Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2024-2028 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2024-2028 Regional Capital Program. Beginning with the 2024-2028 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2024-2028 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2028 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Agency Priority Project Mode 2024 Funding 2024-2028 Funding Sort ascending 10 Year Funding Needed 10 Year Unfunded Need
+ Pace Fixed Route Buses - Electric Bus $0 $78,009,128 $487,500,000 $409,490,872

Replacement of buses reaching useful life with electric buses

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Fixed Route Electric Buses Rolling Stock Bus $0 $78,009,128 ✔︎

Project Details

Description
Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $72,614,500 $72,614,500
State $0 $0 $5,394,628 $5,394,628
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $26,192,311 $0 $78,009,128 $104,201,439

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$28,810,673
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contract was executed, and the vendor provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. Deliveries of the buses were delayed and now expected to begin in Q1-2024. Pace executed a change order to purchase an additional two buses, bringing the total to 22 electric buses. Delivery of charging equipment began this quarter.

Last Updated 12.14.2023

+ Pace Construct New Support Facilities Bus $0 $66,827,687 $0 $0

Add needed capacity for bus maintenance and storage

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ River Division Electrification/Expansion Support Facilities & Equipment Bus $0 $66,827,687 ✔︎

Project Details

Description
This project is for architectural and engineering services that will provide pre-design services, geotechnical engineering, land surveys, traffic studies, existing facilities testing and evaluation and feasibility studies. It will also include design and construction administration, inspections and project oversight. Pace intends to expand and improve its existing River Division bus garage onto newly acquired property south of the existing garage. It will be designed to accommodate storage, servicing,maintenance, and associated program areas for an additional 75 buses, 26 paratransit and 6 nonrevenue vehicles in addition to other improvements to modernize the existing facility. Once the A/E design is completed, construction will follow.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $66,827,687 $66,827,687
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $66,827,687 $66,827,687

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,110,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace has entered into a contract for Architectural and Engineering services for pre-design and design services. The contractor completed the pre-design activities, and final pre-design report was submitted to Pace. The adjacent property acquisition has been completed. Pace is undertaking an electrification study that will inform the design changes needed to make this facility compatible with an electric bus fleet. The design activities are currently on hold pending the recommendations from this study. Pace will need to revise the initial 30% design to incorporate future electrification components before activities resume with the designer.

Last Updated 12.14.2023

+ New I-55 Garage - Plainfield Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Plainfield Garage - Completion of construction of a new 189,000 square foot bus storage and maintenance facility in Plainfield, housing up to 130 buses with 12 maintenance bays and administrative offices. Pace has executed an I.G.A. with Northern Builders and the village of Plainfield to construct the project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $425,000 $0 $0 $425,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$55,385,593
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction of the facility has been completed in September 2022. Pace received the occupancy permit and the facility operations as well as bus service started in October 2022. Pace added an additional phase to the project to include an electric bus charger and electric car chargers, as well as procurement of various furniture and equipment for the facility and offices. This last phase of the project has reached substantial completion in April 2023. This project is currently in close out.

Last Updated 12.14.2023

+ New Northwest Garage - Wheeling Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Northwest Wheeling Garage - Completion of the renovation of a 430,000 square feet bus storage and maintenance facility in Wheeling that will replace Pace's Northwest Division garage in Des Plaines. This CNG fueling facility will house approximately 133 buses with 17 maintenance bays and administrative offices.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$81,129,563
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace has entered into an Intergovernmental Agreement (IGA) with the Village of Wheeling. The improvements to Old Willow Road have been completed. The initial design has been finalized. The project is in the process of being re-scoped to add the electrification component. The design will be updated once Pace’s electrification study is completed to include the additional scope of work.

Last Updated 12.14.2023

+ South Campus Project - Markham Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
This project will provide for construction, project management oversight, project administration, and any associated equipment and services for the Pace South Campus project. New facilities will be built on a 22-acre site that is situated next door to Pace’s South Division (2107 W. 163rd Place) Garage in Markham, Illinois, which is already owned by Pace. The purpose of this project is to consolidate certain operational functions currently operating at each garage into one location.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,916,905
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction has been issued in January 2022. Construction activities are in progress. ComEd replaced the transformer and provided a supply to the Acceptance Facility. The delayed office building AC switchgear was delivered early and the contractor and Pace are working on a timeframe for setting and installing it.

Last Updated 12.14.2023

+ CTA Perform Bus Maintenance Activities Bus $12,373,828 $62,548,156 $360,000,000 $297,451,844

Preform bus maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2024 - Bus Maintenance Rolling Stock Bus $12,373,828 $62,548,156

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $12,373,828 $50,174,328 $62,548,156
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $12,373,828 $50,174,328 $62,548,156

Last Updated 12.14.2023

+ 2022 - Bus Maintenance Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $56,000,000 $0 $0 $56,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Bus maintenance activities began on this project during this reporting period. Major rehabilitation elements will include, but not limited to, body work, vehicle wiring, and brakes.

Last Updated 12.14.2023

+ 2021 - Bus Maintenance Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Funding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA’s scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$53,365,222
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major rehabilitation elements worked on included, but not limited to, body work, vehicle wiring, and brakes. Bus maintenance activities were completed in this reporting period. This will be the final update on this project.

Last Updated 12.14.2023

+ Purchase and Install Driver Barrier Doors for Buses Rolling Stock Bus $0 $0

Project Details

Description
Retrofit approximately 740 buses removing the current polycarbonate barrier shield by installing a full top to bottom barrier door improving security while minimizing glare and anti-reflection effect. The specific fleet buses to be retrofitted will include the 1000 Series buses that are not be replaced with the current order, 4000 Series, and the 4300 Series. All new buses for the current contract and going forward will contain full door shields.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,309,417 $0 $0 $4,309,417

Last Updated 12.16.2022

+ 2023 - Bus Maintenance Rolling Stock Bus $0 $0

Project Details

Description
Perform Bus Maintenance ActivitiesFunding for this project will provide for an ongoing capital maintenance program that consists of tasks necessary to keep buses in service through systematic inspection, detection, and prevention of incipient failure. CTA's scheduled maintenance program consists of planned preventive maintenance work to maintain bus performance. While major overhaul work is performed on a mid-life cycle basis, additional focused maintenance work is required at certain intervals, outside of the mid-life overhaul, during the life of buses. When certain maintenance tasks are needed to repair or replace, before it reaches its end of useful life and failing with an increased frequency, specific component campaign work is conducted.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $36,000,000 $0 $0 $36,000,000

Last Updated 12.16.2022

+ Pace Pulse Infrastructure Bus $59,141,334 $59,141,334 $82,561,000 $23,419,666

Enhance Pulse service

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Pulse Halsted Stations & Passenger Facilities Bus $39,573,834 $39,573,834

Project Details

Description
Architectural/Engineering Design and Construction of stations, vertical markers, and other elements of the Pulse Halsted Arterial Rapid Transit Line. The project corridor consists of approximately 9 miles of South Halsted Street, from the Pace Harvey Transportation Center to 95th Street, and includes the segment of 95th Street that provides a connection to the CTA Red Line 95th/Dan Ryan station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $32,137,334 $0 $32,137,334
State $0 $7,436,500 $0 $7,436,500
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $500,000 $39,573,834 $0 $40,073,834

Last Updated 12.14.2023

+ Pulse 95th Street Stations & Passenger Facilities Bus $19,567,500 $19,567,500

Project Details

Description
Design and construction of stations of the Pulse 95th Rapid Transit Line. The project corridor is approximately 12.4 miles in length and runs east-west between the CTA Red Line 95th/Dan Ryan Station in Chicago and Moraine Valley Community College in Palos Hills primarily routed along 95th Street, as well as several other roadways in Bridgeview, Chicago Ridge, Hickory Hills, and Palos Hills. The proposed line would include connections to other transit services including the CTA Red Line 95th/Dan Ryan Station and other CTA routes, other Pace bus routes, Metra Rock Island District Line Longwood Station, Metra Southwest Service, and Oak Lawn Patriot Station. As Pace’s third anticipated Pulse line, the 95th Street service will improve connectivity and increase transit service levels through higher frequencies, travel time savings, and station amenities. The Pulse 95th Street Line will connect to the Pulse Halsted Line, and eventually to the Pulse Harlem and Cicero Lines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $15,654,000 $0 $15,654,000
State $0 $3,913,500 $0 $3,913,500
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,464,000 $19,567,500 $0 $21,031,500

Last Updated 12.14.2023

+ CTA Rail Shops Improvements System $27,000,000 $58,800,000 $255,900,000 $197,100,000

Provide repair and replacement to worn components at rail maintenance shops

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Skokie Shops - Railcar Hoists Support Facilities & Equipment Rail $15,000,000 $15,000,000

Project Details

Description
Construct two new Rail car body hoists where the non-revenue unit is currently situated. This unit is to move to new facility in late 2023 or early 2024. Additional space with new hoists increases the capacity to overhaul series cars. Over the next five years, CTA will need to continue the overhaul of the 5000 Series, while also addressing life extending work on existing 2600 and 3200 Series expected to remain in fleet until replacement cars are available from a future order.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $15,000,000 $0 $15,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,000,000 $15,000,000 $0 $20,000,000

Last Updated 12.14.2023

+ Rail Car Facility Maintenance Support Facilities & Equipment Rail $4,000,000 $14,000,000

Project Details

Description
Replacement of various shop facility heavy equipment that is ending their useful lives. Equipment includes: carbody hoists at Harlem, spin jacks at Rosemont and Wheel truing machine at 54th (replace with 4-axle), office space at Harlem above classroom, security gates at Kimball/54th for when rollup doors are raised, 2 man gates at DesPlaines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $4,000,000 $10,000,000 $14,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,000 $4,000,000 $10,000,000 $15,000,000

Last Updated 12.14.2023

+ Midway Shop - Wheel Truing Machine Bldg. Extension and Access Track Support Facilities & Equipment Rail $0 $13,800,000

Project Details

Description
Provide railcar access from the north yard. Both cars of a railcar unit will be able to be trued without removing the unit from the shop to turn around. Allows for increased wheel truing activity, improves ride quality, and extends wheel life and track life.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $13,800,000 $13,800,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $13,800,000 $13,800,000

Last Updated 12.14.2023

+ Non-Revenue Rail Vehicle Equipment - Replacement Support Facilities & Equipment Rail $2,000,000 $10,000,000

Project Details

Description
Replace various rail-borne non-revenue vehicles that have exceeded their useful lives. Repairs and spare parts have become increasingly difficult which raises maintenance costs and increases duration of downtime of this critical equipment. Equipment includes: car movers, rail borne sewer vacuum, subway washer vehicle, rail profile grinder, rail cranes, 2 locomotive crane 22 ton, 2 tie cranes w/ close clearance tie replacement head, sky trim tree trimmer, tie inserters, MKVI tamper and stabilizer. Car movers needed to move rail cars in/out of shops, sewer vac needed for subway sewers, subway washer needed for subway cleanliness, other equipment needed for track maintenance.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $8,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,507,124 $2,000,000 $8,000,000 $15,507,124

Last Updated 12.14.2023

+ Skokie Shops - Wheel truing machine replacement Support Facilities & Equipment Rail $4,500,000 $4,500,000

Project Details

Description
Design and install new wheel truing machine.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $4,500,000 $0 $4,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,500,000 $4,500,000 $0 $9,000,000

Last Updated 12.14.2023

+ Skokie Shops Improvements Other Support Facilities & Equipment Rail $1,500,000 $1,500,000

Project Details

Description
Various shop improvements, including: Repurpose truck wash machine area to HVAC/truck wash, fill in truck transfer pit and install truck hi-line, add truck hi-line positions (and lighting, hose reels) in truck storage area, additional air operated 2-ton crane in Paint Booth, engineering lab, additional crane in truck shop on existing rails.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,500,000 $0 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,000,000 $1,500,000 $0 $2,500,000

Last Updated 12.14.2023

+ Skokie Clean Room - Bench Test Equipment Support Facilities & Equipment System $0 $0

Project Details

Description
Skokie Clean Room - Bench Test Equipment: The scope of work provides for modifications to the CTA Skokie Shop (Heavy Maintenance Facility) to accommodate the addition of clean rooms. All of the necessary architectural and MEP systems would be reworked and reactivated in the expanded / modified spaces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,400,000 $0 $0 $4,400,000

Last Updated 12.16.2022

+ Replace Non-Revenue 61st ST. Rail Shop Support Facilities & Equipment Rail $0 $0 ✔︎

Project Details

Description
Construct a new non-revenue vehicle maintenance facility for maintenance and repair of non-revenueequipment. Facility will also include covered storage tracks for track maintenance equipment. Thepurpose of the new Non-Revenue Rail Vehicle Maintenance Facility is to provide facilities formaintenance and repair of over 125 pieces of non-revenue equipment used for right-of-way maintenanceand other rail-mounted non-revenue vehicles.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$70,017,063
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 61st rail shop project continued to make headway. The building enclosure erected as well as roof installed. The contractor continues to make headway with procurement and installation of electrical, mechanical, plumbing, and carpentry inside the building. The contractor continues to perform parking lot and landscaping for the facility as well.

Last Updated 12.14.2023

+ Improve Facilities - Diesel Locomitve Storage Shed Support Facilities & Equipment Rail $0 $0

Project Details

Description
The purpose of this project is to support the expansion of CTA’s diesel-powered snow fighter locomotives via the construction of three sheds, one at each of the following locations: 98th, Midway, and Rosemont Yards to house the four new snow fighter locomotives. The sheds will fully enclose the locomotives. Work at each location provides for a pre-engineered insulated metal building structure, overhead coiling doors, plumbing, mechanical, electrical, fire alarms system, and tie-ins for sewer and electrical service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

Last Updated 12.16.2022

+ 63rd Shop - Non-Revenue Equipment and Service Support Facilities & Equipment Rail $0 $0

Project Details

Description
Purchase of equipment associated with 63rd Shop operations moving from Skokie to 63rd. Also, contracts for movement of existing equipment/material. This is necessary to allow use of the new shop as planned.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

Last Updated 12.16.2022

+ CTA Uncategorized Projects - CTA System $1,697,000 $57,596,000 $160,000,000 $102,404,000

These are a miscellaneous set of Capital projects undertaken by CTA

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Match for FTA Discretionary Awards N/A System $0 $40,000,000

Project Details

Description
Local source of funds are in reserved to match Annual Federal Discretionary Awards.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $40,000,000 $40,000,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $40,000,000 $40,000,000

Last Updated 12.14.2023

+ Train Tracker Digital Signage Upgrade N/A Rail $0 $15,899,000

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's Train Tracker Signage at rail stations and integrate with the Authority's Public Address PA system, with disaster recovery/business continuity solutions, increased reliability, and compliance with ADA.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $15,899,000 $15,899,000
Service Board / Local $0 $0 $0 $0
Total $0 $0 $15,899,000 $15,899,000

Last Updated 12.14.2023

+ Tactile Signage at CTA Bus Stops N/A Bus $1,697,000 $1,697,000

Project Details

Description
This project will install tactile signs at all bus stop poles where CTA public information signs are currently posted to provide information about the exact bus stop location to customers who are blind or have visual or cognitive disabilities
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,357,600 $0 $1,357,600
State $0 $339,400 $0 $339,400
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $1,697,000 $0 $1,697,000

Last Updated 12.14.2023

+ Transit OPACK Teams Sustainability N/A System $0 $0

Project Details

Description
Funding will provide essential layer in Chicago's transit-dedicated strategy to deter, detect, prevent and respond to terrorism in, on and in proximity to critical mass transit infrastructure within the City of Chicago and the surrounding region. This funding provides visible and covert deterrence patrols on train platforms in the downtown business district and in other high-risk/high-consequence assets within the CTA infrastructure and throughout the system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,503,744 $0 $0 $4,503,744

Last Updated 12.16.2022

+ Transit Terrorism Surge Operations (CPD) N/A System $0 $0

Project Details

Description
Funding provides for directed patrols on overtime (surge) activity by CPD SWAT Transit Operational Response with Canine and Heavy Weapons (TORCH) Teams. This project intends to supplement the current surge project which is only activated for selected holidays, significant dates and events and will provide a transit anti-terrorism protection measure on summer weekend rush hours that are still marked by an increase of passenger volume in the downtown business district, creating a heightened risk of terrorist exploitation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,281,825 $0 $0 $1,281,825

Last Updated 12.16.2022

+ 95th St. Corridor Transit Oriented Development Study N/A System $0 $0

Project Details

Description
CTA in partnership with City of Chicago Department of Planning and Development (DPD) will complete a comprehensive Equitable Transit Oriented Development (eTOD) planning study along a 2 mile stretch of the 95th Street Corridor, on the far south side of Chicago. This corridor includes five multimodal transit capital projects as follows: (1) RLE; (2) 95th Street Terminal Reconstruction; (3) Metra 95th Street/Chicago State University Station; and (4) & (5) Pace Pulse Halsted Rapid Transit Line and 95th Rapid Transit Line. The planning study will include the following: 1. existing conditions & market analysis including health & racial equity impact assessment (HREIA)2. land-use/zoning plan3. economic development plan4. transit supportive development guidelines and development concepts5. multimodal connectivity plan6. a coordinated implementation plan for an actionable roadmap
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $800,000 $0 $0 $800,000

Last Updated 12.16.2022

+ Cicero Grade Crossing N/A Rail $0 $0

Project Details

Description
The Cicero Grade Crossing Enhancements project will be located at the Cicero Pink Line, at the intersection of Cicero Ave and 21st Place . Changes to this grade crossing are a priority for CTA and the Illinois Department of Transportation (IDOT) due to several safety incidents at the grade crossing that have put CTA staff and passengers at potential risk. The enhancements to this crossing cover both civil and signal system upgrades. The roadway surfaces and continuous protective rubber boots at South Cicero Avenue have deteriorated over time. The proposed civil and trackwork scope of work calls for replacement of the roadways, sidewalks and continuous protective rubber boots. In addition, the signal system, roadway and pedestrian gate mechanisms at the grade crossing were installed over 16 years ago and since then; replaced three times. The signal system proposed scope of work replaces the gate cables and mechanisms that operate the gates, upgrades the batteries, cables and the signal lighting system to LED. CTA is applying for funds to support the design of this project, with the hope that the lessons learned from the enhancements to this grade crossing can be applied to similar grade crossings in CTA's system.The design phase of the project will explore options to enhance the safety of the grade crossing relative to the adjacent driveway and alley entrances. Both static concepts, such as flexible median indicators and signs, and dynamic considerations, such as LIDAR (light detection and ranging) or camera warnings and activated warning signs, will be reviewed for implementation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $803,100 $0 $0 $803,100

Last Updated 12.16.2022

+ CTA Information Technology System $15,151,168 $49,912,911 $108,565,341 $58,652,430

Improvement of business processes and systems

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Implement Security Projects - HLS Program Support Facilities & Equipment System $6,000,000 $30,000,000

Project Details

Description
Implement Security Projects (HLS Program): This program provides competitive funding to public transportation agencies to protect critical high-risk surface transportation and the traveling public from acts of terrorism and to increase the resilience of transit infrastructure with eligibility based on daily ridership of transit systems serving key high-threat urban areas. It has identified critical infrastructure assets that are vital to the functionality and continuity of major high risk transit systems and whose incapacitation or destruction would have a debilitating effect on national security, public health, safety, or any combination thereof.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,000,000 $24,000,000 $30,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $647,520 $6,000,000 $24,000,000 $30,647,520

Last Updated 12.14.2023

+ Upgrade Technology Systems Support Facilities & Equipment System $0 $4,911,743

Project Details

Description
Project scope will provide for the repair/replacement/upgrade of IT devices and/or systems, software or firmware release upgrades, emergency restoration, subject matter expertise (SME) support, and system monitoring.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $4,911,743 $4,911,743
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $4,911,743 $4,911,743

Last Updated 12.14.2023

+ Information Technology - Bus Router Replacements (MP070's) Support Facilities & Equipment Bus $0 $4,200,000

Project Details

Description
The purpose of this project is to perform a technological refresh of the bus routers to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2024 to have hardware replaced and start refresh project. To provide the CTA transit buses entirely new communications router and management platform by transitioning tocommercially available standard and supported hardware. Maintain annual support agreements with vendors solely dedicated to mobile communication providing a longevity and overall support cost savings.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $4,200,000 $4,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $4,200,000 $4,200,000

Last Updated 12.14.2023

+ Upgrade Office Computer Systems Support Facilities & Equipment System $3,000,000 $3,000,000

Project Details

Description
Funding will provide for the hardware needed for any business-requested upgrades to major IT applications, which may include but not be limited to MMIS, Filemaker Pro, Hyperion, and QuickTrack. This project will also provide for the continued upgrade/replacement of desktop computers, printers servers, software, and associated peripherals.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,000,000 $0 $3,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $3,000,000 $0 $3,000,000

Last Updated 12.14.2023

+ Information Technology - IVN3/IVN4 Replacement Support Facilities & Equipment Bus $2,601,168 $2,601,168

Project Details

Description
The purpose of this project is to perform a technological refresh of the IVNs (Intelligent Vehicle Network) computer system on bus to ensure bus communications network and data management is optimized. This refresh would be applied to the entire fleet of buses. Target 2023 to have hardware replaced and start refresh project. To provide a technology refresh cycle all IVN (Intelligence Vehicle Network)computers on board the CTA Bus Fleet currently active in the Bus transportation field operations with new IVN5 models.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,601,168 $0 $2,601,168
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,561,703 $2,601,168 $0 $5,162,871

Last Updated 12.14.2023

+ Information Technology - MMIS Upgrade Support Facilities & Equipment System $2,500,000 $2,500,000

Project Details

Description
The MMIS application is used for managing repairs and issuing parts to the CTA Bus and Rail fleet. The last upgrade of this application started in 2016 with target completion of 2018. By 2022, this version of the MMIS product will no longer be supported by Trapeze, the vendor of the MMIS application. This request is for the next anticipated major upgrade for this mission critical software. Without the upgrade CTA will not be entitled to fixes and support of this application and can be in danger of operating this critical software with risk of bugs or failureswithout a means to resolve them. Theexpected length of time for this upgrade is 18 months. This project will be to upgrade the MMIS application, and its related hardware. This includes upgrading the MMIS application, Documoto Cloud application, all various interfaces between the applications and other enterprise applicationslike TOPS, ERP, Clever etc. The hardware infrastructure for the MMIS servers (Dev, Test, Training, PROD) will need to be upgraded. The 256 KIOSKS spread across the various CTA facilities will need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,500,000 $0 $2,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $2,500,000 $0 $2,500,000

Last Updated 12.14.2023

+ Information Technology - TOPS Upgrade II Support Facilities & Equipment System $0 $1,500,000

Project Details

Description
To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware. This includes upgrading the TOPS application, Viewpoint application, and the several interfaces with other enterprise applications like TOPS, ERP, Hastus, LMS etc. The hardware infrastructure for the TOPS servers (Dev, Test, Training, PROD) will need to be upgraded along with The Tap / SIT boxes that are spread across the various CTA facilities will also need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $1,500,000 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $1,500,000 $1,500,000

Last Updated 12.14.2023

+ Information Technology - Hastus Upgrade Support Facilities & Equipment System $1,000,000 $1,000,000

Project Details

Description
The purpose of this project is to upgrade to Hastus Version 2022 (or later) to ensure bus and rail scheduling utilizes the advanced scheduling tools Hastus provides to provide 24/7 transit service to CTA riders. This scheduling software utilizes customized rules based on CTA's union rules and also current transit industry trends. Target October 2022 to have hardware in place and start software upgrade project. The current Hastus contract with vendor GIRO requires CTA to begin the update project in Oct 2022 by providing a notice to proceed order in Q4 2022. Delays may result in change orders by the vendor. The CTA uses Hastus software to optimize the efficiency of bus and rail vehicle and crew schedules. Hastus software has been the agency’s exclusive transit scheduling tool since 1999 and CTA has been upgrading its Hastus version every 4-5 years to keep up with the industry trends and improved practices. Hastus is used for bus schedule changes four times annually, and for rail schedule changes, twice annually. In addition, Hastus is used to generate supplemental schedules associated with school trips and special events. Hastus provides critical interfaces for CTA’s operations, bidding - TOPSsystem, Customer Timetables, Clever works and on other budget functions for external stakeholders. Over the course of the 20 years with Hastus, CTA has made significant investments in customizations with each new version and intends to upgrade to the latest version in 2022 to take advantages of the better algorithms and industry trends available at that time.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,000,000 $0 $1,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $1,000,000 $0 $1,000,000

Last Updated 12.14.2023

+ Information Technology - Technology Upgrades Rail Engineering & Maintenance Support Facilities & Equipment Rail $50,000 $200,000

Project Details

Description
Various Technology upgrades, such as: Replace RETS engineer computers with ones similar to Infrastructure Engineering at 567 be able to run CAD including using 3D modeling software (SolidWorks, CATIA, Polyworks). Needed for new car programs for which vendors increasingly are providing files in these formats. Improve Skokie server capacity for storage of larger files related to new car/overhaul programs, incident investigations. WiFi at various shops to allow class material to be accessible remotely from various classrooms and shops; live or remote demonstrations via classrooms will assist with troubleshooting and learning. New laptops are needed for instructors to properly address troubleshooting, event recorder and diagnostics. Tablets for repairers connected via WiFi to MMIS to allow easy access to maintenance manuals/bulletins/etc, quick parts ordering and work order updates.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $50,000 $150,000 $200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $50,000 $150,000 $200,000

Last Updated 12.14.2023

+ Bus Yard Intrusion Detection System Support Facilities & Equipment Bus $0 $0

Project Details

Description
Project calls for a comprehensive intrusion detection system and real-time video surveillance system at each of CTA’s bus garages/yards.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,370,890 $0 $0 $3,370,890

Last Updated 12.14.2023

+ Critical Power Substation Physical Security Hardening Support Facilities & Equipment System $0 $0

Project Details

Description
The goal is to create a comprehensive yet sustainable solution that ultimately prevents, detects, tracks, authorizes, and responds to all human activity around the substations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,989,654 $0 $0 $3,989,654

Last Updated 12.14.2023

+ Cyber Security Network Hardening Support Facilities & Equipment System $0 $0

Project Details

Description
The vision for CTA’s Cyber Security Network Hardening is to operationalize a secure and sustainable program of mitigation and risk reduction for CTA’s critical infrastructure and the control, command, and communications systems that are needed to provide transit services for commuters, tourists, and others depending on CTA every day.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,202,000 $0 $0 $3,202,000

Last Updated 12.14.2023

+ Information Technology - IVN3/IVN4 Replacement - CAD Upgrade Support Facilities & Equipment Rail $0 $0

Project Details

Description
The IVN replacement is a part of the overall project where CTA will also implement a Disruption Management System module, acquire Mobile CAD licenses, associated hardware, and provide for project development.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,972,956 $0 $0 $10,972,956

Last Updated 12.14.2023

+ Transit Cyber Security Support Facilities & Equipment System $0 $0

Project Details

Description
This project calls for the implementation of a comprehensive Transit Cyber Security and Risk Mitigation Project within the Chicago Transit Authority (CTA). Project will include the upgrade, modernization, and hardening of CTA’s core firewall and network infrastructure, adding cyber security tools and services to identify, protect, detect, respond, and recover from and against cyber threats and vulnerabilities. The project will address findings, recommendations, and best practices from recent Threat and Vulnerability Assessments (TVA) and specifically target CTA systems potentially vulnerable from the global Solarwinds hack of 2020.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,912,000 $0 $0 $3,912,000

Last Updated 12.16.2022

+ Rail Station Video Management Support Facilities & Equipment Rail $0 $0

Project Details

Description
This project identifies needs for the complete upgrade and cyber security mitigation of CTA’s CCTV video management system across the rail system. Recent cyber security threat and vulnerability assessment (TVA) findings determined the existing video system has significant cyber vulnerabilities with the operating systems, is beyond useful life and is no longer supported. It is necessary to upgrade the video capture and storage infrastructure at over 200 rail facilities. The system upgrade will address cyber security vulnerabilities with unsupported and insecure Windows XP and Windows 7 operating systems.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,913,000 $0 $0 $4,913,000

Last Updated 12.16.2022

+ Upgrade Computer Systems - (TOPS, Enterprise Systems) Support Facilities & Equipment System $0 $0

Project Details

Description
To upgrade TOPS to Version 2025 or higher. In order to be on the most recent software refresh and technological architecture the TOPS applications should be upgraded every 3-4 years to utilize the latest software algorithms and better means of doing business. The current contract with Trapeze calls for 2 different TOPS upgrade. This request is for the 2nd TOPS upgrade request. This project will be to upgrade the TOPS application, and its related hardware. This includes upgrading the TOPS application, Viewpoint application, and the several interfaces with other enterprise applications like TOPS, ERP, Hastus, LMS etc. The hardware infrastructure for the TOPS servers (Dev, Test, Training, PROD) will need to be upgraded along with The Tap / SIT boxes that are spread across the various CTA facilities will also need to be upgraded.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,700,000 $0 $0 $1,700,000

Last Updated 12.16.2022

+ CTA Systemwide Station Program System $5,000,000 $42,568,629 $118,178,681 $75,610,052

Station upgrades, modernization and accessibility improvements

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Public Address Communication Modernization & Upgrade Stations & Passenger Facilities Rail $0 $14,000,000

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's Public Address System to upgrade the Authority's PA system from antiquated and obsolete technology to modern digital technology with disaster recovery/business continuity solutions, increased capacity, and compliance with NFPA 130. The PA system upgrade will include the upgrade/replacement of the master head-end system at the Control Center and Backup Control Center, and remote systems at each rail station, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $12,000,000 $12,000,000
State $0 $0 $2,000,000 $2,000,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $14,000,000 $14,000,000

Last Updated 12.14.2023

+ Rail Station Communications Infrastructure Modernization Stations & Passenger Facilities Rail $0 $10,000,000

Project Details

Description
Project will provide for the comprehensive rehabilitation, overhaul, and expansion of communications infrastructure at all CTA rail stations to support new and modern technologies for customer facing as well as life safety functions. The rail station communications infrastructure upgrade will include the upgrade/rehabilitaion/expansion of communications infrasturcture at each rail station, including but not limted to conduit, cabling, power sources, networking, HVAC, grounding, and other ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $10,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $10,000,000 $10,000,000

Last Updated 12.14.2023

+ Security Camera Modernization and Upgrade Stations & Passenger Facilities System $2,000,000 $9,568,629

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's CCTV Security Camera Video System to upgrade the Authority's camera and video management system and communications transport system from antiquated and obsolete technology to modern high-speed technology with disaster recovery/business continuity solutions, increased capacity, and inter-operability with City of Chicago OEMC. The video system upgrade will include the upgrade of the master CCTV head-end system at the Control Center and Headquarters, and life safety CCTV systems upgrades at each rail station, transit facility, and critical infrastructure, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $7,568,629 $9,568,629
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,000,000 $2,000,000 $7,568,629 $11,568,629

Last Updated 12.14.2023

+ Refresh and Renew Program Expansion Stations & Passenger Facilities Rail $3,000,000 $9,000,000

Project Details

Description
Provides a heavy investment in refreshing stations and facilities every five years to promote safety, security and longevity to all CTA facilities including, but not limited to Rail Stations and Platforms, Bus Garages and Rail Shops across the system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $3,000,000 $6,000,000 $9,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,000,000 $3,000,000 $6,000,000 $15,000,000

Last Updated 12.14.2023

+ Western Station Brown Line - Reconstruction Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehabilitation required at this station that was not part of the Brown Line Reconstruction project and has older elevators that are part of the ASAP program on replacing existing elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $30,162,349 $0 $0 $30,162,349

Last Updated 12.16.2022

+ Rehabilitate Rail Stations - Systemwide Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehabilitate Rail Stations Systemwide - Rail Stations Program would provide an annual appropriation for much-needed rehabilitation and modernization work at existing CTA rail stations. In addition, Infrastructure’s Rail Stations Program funds could be re-appropriated to support other critical needs at rail stations as they arise and implementation of systemwide projects can be scaled dependent on funding and locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,925,000 $0 $0 $5,925,000

Last Updated 12.16.2022

+ Park & Ride Improvements Stations & Passenger Facilities System $0 $0

Project Details

Description
Capital maintenance work is necessary to improve or maintain parking lots at a SOGR. Renewal work for priority locations includes concrete structure restoration, surface paving, curb and sidewalk, drainage systems, and installation of parking machines.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,500,000 $0 $0 $1,500,000

Last Updated 12.16.2022

+ Station Security Enhancements Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Station Security Enhancements Systemwide (Safe and Secure) Initiative invests $15 million to provide for enhancements to be made to stations that include lighting, repairs, and other improvements. This multiple year effort is expected to touch over 100 stations throughout the system
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

Last Updated 12.16.2022

+ Central Station (Purple Line) - Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace Central Station stairway, in Evanston, which include risers, treads, stair stringers, handrails, guardrails, canopies and enclosures.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,414,066 $0 $0 $2,414,066

Last Updated 12.16.2022

+ Systemwide Security Cameras Improvements (Safe & Secure) Stations & Passenger Facilities System $0 $0

Project Details

Description
Systemwide Security Cameras Improvements (Safe & Secure): Systemwide Security Cameras Safe and Secure investment of $18.0 M will add 1,000 new cameras and upgrade more than 3,800 older-model cameras throughout the system, including adding additional camera coverage to CTA-owned bus turnarounds and add monitors at all 146 CTA kiosks.$5M Modernize cameras$1M Install monitors at all kiosks$4M Install cameras at all CTA owned bus turnarounds$8M Maintain cameras in state of the art condition
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,707,200 $0 $0 $4,707,200

Last Updated 12.16.2022

+ Quincy Loop Station Upgrade Stations & Passenger Facilities Rail $0 $0

Project Details

Description
The purpose of this project is make improvements to the historic Quincy Loop station, including the addition of two elevators to make this station accessible. In addition, this project will repair, repaint and refinish interior elements throughout the stationhouse, and will also paint the exterior of the stationhouse. Lighting will be upgraded and the canopy roof will be repaired where necessary.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $731,332 $0 $0 $731,332

Last Updated 12.16.2022

+ Clark and Lake Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace stairs at mezzanine level at Blue Line Clark and Lake Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $650,000 $0 $0 $650,000

Last Updated 12.16.2022

+ Rehabilitate Rail Stations -95th Terminal Stations & Passenger Facilities Rail $0 $0

Project Details

Description
This new job order will support the final change order for the construction firm, including the removal of several underground storage tanks near the terminal.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $625,384 $0 $0 $625,384

Last Updated 12.16.2022

+ Cottage Grove Station Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
CTA has partnered with the Preservation of Affordable Housing (POAH) to revitalize the southeastcorner of 63rd Street and Cottage Grove Avenue with a new multi-use office/retail space, which willcontain a new Cottage Grove station house. Overall the general design concept relocates the CottageGrove station house within POAH's new Woodlawn Crossing mixed-use development at the southeastcorner of 63rd Street and Cottage Grove Avenue, while the existing platforms and other related railinfrastructure will remain in their current locations. The POAH design concept also adds a newpedestrian bridge and canopy to connect the existing platforms to POAH's Woodlawn Crossing building.The project will dramatically decrease the footprint of the CTA's Cottage Grove station over theintersection of 63rd Street and Cottage Grove, which will provide more natural light at street-level anddirectly respond to community feedback. The project features a number of station enhancements thatwill improve customer experience, including attractive new sculptural canopies, contemporary stationfinishes, a new elevator, and brighter lighting inside the station and on the platform. This funding willprovide for the demolition of the existing station house and canopy, new stationhouse including finisheswithin a new multi-use office/retail space conforming to CTA standards and criteria, platform extensions,new stairs from platform to grade, a new platform canopy, new friction buffer stops and associated trackwork, structural steel girder and stringer repairs, new lighting, new signage, and new train operator'sfacility.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$76,447,966
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A contract has been awarded in January 2021 and CTA has issued a notice to proceed. The 60% design has been completed. Negotiations with POAH and City of Chicago Department of Planning and Development (CDPD) on final design for building where station entrance will be located are ongoing. POAH procured their own designer to support this project. Design is currently on hold until an agreement is reached with POAH and CDPD. CTA is exploring the option to continue design on the structural and track component of the project, as this work will be done by CTA internal forces.

Last Updated 12.14.2023

+ Rehabilitate Blue Line Stations - Grand, Chicago and Division Stations Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehab of Grand, Chicago and Division Stations on the Blue Line O'hare branch.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,336,026 $0 $0 $2,336,026

Last Updated 12.14.2023

+ Irving Park Station - Escalator and Canopy Replacement Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
Platform canopies and escalators will be replaced at Irving Park station on the O'Hare Blue Line. This project will address safety and state of good repair needs by replacing the worn and damaged platformcanopies at this station. Platform canopies that are in a state of disrepair allow water infiltration, which can cause damage to additional building materials and equipment and pose a safety risk to bothcustomers and employees. The scope of work for the station canopies includes the demolition and replacement of deteriorated canopy corrugated metal roofs, and repair and modification of the supportingsteel structure. Furthermore, escalators will be replaced at Irving Park Station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,782,125
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction work has been completed. The escalators have been installed and the canopy work has reached substantial completion. Activities on final punch list items are ongoing. The project is in the close out phase.

Last Updated 12.14.2023

+ Loyola Station Red Line - Stair and Elevator Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Project will reconstruct or replace the existing cast-in-place concrete stairs that go from the main stationhouse to the elevated platform. Additionally, the traction elevator will be fully replaced with all new components including cab, platform, cables, motor, and controller.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $0 $0 $4,000,000

Last Updated 12.16.2022

+ 43rd Street Station Green Line - Improvements Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Project will revise an exit only stair to reduce the street level footprint and make other aesthetic and state-of-good repair upgrades to coordinate with an upcoming new adjacent development.Creates a Green Line TOD project at 43rd Station in Southeast side of the City and provides for an enhanced environment to sustain the redevelopment occurring within the neighborhood.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

Last Updated 12.16.2022

+ CTA Administration - CTA System $8,392,961 $42,553,614 $55,000,000 $12,446,386

CTA's administrative projects

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ Office Building Principle and Interest Contingencies and Administration System $6,186,525 $30,938,800

Project Details

Description
The scope of this project will provide for capitalized lease payments for the new administration building, and improvements and upgrades to existing facilities and associated elements throughout the system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $6,186,525 $24,752,275 $30,938,800
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,375,631 $6,186,525 $24,752,275 $43,314,431

Last Updated 12.14.2023

+ Support Services Contingencies and Administration System $2,206,436 $11,614,814

Project Details

Description
Funding will provide for Project Administration for the program of projects. Supports a variety of tasks necessary to administer the project that include, but are not limited to, ensuring that quarterly and milestone progress reports are submitted on time, ensuring that sufficient funds are available for approved projects, reviewing and approving invoices for payment, submitting approved invoices for reimbursement, identifying and cataloging agency assets, preparing financial statements, and ensuring that approved projects meet expenditure goals established for the participation of DBEs.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,206,436 $9,408,378 $11,614,814
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,537,681 $2,206,436 $9,408,378 $19,152,495

Last Updated 12.14.2023

+ CTA Elevated Track and Structure Systemwide Rail $9,595,891 $38,383,564 $380,000,000 $341,616,436

Preform elevated track and structure maintenance activities to keep the fleet in a state of good repair.

Project Title Asset Category Mode 2024 Funding 2024-2028 Funding PMO
+ 2024 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $9,595,891 $38,383,564

Project Details

Description
Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $9,595,891 $28,787,673 $38,383,564
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $9,595,891 $28,787,673 $38,383,564

Last Updated 12.14.2023

+ 2022 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work. CTA purchasing is continuing to work on obtaining more materials for the project and continue to submit contract documentation for approval.

Last Updated 12.14.2023

+ 2020 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure work was completed, and final billing remains. This will be the final update on this project.

Last Updated 12.14.2023

+ 2021 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements for this project were completed in this reporting period. Major elements included, but were not limited to, ironworkers; track, signal and utilities work. Final invoices remain. This will be the final update on this project.

Last Updated 12.14.2023

+ 2023 - Elevated Track and Structure Maintenance Systemwide Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Elevated Track and Structure Systemwide - Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas:Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system.Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,000,000 $0 $0 $38,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements ongoing. Major elements include, but are not limited to, ironworkers; track, signal and utilities work.

Last Updated 12.14.2023