Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the June 2024 Project Management Oversight report. 

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ Metra Elevator Replacement Stations & Passenger Facilities Rail $2,520,000 $48,020,000 Behind Schedule

Project Details

Description
This project will replace or renovate elevators at various stations across the Metra system.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $25,610,000 $25,610,000
State $0 $2,520,000 $19,890,000 $22,410,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $8,030,000 $2,520,000 $45,500,000 $56,050,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$9,400,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The elevator modernization for Millennium Station and Grand & Cicero are in the design development phase with 60% design under review and incorporating comments. Metra is also working on task order amendments. A systemwide elevator inspection and assessment is in progress as well as having proposals being evaluated.

Last Updated 09.25.2024

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $2,520,000 $2,520,000 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,520,000 $0 $2,520,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,314,071 $2,520,000 $0 $6,834,071

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. TSP data and operations monitoring continued on Dempster Avenue, testing and TST data analysis continued on Grand Ave. as well as Roosevelt Road. TSP deployment was completed at 147th Street and 95th Street where the vendor continues testing. Cicero Ave. has TSP installation ongoing. The contractor is working on permit acquisitions for Cermak, Rand Road, and 159th.

Last Updated 06.10.2024

+ Metra Car and Locomotive Cameras Rolling Stock Rail $2,000,000 $10,000,000 On Schedule

Project Details

Description
This project involves the purchase of a digital video recording (DVR) system. The system will replace the 12-year old, obsolete system currently running on Metra’s rolling stock. The new system will allow for video recording of railroad signal aspects and incidents and includes inward-facing cameras and outward-facing, dual-lens cameras.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $2,000,000 $8,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,000,000 $2,000,000 $8,000,000 $14,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$19,944,178
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The new technology allows recording at a faster frame rate and higher resolution, allowing slowing down the recording to less than real time rates without distortion, blurring, or loss of resolution. Currently, the DVR system is being installed by Metra Forces and passenger cameras are being installed by a vendor. All prototype installations were completed with them running with no issues. The full-scale installation began, and kits started delivery in October 2022. In total, 92 cars were completed, and the project is on-going and continuing installation activities.

Last Updated 06.10.2024

+ Pace Purchase 15-passenger Paratransit Vehicles Rolling Stock Bus $1,754,725 $31,047,716 On Schedule

Project Details

Description
Paratransit Vehicles - Pace plans to purchase 298 replacement vehicles (22'-25' cutaway) including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for paratransit services.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,754,725 $29,292,991 $31,047,716
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,388,134 $1,754,725 $29,292,991 $38,435,850

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$69,991,388
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
These buses will service DuPage, Kane, Lake, Will and Cook counties. Pace awarded a new contract in November 2020. The first order was for a quantity of 210 paratransit buses. The final vehicle of the base order was delivered in this reporting period in March 2024. Pace is working with the vendor for the second order of vehicles. These vehicles will combine additional paratransit vehicles & vehicles to be used for the community vehicle program. Final change order terms and pricing discussions are ongoing.

Last Updated 06.10.2024

+ Metra Morgan Interlocking Electrical, Signal & Communications Rail $1,500,000 $1,500,000 On Schedule

Project Details

Description
This project will provide design and construction funds for the replacement of the Morgan Street Interlocking on Metra’s Milwaukee C&M subdivision, the signal system infrastructure between Canal Street and A-2 interlocking. The Morgan St. Interlocker and crossings were originally installed in the early 1960’s. The signal system is also affected by the extreme weather conditions common to the Chicago region. It has become extremely difficult in recent years to get parts to make repairs to keep the system operational.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $1,500,000 $0 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,870,000 $1,500,000 $0 $5,370,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$11,320,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Morgan interlocker overall site design reached the 60% design milstone. The Morgan interlocker critical component design work reached 100% design during this reporting period. An IGA with CDOT was executed and CDOT is reviewing the civil drawings. Once approved and comments addressed, the civil drawings before the designer can proceed to the 90% design submittal.

Last Updated 06.10.2024

+ Metra Shelters Stations & Passenger Facilities Rail $1,025,000 $3,125,000 On Schedule

Project Details

Description
This project will fund the installation of shelters at stations across the system, which will provide on-demand heat. Specific locations are to be determined, based on existing conditions and demand. Shelters will be pre-fabricated structures and may include on-demand heating elements.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $1,025,000 $2,100,000 $3,125,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,500,000 $1,025,000 $2,100,000 $7,625,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$6,025,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Aluminum shelters continue to be installed throughout the system. Currently, shelter installation is on hold at Morton Grove, Western Ave., 67th St., 83rd St.. Western Avenue and Woodstock had the NEPA review completed and are at 90% design and continuing. Procurement packages for the next package of stations is in process.

Last Updated 09.25.2024

+ Metra Cybersecurity Systems N/A Rail $955,000 $955,000 On Schedule

Project Details

Description
The goal of this project is to enhance Metra's cybersecurity and implement Metra’s cybersecuritystrategy. The objectives of this strategy are to implement vulnerability risk management, institute patchautomation, establish security operations sharing, and counter emerging threats through detection andresponse.This project will fund the purchase and installation of equipment and software for scanning,prioritization, and remediation of vulnerabilities. This also includes the purchase of hardware andsoftware for multiple networks and segments including IT systems, positive train control (PTC),SCADA infrastructure, and signal, telecom, and camera networks. The purchased equipment will covervulnerability scanning and prioritization, patch automation and remediation, Security Information andEvent Management (SIEM), and endpoint detection and response (EDR).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $955,000 $0 $955,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,700,000 $955,000 $0 $2,655,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Contracts for cybersecurity and vulnerability software were awarded and software installation completed for 7 contracts. Contracts were awarded for vulnerability assessment and shared cloud software, as well as reaching award for remote desktop management. Work continues on software implementation with these programs.

Last Updated 09.25.2024

+ Pace Fixed Route Electric Buses Rolling Stock Bus $826,779 $78,835,907 On Schedule

Project Details

Description
Replace 52 diesel buses with electric buses including any associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections).
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $826,779 $72,614,500 $73,441,279
State $0 $0 $5,394,628 $5,394,628
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $26,192,311 $826,779 $78,009,128 $105,028,218

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$28,749,859
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contract was executed, and the vendor originally provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. However, the vendor was bought out by a new company, Phoenix Cars, LLC. Since the change, Phoenix has provided Pace with an updated delivery schedule and Pace will start to receive vehicles in early 2025.

Last Updated 06.10.2024

+ CTA Forest Park: Phase 1 - Trackwork Halsted to IMD Track & Structure Rail $737,767 $737,767 Ahead of Schedul

Project Details

Description
The CTA's Forest Park Blue Line Upgrades Project is the first of four phases of the Forest Park Branch. This project will provide for new trackwork from Halsted to Illinois Medical District (IMD), an accessible station at Racine, advanced utility work, and a new substation and traction power equipment upgrades at Hermitage. This work will enhance service quality via speed, reliability, and comfort, and improve operational efficiency on the Forest Park Branch of CTA's rapid transit Blue Line service.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $737,767 $0 $737,767
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $43,497,351 $737,767 $0 $44,235,118

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$147,765,006
On Budget
Ahead of Schedul

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The major trackwork and signal work has been completed, with almost three miles of track, between the LaSalle and Illinois Medical District stations rebuild. The contractor is in the final stages of providing submittals and warranties. This project was completed early and is in the close out phase. This will be the final update for this project.

Last Updated 06.10.2024

+ Metra Gresham Area Bridges Track & Structure Rail $500,000 $500,000 On Schedule

Project Details

Description
This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution. Both bridges are named after the Chicago street over which they cross, carry two main line tracks, and will be replaced with resilient concrete bridges.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $500,000 $0 $500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $17,000,000 $500,000 $0 $17,500,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$27,843,507
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Notice to Proceed for construction has been issued in September 2023. Currently the contractor is working on submittals and the permitting process. There are some delays associated with permitting process.

Last Updated 09.25.2024