the video capture and storage infrastructure at over 200 rail facilities. The system upgrade will address cyber security vulnerabilities with unsupported and insecure Windows XP and Windows 7 operating systems.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,913,000 $0 $0 $4,913,000

Last Updated 12.16.2022

+ Transit Cyber Security Support Facilities & Equipment System $0 $0

Project Details

Description
This project calls for the implementation of a comprehensive Transit Cyber Security and Risk Mitigation Project within the Chicago Transit Authority (CTA). Project will include the upgrade, modernization, and hardening of CTA’s core firewall and network infrastructure, adding cyber security tools and services to identify, protect, detect, respond, and recover from and against cyber threats and vulnerabilities. The project will address findings, recommendations, and best practices from recent Threat and Vulnerability Assessments (TVA) and specifically target CTA systems potentially vulnerable from the global Solarwinds hack of 2020.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,912,000 $0 $0 $3,912,000

Last Updated 12.16.2022

+ Upgrade Computer Systems - (TOPS, Enterprise Systems) Support Facilities & Equipment System $0 $0

Project Details

Description
To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware. This includes upgrading the TOPS application, Viewpoint application, and the several interfaces with other enterprise applications like TOPS, ERP, Hastus, LMS etc. The hardware infrastructure for the TOPS servers (Dev, Test, Training, PROD) will need to be upgraded along with The Tap / SIT boxes that are spread across the various CTA facilities will also need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,700,000 $0 $0 $1,700,000

Last Updated 12.16.2022

+ Upgrade Office Computer Systems Support Facilities & Equipment System $3,000,000 $3,000,000

Project Details

Description
Funding will provide for the hardware needed for any business-requested upgrades to major IT applications, which may include but not be limited to MMIS, Filemaker Pro, Hyperion, and QuickTrack. This project will also provide for the continued upgrade/replacement of desktop computers, printers servers, software, and associated peripherals.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,000,000 $0 $3,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $3,000,000 $0 $3,000,000

Last Updated 12.14.2023

+ Upgrade Technology Systems Support Facilities & Equipment System $0 $4,911,743

Project Details

Description
Project scope will provide for the repair/replacement/upgrade of IT devices and/or systems, software or firmware release upgrades, emergency restoration, subject matter expertise (SME) support, and system monitoring.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $4,911,743 $4,911,743
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $4,911,743 $4,911,743

Last Updated 12.14.2023

+ CTA Perform Bus Maintenance Activities Bus $12,373,828 $49,495,312 $360,000,000 $310,504,688

Preform bus maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2021 - Bus Maintenance Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,365,222
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes. Bus maintenance activities were completed in this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ 2022 - Bus Maintenance Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $56,000,000 $0 $0 $56,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,000,000
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Bus maintenance activities were completed during this reporting period. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes. This will be the final update on this project.

Last Updated 06.10.2024

+ 2023 - Bus Maintenance Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Perform Bus Maintenance ActivitiesFunding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA's scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $36,000,000 $0 $0 $36,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Bus maintenance activities began during this reporting period. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 06.10.2024

+ 2024 - Bus Maintenance Rolling Stock Bus $12,373,828 $49,495,312

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $12,373,828 $37,121,484 $49,495,312
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $12,373,828 $37,121,484 $49,495,312

Last Updated 12.14.2023

+ Purchase and Install Driver Barrier Doors for Buses Rolling Stock Bus $0 $0

Project Details

Description
Retrofit approximately 740 buses removing the current polycarbonate barrier shield by installing a full top to bottom barrier door improving security while minimizing glare and anti-reflection effect. The specific fleet buses to be retrofitted will include the 1000 Series buses that are not be replaced with the current order, 4000 Series, and the 4300 Series. All new buses for the current contract and going forward will contain full door shields.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,309,417 $0 $0 $4,309,417

Last Updated 12.16.2022

+ CTA Railcar Overhauls Rail $11,899,057 $198,594,174 $491,053,968 $292,459,794

Quarter-life overhaul of 5000-series rail cars and life-extending overhauls of older 2600 and 3200-series rail cars

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $1,899,057 $41,619,579 ✔︎

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $33,591,710 $33,591,710
State $0 $0 $6,128,812 $6,128,812
RTA $0 $0 $0 $0
Service Board / Local $0 $1,899,057 $0 $1,899,057
Total $31,335,000 $1,899,057 $39,720,522 $72,954,579

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the beginning of May, 434 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. On average, CTA forces are overhauling 14 rail cars per month.

Last Updated 06.10.2024

+ Life extending Overhaul 2600/3200 Series Rolling Stock Rail $0 $136,974,595

Project Details

Description
Life extending overhaul on the 258 3200 Series and 300 2600 Series cars. Work on these cars will focus on major systems starting with the proplusion/powering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $104,665,377 $104,665,377
State $0 $0 $32,309,218 $32,309,218
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $136,974,595 $136,974,595

Last Updated 12.14.2023

+ Rail Car Overhaul - 2600-Series Rolling Stock Rail $0 $0 ✔︎

Project Details

Description
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation ofthe propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed inAugust 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. The first delivery ofmaterial is expected to arrive in May 2021 and the overhaul is expected to take place in the first half of 2022.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,314,552
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project consists of three phases. Phase A is for rail car motor replacement and was completed in October 2019. Phase B is for procurement and installation of the propulsion kits with the parts contract was executed, and kits were received. Work for this phase began in November 2019 and all 90 cars were completed in August 2020. Phase C is for the procurement of material contracts and installation. The contract was approved at the October 2020. All cars have completed the overhaul as of March 2022 and this project is considered complete. This will be the final update on this project.

Last Updated 12.14.2023

+ Replace video system 3200 and 5000-Series railcars Rolling Stock Rail $10,000,000 $20,000,000 ✔︎

Project Details

Description
Replace the existing video system on the 5000-series rail cars which is obsolete and no longer supported by the vendor. Replace existing video system on the 3200-series rail cars with a more reliable system. Useable components removed from the 3200s will be re-used to support the same system on the 2600-seriese rail cars.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $10,000,000 $10,000,000 $20,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,100,000 $10,000,000 $10,000,000 $25,100,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
CTA finalized the procurement process and the contract was awarded to Railhead Corporation. CTA is working with the contractor to begin specification development.

Last Updated 06.10.2024

+ CTA Elevated Track and Structure Systemwide Rail $9,595,891 $38,383,564 $380,000,000 $341,616,436

Preform elevated track and structure maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2020 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure work was completed, and final billing remains. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. This will be the final update for this project.

Last Updated 06.10.2024

+ 2023 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas:Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system.Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work.

Last Updated 06.10.2024

+ 2024 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $9,595,891 $38,383,564

Project Details

Description
Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $9,595,891 $28,787,673 $38,383,564
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $9,595,891 $28,787,673 $38,383,564

Last Updated 12.14.2023

+ CTA Administration - CTA System $8,392,961 $42,553,612 $55,000,000 $12,446,388

CTA's administrative projects

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Office Building Principle and Interest Contingencies and Administration System $6,186,525 $30,938,800

Project Details

Description
The scope of this project will provide for capitalized lease payments for the new administration building, and improvements and upgrades to existing facilities and associated elements throughout the system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,186,525 $24,752,275 $30,938,800
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,375,631 $6,186,525 $24,752,275 $43,314,431

Last Updated 12.14.2023

+ Support Services Contingencies and Administration System $2,206,436 $11,614,812

Project Details

Description
Funding will provide for Project Administration for the program of projects. Supports a variety of tasks necessary to administer the project that include, but are not limited to, ensuring that quarterly and milestone progress reports are submitted on time, ensuring that sufficient funds are available for approved projects, reviewing and approving invoices for payment, submitting approved invoices for reimbursement, identifying and cataloging agency assets, preparing financial statements, and ensuring that approved projects meet expenditure goals established for the participation of DBEs.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,206,436 $9,408,376 $11,614,812
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,537,681 $2,206,436 $9,408,376 $19,152,493

Last Updated 12.14.2023

+ Metra Uncategorized Projects - Metra Rail $7,305,000 $21,755,000 $0 $0

These are a miscellaneous set of Capital projects undertaken by Metra

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ COVID 19 - Modifications N/A Rail $0 $0

Project Details

Description
This project will fund modifications to gallery cars and EMU's to improve the interior air quality and sanitation within Metra's railcar fleet. Project activities will address public health concerns and to mitigate airborne viruses. Improvements to be made by this project may include, but is not limited to improving HVAC system components, filter upgrades, new UV lights, installation of hand sanitizer dispensers, signage, and other upgrades as needed.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,700,000 $0 $0 $6,700,000

Last Updated 12.16.2022

+ Cybersecurity Systems N/A Rail $955,000 $955,000 ✔︎

Project Details

Description
The goal of this project is to enhance Metra's cybersecurity and implement Metra’s cybersecuritystrategy. The objectives of this strategy are to implement vulnerability risk management, institute patchautomation, establish security operations sharing, and counter emerging threats through detection andresponse.This project will fund the purchase and installation of equipment and software for scanning,prioritization, and remediation of vulnerabilities. This also includes the purchase of hardware andsoftware for multiple networks and segments including IT systems, positive train control (PTC),SCADA infrastructure, and signal, telecom, and camera networks. The purchased equipment will covervulnerability scanning and prioritization, patch automation and remediation, Security Information andEvent Management (SIEM), and endpoint detection and response (EDR).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $955,000 $0 $955,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,700,000 $955,000 $0 $2,655,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Contracts for cybersecurity and vulnerability software were awarded and software installation completed for 7 contracts. Contracts were awarded for vulnerability assessment and shared cloud software, as well as reaching award for remote desktop management. Work continues on software implementation with these programs.

Last Updated 06.10.2024

+ Infrastructure Engineering BNS N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Infrastructure Engineering MED N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Infrastructure Engineering MET N/A Rail $800,000 $9,550,000

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $800,000 $8,750,000 $9,550,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,500,000 $800,000 $8,750,000 $12,050,000

Last Updated 12.14.2023

+ Infrastructure Engineering MWD N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Infrastructure Engineering RID N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ Infrastructure Engineering UPR N/A Rail $0 $0

Project Details

Description
This project funds various engineering responsibilities for capital projects. Metra’s Engineering Department as well as consultant engineers provide support to capital projects. The associated professional consultant services include design engineering and/or construction management in the areas of civil, structural, electrical, mechanical, signal, communications and environmental engineering.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $400,000 $0 $0 $400,000

Last Updated 12.16.2022

+ IT Components & Services N/A Rail $3,100,000 $5,800,000 ✔︎

Project Details

Description
Purchases various pieces of equipment that will be utilized at Metra Headquarters and outlying Metra facilities. Purchases may include, but are not limited to, replacement of obsolete information technology infrastructure, upgrade network switches, computers and printers, copiers, new and replacement servers, financial system software, and other software.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $2,700,000 $2,700,000
State $0 $3,100,000 $0 $3,100,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $750,000 $3,100,000 $2,700,000 $6,550,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,059,193
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This is a multiple year and multiple project type of capital project. Purchase orders have been awarded for various computer hardware and software. Hardware has been delivered and installed. Purchase Order Releases for computer hardware and software continue in process and deliveries will continue over the next several years.

Last Updated 06.10.2024

+ Metra TBD N/A Rail $0 $0

Project Details

Description
Projects TBD
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.16.2022

+ Revenue Accounting System N/A Rail $0 $0 ✔︎

Project Details

Description
Metra will implement a new and updated revenue accounting system and will alsoprovide funding for Metra to scope and release an RFP to integrate its currentfinancial system into an Enterprise Resource Planning (ERP) system that will becompliant with current best practices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$16,205,776
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Phase 4 of the Financial System Replacement, the Review Accounting module, went live as of October 2020 and final elements were executed in October of this year. This will be the final update on this project.

Last Updated 12.14.2023

+ Systemwide Cameras N/A Rail $2,450,000 $5,450,000

Project Details

Description
This project consists of adding up to 600 cameras per year throughout the Metra system. Installation on the Rock Island (RI) Line and the Southwest Service (SWS) Line, this project may support up to 1,300 cameras to be installed at all grade crossings and the 23 existing depots on the RI and SWS. Project expenses may including, but are not limited to, cameras and associated wiring and masts. This is a multi-year, phase-funded project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $3,000,000 $3,000,000
State $0 $2,450,000 $0 $2,450,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,400,000 $2,450,000 $3,000,000 $6,850,000

Last Updated 12.14.2023

+ CTA Life-Extending Bus Overhaul 430 (1000 series) Bus $6,737,430 $6,737,430 $9,372,083 $2,634,653

Overhauls to maintain sufficient fleet until the first order of replacement buses is received

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Life Extending Bus Overhaul - 430 Standard (1000 Series) Rolling Stock Bus $6,737,430 $6,737,430 ✔︎

Project Details

Description
Life Extending Overhaul - Up to 430 Standard (1000 Series) - This project will overhaul the engine and other major sub-components to provide the minimal amount of work necessary to keep the fleet going. By end of FY2020 630 buses will have met their estimated 12 year life expectancy. This extension would extend the bus life by four years. The life extension for the 40 foot 1000-1629 New Flyer Bus is essential to keeping a majority of the CTA fleet running in optimal condition. The current fleet of 40 foot NF buses is over 1000 buses. This project is essential to meet availability requirements for CTA. These buses were purchased in 2006-2007 and this life extension is essential to maintaining peak availability requirements at all 7 bus garages.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,737,430 $0 $6,737,430
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $25,100,429 $6,737,430 $0 $31,837,859

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,893,610
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The CTA Team drafted technical specs and the project scope is under review as of this reporting period. The team completed testing the pilot Haldex air dryers on two buses and the buses were put back in service. The Team continues to complete the project independent cost estimate and release the updated specifications to the Purchasing Department to start the bid review/release process.

Last Updated 06.10.2024

+ CTA Program Management System $6,606,375 $33,031,875 $66,064,000 $33,032,125

Provide for Program Management

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Program Management Contingencies and Administration System $6,606,375 $33,031,875

Project Details

Description
Professional services to manage implementation of the CTA's Capital Construction Program. Funds provide for a construction program management consultant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,606,375 $26,425,500 $33,031,875
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,212,750 $6,606,375 $26,425,500 $46,244,625

Last Updated 12.14.2023

+ CTA Systemwide Station Program System $5,000,000 $42,568,629 $118,178,681 $75,610,052

Station upgrades, modernization and accessibility improvements

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 43rd Street Station Green Line - Improvements Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Project will revise an exit only stair to reduce the street level footprint and make other aesthetic and state-of-good repair upgrades to coordinate with an upcoming new adjacent development.Creates a Green Line TOD project at 43rd Station in Southeast side of the City and provides for an enhanced environment to sustain the redevelopment occurring within the neighborhood.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

Last Updated 12.16.2022

+ Central Station (Purple Line) - Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace Central Station stairway, in Evanston, which include risers, treads, stair stringers, handrails, guardrails, canopies and enclosures.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,414,066 $0 $0 $2,414,066

Last Updated 12.16.2022

+ Clark and Lake Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace stairs at mezzanine level at Blue Line Clark and Lake Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $650,000 $0 $0 $650,000

Last Updated 12.16.2022

+ Cottage Grove Station Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
CTA has partnered with the Preservation of Affordable Housing (POAH) to revitalize the southeastcorner of 63rd Street and Cottage Grove Avenue with a new multi-use office/retail space, which willcontain a new Cottage Grove station house. Overall the general design concept relocates the CottageGrove station house within POAH's new Woodlawn Crossing mixed-use development at the southeastcorner of 63rd Street and Cottage Grove Avenue, while the existing platforms and other related railinfrastructure will remain in their current locations. The POAH design concept also adds a newpedestrian bridge and canopy to connect the existing platforms to POAH's Woodlawn Crossing building.The project will dramatically decrease the footprint of the CTA's Cottage Grove station over theintersection of 63rd Street and Cottage Grove, which will provide more natural light at street-level anddirectly respond to community feedback. The project features a number of station enhancements thatwill improve customer experience, including attractive new sculptural canopies, contemporary stationfinishes, a new elevator, and brighter lighting inside the station and on the platform. This funding willprovide for the demolition of the existing station house and canopy, new stationhouse including finisheswithin a new multi-use office/retail space conforming to CTA standards and criteria, platform extensions,new stairs from platform to grade, a new platform canopy, new friction buffer stops and associated trackwork, structural steel girder and stringer repairs, new lighting, new signage, and new train operator'sfacility.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$61,469,049
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A design contract has been awarded in January 2021 and CTA has issued a Notice to Proceed. The 60% design has been completed. Negotiations with POAH and City of Chicago Department of Planning and Development (CDPD) on final design for building where station entrance will be located are ongoing. POAH procured their own designer to support this project. Design is currently on hold until an agreement is reached with POAH and CDPD. CTA internal forces are working on the structural and track component of the project. Activities related to track and structure improvements as well as the relocation of the track crossover and signal house are ongoing. The fabrication of components for the structural and track work is in progress.

Last Updated 06.10.2024

+ Irving Park Station - Escalator and Canopy Replacement Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
Platform canopies and escalators will be replaced at Irving Park station on the O'Hare Blue Line. This project will address safety and state of good repair needs by replacing the worn and damaged platformcanopies at this station. Platform canopies that are in a state of disrepair allow water infiltration, which can cause damage to additional building materials and equipment and pose a safety risk to bothcustomers and employees. The scope of work for the station canopies includes the demolition and replacement of deteriorated canopy corrugated metal roofs, and repair and modification of the supportingsteel structure. Furthermore, escalators will be replaced at Irving Park Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,782,125
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction work has been completed. The escalators have been installed and the canopy work has reached substantial completion. Activities on final punch list items are ongoing. The project is in the close out phase.

Last Updated 12.14.2023

+ Loyola Station Red Line - Stair and Elevator Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Project will reconstruct or replace the existing cast-in-place concrete stairs that go from the main stationhouse to the elevated platform. Additionally, the traction elevator will be fully replaced with all new components including cab, platform, cables, motor, and controller.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $0 $0 $4,000,000

Last Updated 12.16.2022

+ Park & Ride Improvements Stations & Passenger Facilities System $0 $0

Project Details

Description
Capital maintenance work is necessary to improve or maintain parking lots at a SOGR. Renewal work for priority locations includes concrete structure restoration, surface paving, curb and sidewalk, drainage systems, and installation of parking machines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,500,000 $0 $0 $1,500,000

Last Updated 12.16.2022

+ Public Address Communication Modernization & Upgrade Stations & Passenger Facilities Rail $0 $14,000,000

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's Public Address System to upgrade the Authority's PA system from antiquated and obsolete technology to modern digital technology with disaster recovery/business continuity solutions, increased capacity, and compliance with NFPA 130. The PA system upgrade will include the upgrade/replacement of the master head-end system at the Control Center and Backup Control Center, and remote systems at each rail station, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $12,000,000 $12,000,000
State $0 $0 $2,000,000 $2,000,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $14,000,000 $14,000,000

Last Updated 12.14.2023

+ Quincy Loop Station Upgrade Stations & Passenger Facilities Rail $0 $0

Project Details

Description
The purpose of this project is make improvements to the historic Quincy Loop station, including the addition of two elevators to make this station accessible. In addition, this project will repair, repaint and refinish interior elements throughout the stationhouse, and will also paint the exterior of the stationhouse. Lighting will be upgraded and the canopy roof will be repaired where necessary.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $731,332 $0 $0 $731,332

Last Updated 12.16.2022

+ Rail Station Communications Infrastructure Modernization Stations & Passenger Facilities Rail $0 $10,000,000

Project Details

Description
Project will provide for the comprehensive rehabilitation, overhaul, and expansion of communications infrastructure at all CTA rail stations to support new and modern technologies for customer facing as well as life safety functions. The rail station communications infrastructure upgrade will include the upgrade/rehabilitaion/expansion of communications infrasturcture at each rail station, including but not limted to conduit, cabling, power sources, networking, HVAC, grounding, and other ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $10,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $10,000,000 $10,000,000

Last Updated 12.14.2023

+ Refresh and Renew Program Expansion Stations & Passenger Facilities Rail $3,000,000 $9,000,000

Project Details

Description
Provides a heavy investment in refreshing stations and facilities every five years to promote safety, security and longevity to all CTA facilities including, but not limited to Rail Stations and Platforms, Bus Garages and Rail Shops across the system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,000,000 $6,000,000 $9,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,000,000 $3,000,000 $6,000,000 $15,000,000

Last Updated 12.14.2023

+ Rehabilitate Blue Line Stations - Grand, Chicago and Division Stations Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehab of Grand, Chicago and Division Stations on the Blue Line O'hare branch.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,336,026 $0 $0 $2,336,026

Last Updated 12.14.2023

+ Rehabilitate Rail Stations - Systemwide Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehabilitate Rail Stations Systemwide - Rail Stations Program would provide an annual appropriation for much-needed rehabilitation and modernization work at existing CTA rail stations. In addition, Infrastructure’s Rail Stations Program funds could be re-appropriated to support other critical needs at rail stations as they arise and implementation of systemwide projects can be scaled dependent on funding and locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,925,000 $0 $0 $5,925,000

Last Updated 12.16.2022

+ Rehabilitate Rail Stations -95th Terminal Stations & Passenger Facilities Rail $0 $0

Project Details

Description
This new job order will support the final change order for the construction firm, including the removal of several underground storage tanks near the terminal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $625,384 $0 $0 $625,384

Last Updated 12.16.2022

+ Security Camera Modernization and Upgrade Stations & Passenger Facilities System $2,000,000 $9,568,629

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's CCTV Security Camera Video System to upgrade the Authority's camera and video management system and communications transport system from antiquated and obsolete technology to modern high-speed technology with disaster recovery/business continuity solutions, increased capacity, and inter-operability with City of Chicago OEMC. The video system upgrade will include the upgrade of the master CCTV head-end system at the Control Center and Headquarters, and life safety CCTV systems upgrades at each rail station, transit facility, and critical infrastructure, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $7,568,629 $9,568,629
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $2,000,000 $7,568,629 $11,568,629

Last Updated 12.14.2023

+ Station Security Enhancements Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Station Security Enhancements Systemwide (Safe and Secure) Initiative invests $15 million to provide for enhancements to be made to stations that include lighting, repairs, and other improvements. This multiple year effort is expected to touch over 100 stations throughout the system
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

Last Updated 12.16.2022

+ Systemwide Security Cameras Improvements (Safe & Secure) Stations & Passenger Facilities System $0 $0

Project Details

Description
Systemwide Security Cameras Improvements (Safe & Secure): Systemwide Security Cameras Safe and Secure investment of $18.0 M will add 1,000 new cameras and upgrade more than 3,800 older-model cameras throughout the system, including adding additional camera coverage to CTA-owned bus turnarounds and add monitors at all 146 CTA kiosks.$5M Modernize cameras$1M Install monitors at all kiosks$4M Install cameras at all CTA owned bus turnarounds$8M Maintain cameras in state of the art condition
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,707,200 $0 $0 $4,707,200

Last Updated 12.16.2022

+ Western Station Brown Line - Reconstruction Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
Rehabilitation required at this station that was not part of the Brown Line Reconstruction project and has older elevators that are part of the ASAP program on replacing existing elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $30,162,349 $0 $0 $30,162,349

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$30,026,352
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
CTA has reviewed the Design-Build Contractors pricing and technical proposals for the 60% design and 100% design for the Advance Work packages. The contractor will be expected to receive all permits necessary for the advance work by end of Q2-2024 and begin construction elements for the advance work when all permits are received.

Last Updated 06.10.2024

+ CTA Non-Revenue Vehicle Replacement Program System $3,225,000 $8,450,000 $70,740,422 $62,290,422

Replacement of vehicles needed for maintenance and operations support

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Equipment and Non-Revenue Vehicles Program Support Facilities & Equipment System $2,000,000 $6,000,000

Project Details

Description
CTA plans to invest funds annually to fund the phased replacement of aged equipment and vehicles used by CTA maintenance groups that include Bus, Rail, Power & Way, and Facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $4,000,000 $6,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,269,359 $2,000,000 $4,000,000 $7,269,359

Last Updated 12.14.2023

+ Non-Revenue Utility Vehicle Replacement Support Facilities & Equipment System $1,225,000 $2,450,000

Project Details

Description
Heavy-Duty Vehicles to support routine infrastructure maintenance, emergency repairs, and recovery operations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,225,000 $1,225,000 $2,450,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,450,000 $1,225,000 $1,225,000 $4,900,000

Last Updated 12.14.2023

+ Non-Revenue Vehicles - Diesel Locomotives Support Facilities & Equipment Rail $0 $0 ✔︎

Project Details

Description
Equipment and Non-Revenue Vehicles (Diesel Locomotives): Funding will provide for the replacement of CTA's diesel locomotive snow fighters. The self-propelled locomotives with special attachments to remove snow and ice during severe winter weather conditions are able to operate and clear system track, so that CTA can safely power up the system to restore/provide service. When traction power is down, this equipment will also be used to move rolling stock to secure locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,333,095 $0 $0 $3,333,095

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$22,731,013
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is in full production mode and the contractor delivered the first locomotive to CTA during this reporting period. On site testing continues and CTA continues to work with the vendor to address final configuration and modifications on the first vehicle before final acceptance. All changes will be pushed to locomotives two through four. Delivery of the second vehicle will take place after acceptance of vehicle #1 and will continue commissioning and delivering of the vehicles.

Last Updated 06.10.2024