Planning Programs and Projects

This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus. 

Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.

i

This search filters based on details within the Planning Project. The search box below allows users to search by Planning Project name.

Year Project Title Program Project Type Project Partner Budget Funding Source(s) Status
+ Wood Dale Station Area Plan Community Planning Transit-Oriented Development Plan Wood Dale $91,700
  • Local
  • Federal
Completed

Project Details

Description
This study provided a station area plan that examined ways to integrate development plans and increase access to the station, taking into account the roadway re-alignment and rail grade separation feasibility studies that are currently underway. A market analysis was conducted to ascertain the commercial, residential, and retail markets in the station area.
Current Activities

The study was completed in June, 2006. The Village is currently exploring technical assistance opportunities to update their village-wide comprehensive plan. Once this is accomplished, rezoning the TOD area is the next step. Wood Dale Station, a mixed-use condo building, was built across from the station in 2006 and additional condos were built along Irving Park Road in the TOD area. 

Wood Dale was chosen as part of the 2011 RTA Community Planning Program of Projects for assistance with developer recruitment and solicitation of opportunities in the TOD study area. A panel of development experts met in July 2012 to discuss potential redevelopment opportunities on City-owned land across from the Metra station. A summary of this discussion can be found below under Related Reports.

Funding Amounts by Source
Source Amount
Local $18,340
Federal $73,360

Last Updated 02.15.2024

+ Cook-DuPage Corridor Study Community Planning Transit Improvement Plan Regional Transportation Authority (RTA) $1,618,000
  • RTA
  • Federal
Completed

Project Details

Description

The RTA led the Cook-DuPage Corridor study with the Illinois Department of Transportation (IDOT) to examine a broad range of transportation system improvements to address the mobility needs in the western suburbs of Chicago. The Cook-DuPage Corridor covers a large portion of the Chicago metropolitan area and is centrally located in the region. It extends approximately 30 miles from Cicero Avenue (IL50) in the city of Chicago/town of Cicero to the Kane/DuPage county line. Metra's Milwaukee District-West and Burlington Northern Santa-Fe commuter lines form the north and south boundaries respectively. The corridor spans all or portions of 51 municipalities in suburban Cook and DuPage counties and the Austin neighborhood of Chicago, an area that includes over 1 million residents and 750,000 jobs.

The Cook-DuPage Corridor is one of several corridors recommended for multi-modal analysis in the 2030 Regional Transportation Plan (CATS, October 2003). The Plan includes a number of major transit and highway proposals to address congestion and improve mobility in the western suburbs of Cook and DuPage counties. These are: High Occupancy Vehicle (HOV) lanes on the west end of the Eisenhower Expy. (I-290); Additional lanes on the East-West Tollway (I-88); Extension of the CTA Blue Line Congress branch to the western suburbs of DuPage County; Ogden Avenue transitway, from Navy Pier to North Riverside; Cermak Road bus rapid transit; DuPage County "J" bus rapid transit corridor, connecting Naperville, Oak Brook, O'Hare and Schaumburg; Inner Circumferential rail service (IHB/BRC) between O'Hare and Midway.

Mobility problems and potential solutions will be examined in three study phases spanning 2003-2010: 1) Travel Market Analysis, 2) Options Feasiblity, and 3) System Analysis. Locally led study components will be undertaken to formulate corridor planning standards and community development and land use plans/policies.

Current Activities

The Cook-DuPage Corridor Travel Market Analysis final report was published in December 2005. The second phase of study, Options Feasibility, was begun in early 2006 and completed in mid 2008. The RTA officially closed the Cook DuPage Corridor Study in April 2009.

All of the major capital projects in the region including Cook-DuPage Corridor proposed projects for system expansion now are being evaluated by the Chicago Metropolitan Agency for Planning for the Go To 2040 Plan. In addition, many of the projects in the recommended system are now moving to a more concrete stage of development through specialized studies undertaken by project sponsors. A Blue Line extension, High Occupancy Vehicle Lane and I-290 Bus Rapid Transit will undergo more detailed cost-effectiveness, ridership, environmental and engineering study through the Illinois Department of Transportation's (IDOT) Preliminary Engineering and Environmental Study (Phase 1). Additional information is available on the project website at www.eisenhowerexpressway.com. Similaly, Bus Rapid Transit is undergoing similar analysis in IDOT's ongoing Elgin-O'Hare West By-Pass Study.

Funding Amounts by Source
Source Amount
RTA $1,039,789
Federal $578,211

Last Updated 05.19.2021

+ La Grange Comprehensive Plan Update and BNSF Corridor Plan Community Planning Transit-Oriented Development Plan La Grange $125,000
  • Local
  • Federal
Completed

Project Details

Description
As part of the Village of La Grange's effort to revise their Comprehensive Plan, the Village performed a detailed analysis of transit-oriented development opportunities along the Burlington Northern Santa Fe (BNSF) corridor, which includes two Metra stations in the Village. This project was completed in May 2005.
Current Activities

The Village has seen major redevelopment and build-up of their downtown over the past 10-12 years with a mix of national chains and local businesses, along with condo and townhome development. 

In late 2010, Metra completed a project to upgrade and replace the platforms at the Stone Avenue Metra station and the Village renovated the interior and exterior of the historic Stone Avenue Station in partnership with Metra, BNSF Railway and the West Suburban Mass Transit District. This renovation enhances the station structure, outbound platform shelter and the grounds as an outdoor public gathering space. Additionally, the Village reconstructed the Brainard Avenue commuter parking lot with a permeable green paver integrated drainage system. 

In 2012, the RTA provided assistance to the Village through a collaborative effort with CMAP, ICC, BNSF, Metra and ATA to complete a pedestrian access improvement study at the Stone Avenue Station. The full Access Improvements report can be found below in the Related Studies section. 

In 2013 the RTA applied for CMAQ funding on behalf of the Village for these access improvements. CMAP approved the RTA's CMAQ submittal and the construction of these improvements will began in 2016. 

In August 2017 at 254 unit apartment building opened near the intersection of Ogden Avenue and LaGrange Road, a five minute walk to the LaGrange Road Metra station.]

The RTA is currently working with the Village of La Grange to update their Comprehensive and TOD Plans.

Funding Amounts by Source
Source Amount
Local $65,000
Federal $60,000

Last Updated 02.15.2024

+ Mundelein Station Area Plan Community Planning Transit-Oriented Development Plan Mundelein $78,568
  • Local
  • Federal
Completed

Project Details

Description

The plan emphasized an appropriate mix of land uses to revitalize a currently under utilized area adjacent to the commuter rail station. Revitalizing the area with the addition of appropriate access improvements will effectively connect the station area with the Village's downtown. This project was completed in January 2005.

Current Activities

Phase I of the nine-building Cardinal Square development, an 84 unit building located directly east of the Metra Station, was completed and occupied in 2008. Phase II, a 65 unit building, was completed in 2015, and construction of Phase III (180 units) was completed in 2024. 

In 2014 construction was completed on a new mixed-use building in the Village Center that includes a new village hall and new retail/office space. As part of this project, the Village also constructed a new public right-of-way, Plaza Circle, to provide better access to the Metra station and Village Hall. 

In an effort to improve pedestrian circulation in the station area, the Village designed and constructed a pedestrian overpass at the Metra station. The project was awarded CMAQ funding in October 2015 and was completed in October 2022. In fall of 2015, construction began on Fairhaven Crossing, a 40 unit affordable residential development for families and individuals with disabilities located on Hawley Street within convenient walking distance of the Metra station. Construction was completed in fall of 2016 and the building is currently occupied.

In 2024 construction was completed of 139 residential units on the site of a former recycling center at 101 E. Maple, purchased by the Village to encourage new retail or resident development of the site, which would be more fitting with the rest of the downtown area. The Village is constructed water/sewer, roadway, and pedestrian infrastructure improvements on Seymour Ave, Morris Ave, and Park St to support this development.

In 2024 construction was completed on a 165 unit development adjacent to the new Village Hall on Plaza Circle. To facilitate this project, which was a central recommendation of the 2005 TOD plan, the Village purchased ten acres of land previously occupied by an industrial building. The tenant of the building was relocated to another Village-owned property immediately south of the Metra commuter parking lot.

Also in 2024 construction commenced on the Mundelein Senior Apartments, a 46-unit, 4-story apartment building at the corner of Prospect Avenue and Hawley Street. This will be an independent living senior housing facility two blocks east of the Metra station.

Funding Amounts by Source
Source Amount
Local $18,568
Federal $60,000

Last Updated 10.11.2024

+ New Lenox Station Area Plan Community Planning Transit-Oriented Development Plan New Lenox $121,629
  • Local
  • Federal
Completed

Project Details

Description
This project created a concept plan for a mixed-use development located at the proposed new Metra commuter station on the SouthWest Line extension. The 240- acre site located at Laraway and Cedar Roads is currently vacant. The village's goal is to create a transit-supportive development.
Current Activities

This study (completed in 2005) addressed a proposed station at Laraway Road along the Southwest Service expansion. This expansion project, which included 11 miles of new track, was completed in January 2006, including the Laraway Road station (opened October 9, 2006). As part of the 2013 RTA Community Planning Program of Projects, the RTA worked with ULI to convene a panel of development experts to provide guidance and advice to the Village as they try to attract development to the 240-acre vacant area near the Laraway Road Metra Station. This discussion took place on October 25, 2013 and the Summary Report can be found in Related Studies

Funding Amounts by Source
Source Amount
Local $24,326
Federal $97,303

Last Updated 02.15.2024

+ Oak Park Intermodal Station Area Plan Community Planning Transit-Oriented Development Plan Oak Park $241,518
  • Local
  • Federal
Completed

Project Details

Description
This study examined ways to increase usage of the station, increase access to the station by alternative modes of transportation, enhance transfers between modes at the station, and integrate with development plans.
Current Activities

This project was completed in May 2005. In late November 2011, it was announced that the West Cook County Housing Collaborative received a nearly $3 million grant for its transit-oriented development strategy to update comprehensive plans and to create a sustainable transit-oriented development fund for the communities of Bellwood, Berwyn, Forest Park, Maywood and Oak Park. The communities are completed Comprehensive Plans that include recommendations for priority redevelopment parcels in each community's TOD area. 

Many development projects have been completed in the Village's TOD areas. Construction was completed on a 21-story mixed-use building at Lake Street and Forest Avenue, called Vantage Oak Park, in summer of 2016 with the first units occupied in July. The development includes 270 rental apartments, 25,000SF of ground-level retail and an integrated parking garage with 288 residential spaces and 300 public spaces. Another mixed-use residential, retail and parking project, called Oak Park Station, opened in late 2017 on the Village-owned Westgate site between Lake Street and North Boulevard just east of Harlem Avenue. Oak Park Station features a 20-story tower and five-story building that include 270 rental apartments, 28,000 square feet of retail and a five-story parking garage with 428 spaces for residential, retail, and public use. Additionally, a new transit-oriented development on the southeast corner of South Boulevard and Harlem Avenue was completed in 2019. The building, known as Eleven 33, is a mixed-use structure consisting of approximately 263 rental apartments, 10,000 square feet of retail and a 400 space parking garage. These new developments encourage increased ridership on all available transit services in the downtown area by adding a significant number of residential units within walking distance of CTA, Metra and Pace service. 

The Village is also planning an extension of the Marion Street streetscape improvements west on South Boulevard to Harlem Avenue to enhance pedestrian and bicycle mobility and access to surrounding transit service. These improvements would include wider sidewalks, shorter intersection crosswalk distances improved lighting and public seating. The project is partially funded through the Transportation, Community and System Preservation Program (TCSP).

Funding Amounts by Source
Source Amount
Local $181,518
Federal $60,000

Last Updated 02.14.2024

+ Pace Market Feasibility Study for North Central Shuttle Service Community Planning Transit Improvement Plan Pace Suburban Bus $75,417
  • RTA
  • Federal
Completed

Project Details

Description
This study examined the market feasibility of a comprehensive employer-based shuttle to serve employment centers located along Metra's North Central commuter line, which serves 11 Metra stations. A survey was developed and administered to employers in the corridor to determine demand for potential shuttle service.
Current Activities
This project was completed in March 2005. An initial set of routes began operations in November of 2006. These routes are the Townline Road Shuttle Bug (Route #580), Lincolnshire Shuttle Bug (Route #581) and the Discover/Baxter Shuttle Bug (Route #582). Pace is continuously exploring new opportunities to provide service to additional employers in the area.
Funding Amounts by Source
Source Amount
RTA $15,083
Federal $60,334

Last Updated 02.28.2013

+ Riverside Central Business District Station Area Plan Community Planning Transit-Oriented Development Plan Riverside $75,000
  • Local
  • Federal
Completed

Project Details

Description
This project addressed redevelopment potential in the Village's historic downtown. The study also addressed improvements to the railscape.
Current Activities
The study was completed in June, 2006 and the Village worked with CMAP in 2013 to update the study to reflect the current economy. The RTA supported their efforts and continues to provide assistance as the Village implements the updated downtown plan.

In 2018 the Village was awarded funding from the Illinois Transportation Enhancement Program to make needed pedestrian safety improvements for the area in and around the downtown Riverside Metra station.
Funding Amounts by Source
Source Amount
Local $15,000
Federal $60,000

Last Updated 10.30.2018

+ Winthrop Harbor Station Area Plan Community Planning Transit-Oriented Development Plan Winthrop Harbor $72,200
  • Local
  • Federal
Completed

Project Details

Description
This study recommends the redevelopment of the Village's business district using the Metra station as the anchor, while placing emphasis on the proximity of the harbor to downtown.
Current Activities

This project was completed in January 2005. Per a recommendation in the plan, the Village enhanced the streetscape along 7th Street in the TOD area in 2010 with funding assistance from ITEP. Currently, the Village is exploring ways to market their harbor and adjacent proximity to Lake Michigan as a destination and development opportunity for condos, hotel and retail. The Village was chosen as part of the 2012 RTA Community Planning Program for assistance revising their zoning code in the TOD area. This project began in April 2013 and new TOD area zoning regulations were adopted in May 2014. The adopted regulations can be found here.

Funding Amounts by Source
Source Amount
Local $14,440
Federal $57,760

Last Updated 02.14.2024

+ Franklin Park West Line Station Area Planning Study Community Planning Transit-Oriented Development Plan Franklin Park $75,000
  • Local
  • Federal
Completed

Project Details

Description
This project assessed the feasibility of transit-oriented development in the vicinity of the Metra Milwaukee West Line station in downtown Franklin Park. The goal of the project was to foster improvements to the area served by the Metra Station in order to attract and retain businesses, increase potential tax revenues to the Village, and increase transit ridership by enhancing pedestrian, bus and auto access to the station. This project was completed in February 2006.
Current Activities
RTA worked with the Village to convene a ULI Developer Discussion Panel to solicit guidance and advice on ways to attract TOD investment in the study area. A panel of development experts met with Village staff and elected officials in July 2012 to discuss potential redevelopment opportunities at the vacant LaSalle Bank site located on Minneapolis & 25th Avenues as well as vacant land next to The Crossings condominium development. A summary of this discussion can be found below in the Study Documents.

In 2014 the completed updates to their downtown zoning code, in partnership with the RTA, to better facilitate TOD development and the Village also pursued a Quiet Zone in the TOD area in partnership with the Village of River Grove. For more information please visit http://www.chicagotribune.com/suburbs/franklin-park/news/ct-fhj-train-quiet-tl-0219-20150212-story.html.
In 2020 the Village approved the sale of a downtown parcel at 9600 Franklin Avenue to make way for the construction of a 6-story, 110-unit, market rate luxury rental housing development with ground floor retail.
Funding Amounts by Source
Source Amount
Local $15,000
Federal $60,000

Last Updated 08.20.2020