Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site.  The latest report is the June 2024 Project Management Oversight report. 

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Agency Project Title Asset Category Mode 2024 Funding 2024-2028 Funding Status
+ ADA Technology Upgrades and Transfer Centers Systemwide Bus $0 $0 On Schedule

Project Details

Description
Regional ADA Paratransit Communication Technology and Transfer Locations - Projects include upgrades to the Trapeze software, TripCheck online booking and tracking, TripCheck Interactive Voice Response phone system, text/email notifications, and Ventra integration. In areas with frequent transfers, funding will be used to purchase land, build facilities, and provide amenities for riders. Pace has identified a location that is adjacent to the Northwest Transportation Center in Schaumburg that is planned to be the first of these transfer locations.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$20,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction at the Northwest Transportation Center ADA Transfer Facility is ongoing. The contractor completed the underground sewer and drainage structure installation. Site work is ongoing with sandblasting of the existing bus bays and painting. Construction of the transfer facility included building the walls, slab-on-grade floor, transfer facility utilities, new bus driveway pavement, light pole foundations, curb and gutter. Progress continues on the implementation of various technology enhancement projects. The first two phases of the Taxi Access Program have been completed and the vendor is currently working on the third phase. Activity continues on two phases of Trapeze technology enhancements to Pace’s Trapeze paratransit scheduling system.

Last Updated 09.25.2024

+ CTA All Station Accessibility Program & Canopies at Montrose Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This job order will provide for the design/construction of two new elevators at the Montrose Blue Line Station. Further this project will fund replacement of canopies at Montrose station.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,703,822 $0 $0 $7,703,822

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$24,918,224
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the design phase. The 60% design has been submitted to CTA. Design documents have been submitted to the State Historic Preservation Office (SHPO) for review and approval.

Last Updated 06.10.2024

+ CTA All Station Accessibility Program - California Station Stations & Passenger Facilities Rail $0 $0 Behind Schedule

Project Details

Description
This project with provide for the renovation and expansion of the California Station. It will include a new platform, new emergency exist stairs and two new elevators. The station will be 100% ADA accessible. In addition, state of good repair work will be performed as part of the station renovation.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,570,000 $0 $0 $9,570,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$36,060,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is currently in the design phase. The 100% design has been submitted and is currently under review by CTA. The State Historic Preservation Office (SHPO) approved the design. CTA is working on acquisition of three properties required for the construction of this project.

Last Updated 06.10.2024

+ CTA All Station Accessibility Program - Elevator Replacement Stations & Passenger Facilities Rail $0 $4,633,224 Behind Schedule

Project Details

Description
Funding will provide for second installment of funds to rehabilitate and/or replace elevators throughout the system. This funding along with the granted Rebuild Illinois funds provide in part for phase one of the program. For the Elevator Replacement Program, complete inspection of an elevator will need to be conducted to identify all deficiencies. Once inspections are complete, the CTA will need to determine whether rehabilitation or replacement is warranted. The individual scope of work for each elevator will vary depending on its condition and elevator type (machine room-less (MRL), geared, gearless, or hydraulic). Inspections of all components of the following systems are required to determine the full scope of work at each individual elevator and to determine whether rehabilitation or replacement is warranted:• Mechanical Systems• Electrical Systems• Material Finishes• Control Systems• Communication Systems• Security Systems• Structural Members• ADA Code Compliance • Municipality Building Code Compliance
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $4,633,224 $4,633,224
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $11,585,000 $0 $4,633,224 $16,218,224

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$34,855,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designer completed site assessments and elevator inspections. An assessment report to prioritize the elevator replacement and rehabilitation locations has been developed. The report also provides the scope of work needed for each individual elevator. CTA is working with the designer to put together construction packages based on the priority recommendations from the assessment report to start the Task Order procurement process.

Last Updated 06.10.2024

+ Metra Auburn Park New Station Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
The new station in the Auburn Park neighborhood of Chicago will feature a platform-length canopy and heated headhouse with two elevators. The station will include a center boarding platform with a staircase down to street level entrance tunnel, a landscaped plaza with benches, canopy, bicycle parking, and a vendor space Metra will lease. A parking lot will include 79 parking stalls, 5 ADA parking spaces, and a passenger drop-off lane. The new station will be fully ADA accessible.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,300,000 $0 $0 $6,300,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$33,178,767
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction activities are in progress. The contractor completed the vendor building walls and Union Ave curb, sidewalk, and ADA ramps. In addition to that, the ongoing work includes the retaining wall and bridge deck waterproofing as well as demolition to prepare for the elevated station and the underground electrical installation.

Last Updated 09.25.2024

+ Metra Bicycle Parking Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
Metra was awarded CMAQ grants for the purchase and installation of bicycle parking facilities at stations across the system. Specific locations are to be determined
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $161,500 $0 $0 $161,500

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$85,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra reached the 100% design submittal which is currently under review. Once the review is completed, any final comments will be addressed and Metra will proceed to develop the Invitation for Bid documents.

Last Updated 06.10.2024

+ CTA Blue Line O'Hare Branch Traction Power Improvements Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,405,159 $0 $0 $12,405,159

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$207,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.

Last Updated 12.14.2023

+ CTA Blue Line Traction Power - Barry, Damen and Canal Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
Construct a tie house (at the intersection of Milwaukee/Canal/Lake Street) and two new substations (at Barry/Kimball intersection and Damen/Milwaukee intersection) to support traction power needs on the Blue Line. These assets will support increasing ridership demands as well as the power needed to support 5000 and 7000 series rail cars. The location of the tie house and substations were determined by the Blue Line Load Flow study, which identified areas that were likely to experience traction power issues.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,200,191 $0 $0 $2,200,191

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$123,967,362
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction work is ongoing at Canal, Damen, Haymarket and the Canal Tie-House. AC switchgear was installed at the Haymarket substation, however there is work to investigate and repair a line crack that occurred. Damen electrical work and Barry curtainwall work is ongoing.

Last Updated 09.25.2024

+ Metra Bridge 86 - 78th St Entrance Track & Structure Rail $0 $33,160,000 On Schedule

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $33,160,000 $33,160,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $0 $33,160,000 $48,140,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,980,365
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the bridge and entrance continued to 90% completion. The Task Order amendment for 90% design is in progress.

Last Updated 09.25.2024

+ Metra Bridge A-32 Reconstruction Track & Structure Rail $0 $0 On Schedule

Project Details

Description
The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.
Funding Amounts by Source
*Previous funding shows all funding since 2021, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2021 that is not shown in table.
Source Previous Funding* 2024 Funding 2025-2028 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$38,041,561
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities during this reporting period. The bridge steel girders were delivered and installed, and waterproofing of the bridge deck were completed. The project is 74% complete.

Last Updated 06.10.2024