Planning Programs and Projects
This page allows users to search for projects from the RTA’s Planning Programs. Users can search for projects by name or keyword from the Search bar or the Filter pulldown menus.
Table results display summary information about each project. To view more details for a project, select the + icon to expand the view for additional information.
Year | Project Title | Program | Project Type | Project Partner | Budget | Funding Source(s) | Status | |||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
+ | Mount Prospect Rand Road Corridor Plan | Community Planning | Transit Improvement Plan | Mount Prospect | $125,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project conducted an update of the Rand Road Corridor Plan, originally completed in 1998. The new plan includes an emphasis on transportation, transit access and land use along the corridor. Recommendations focus on improvements to bicycle/pedestrian infrastructure, Pace bus access and suggested intersection designs to create a more multi-modal environment.
Current Activities
The final plan was accepted by the Village Board in February 2017. The RTA will continue to provide implementation support to the Village as needed.
Funding Amounts by Source
Last Updated 03.31.2017 |
||||||||||||||
+ | Naperville/Lisle Partners Ride DuPage to Work '15 | Section 5310 / JARC / NF | Operating | Naperville | $744,052 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
This project, as part of the Ride DuPage program provides seniors and individuals with disabilities increased employment opportunities by providing them with transportation to jobs in and outside of their own town and at times that may extend beyond traditional work hours. Seven local governments sponsor the service: City of Naperville, Naperville Township, Lisle Township, Wheatland Township, Village of Glen Ellyn, City of Wheaton, and Milton Township.
Current Activities
The service provided 2,445 trips in May 2018. This project is complete.
Funding Amounts by Source
Last Updated 06.13.2019 |
||||||||||||||
+ | Pace Local Transit Planning For Hoffman Estates, Waukegan and Woodridge | Community Planning | Transit Improvement Plan | Pace Suburban Bus | $150,000 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project funded technical assistance to Pace to enable them to conduct the following studies: The Green Bay Road Flexible Transportation Study in Lake County; the Barrington Road / I-90 Hoffman Estates Circulator and Land Use Study; and the Woodridge Park and Ride Transportation Plan. Current Activities
The Hoffman Estates study recommended transit service alternatives, revised land uses and bicycle / pedestrian improvements. In 2018 Pace launched I-90 Express Bus services to the new Barrington Road Station as well as the new Route 612, Barrington Road Cirulator in Hoffman Estates. Funding Amounts by Source
Last Updated 03.03.2021 |
||||||||||||||
+ | Pace North Avenue Corridor Study | Community Planning | Corridor Planning | Pace Suburban Bus | $200,000 |
|
Completed | |||||||
Project DetailsDescription
This project funded technical assistance to Pace to conduct a corridor study of North Avenue between Harlem Avenue and York Road. This study aligned with the goals and objectives of the Pace Vision 20/20 plan as well as addressed regional concerns expressed in the CMAP GOTO 2040 plan. Recommendations include providing improved access to current Pace and CTA bus services, providing improved connections for people walking and biking, transportation and land-used tactics to improve the corridor for future Pace Pulse service, and some redevelopment concepts for two sites with redevelopment opportunity along the corridor. Current Activities
This study was completed in June 2017 and Pace staff has begun to determine which of the recommendations to consider first for implementation. In 2021 the Village of Melrose Park was awarded $566,000 from Cook County as part of the 2021 Invest in Cook grant program awards. The funds will be used to make roadway improvements at the intersection of IL-64 (North Avenue) and George Street. Correcting the offset intersection will improve safety for motorists and other users while also improving traffic circulation along commercial properties. Construction will involve installation of new traffic signals, relocating a shopping center entrance drive, as well as modifying sidewalks, ADA ramps, and a bike path. The 2017 Pace North Avenue Corridor Plan highlighted this intersection as needing modifications to better serve Pace riders, which this project will accomplish. The City of Northlake was also awarded funding for right-of-way for roadway improvements to Railroad Avenue, a major trucking corridor within the City. This project will bring Railroad Avenue up to modern design standards for safety and efficiency and improve the movement of trucks in the area. Improvements include adding a southbound right turn lane to improve capacity at the intersection of IL 64 (North Avenue) and Railroad Avenue, upgrading pedestrian accommodations to current ADA standards, and providing new signalized pedestrian crossings. The new signalized pedestrian crossing will improve access to the Pace 309 route. Funding Amounts by Source
Last Updated 01.10.2022 |
||||||||||||||
+ | Palatine TOD Plan | Community Planning | Transit-Oriented Development Plan | Palatine | $99,993 |
|
Completed | |||||||
Project DetailsRelated Reports
Description
This project assisted the Village with creating a TOD Plan for the downtown area that will serves as an update to the Village 2004 Downtown Land Use Guide. This plan built upon already completed development and redevelopment in the downtown area in the 1990's and early 2000's. This Plan is a refined vision for remaining pocket areas that have potential for redevelopment and focuses on fringe areas where high-density, TOD development transitions back into more traditional, low-density land uses. Current Activities
The final TOD Plan was adopted by the Village Board on November 14, 2016 and the Village is assessing initial implementation steps it could take. In September 2018, 'Stone Garden' Single Family Homes completed construction near the Palatine Metra Station. In 2022 the Village was awarded right-of-way funding for Palatine Road improvements from Smith Street through Quentin Road identified in the plan. These improvements will include the reconstruction of Palatine Road, bike lane improvements, and associated sidewalk and pedestrian enhancements. These improvements will not only further solidify this section of Palatine Road as a western gateway into Downtown, but also greatly enhance the pedestrian and bicycle connectivity to Downtown Palatine. Funding Amounts by Source
Last Updated 05.11.2023 |
||||||||||||||
+ | RGAs Comprehensive Program '15 | Section 5310 / JARC / NF | Operating | Ray Graham Association | $1,219,384 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
The project transports individuals with disabilities from their homes to Community Learning Centers and to a variety of other activities including grocery shopping, medical appointments, volunteer opportunities and recreational activities.
Current Activities
The service provided 22,459 trips in June 2018. This project is complete.
Funding Amounts by Source
Last Updated 06.13.2019 |
||||||||||||||
+ | Ride in Kane Phase 13 & 14 | Section 5310 / JARC / NF | Operating | Association for Individual Development (AID) | $3,098,924 |
|
Completed | |||||||
Project DetailsRelated Reports
Not Available Description
This project coordinates paratransit services in Kane County into a centralized system that optimizes transportation resources for older adults and persons with disabilities. The sponsors of this project include multiple private non-profit organizations and local units of government. Current Activities
The operating service provided 5,656 trips in August 2019. This project is complete. Funding Amounts by Source
Last Updated 11.19.2023 |
||||||||||||||
+ | Ride Lake County Central Dial-a-Ride '15 | Section 5310 / JARC / NF | Operating | Lake County | $275,204 |
|
In Progress | |||||||
Project DetailsRelated Reports
Not Available Description
Lake County combined three separate dial-a-ride services, operating in the Central Lake/Shields township area, into one service. The project initially calls for Shields Township to operate separately while the Fremont and Central Lake partners (Fremont Township, Libertyville Township, Villages of Libertyville and Mundelein) are combined. The service provides expanded dial-a-ride transportation in Lake County to seniors and individuals with disabilities residing in Central Lake County. Five municipalities and Lake County sponsor the project. Current Activities
The operating service provided 252 trips in April 2022. Funding Amounts by Source
Last Updated 09.16.2022 |
||||||||||||||
+ | Ride Lake County West '15 | Section 5310 / JARC / NF | Operating | Lake County | $201,970 |
|
In Progress | |||||||
Project DetailsRelated Reports
Not Available Description
This dial-a-ride service will operate weekdays in Antioch, Avon, Grant, and Lake Villa townships. A portion of the service will be a flexible route connecting three Metra stations on the NCS Line and Milwaukee District - North Line with residential areas to offer greater access to employment opportunities primarily for individuals with limited mobility and other transit dependent populations. The service expanded its boundaries in December 2012 to include Waconda and Fremont Townships. Lake County implemented the service January 11, 2010. Current Activities
The operating service provided 588 trips in April 2022. Funding Amounts by Source
Last Updated 09.16.2022 |
||||||||||||||
+ | River Grove Developer Discussion Panel | Community Planning | Development Dialogue | River Grove | $3,000 |
|
Completed | |||||||
Project DetailsDescription
This project assisted the Village with implementation efforts as recommended in their recently adopted TOD plan that was funded through the Community Planning program. A developer panel was conducted with the goal of assisting the Village with several redevelopment sites identified in the plan. Future redevelopment of these sites will capitalize on the proximity to exiting transit facilities as well as help strengthen the vitality of downtown River Grove. Current Activities
The discussion panel was held on November 18, 2015. The final summary report is complete and can be found in the Related Studies section. In 2021, the River Grove Station development was completed and began leasing units. The 40-unit multi-family development is located adjacent to the River Grove Metra station in the area designated as "Site 1" in the River Grove Thatcher Avenue Transit-Oriented Development Plan (2014). This site was the subject of the 2015 Developer Panel. Funding Amounts by Source
Last Updated 01.10.2022 |