PROJECT DETAILS
Description:
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024.
Core Requirement(s) | |
---|---|
Maintain and Improve Safety and Reliability | ✓ |
Achieve Full Accessibility | |
Meet Regulatory Requirements | ✓ |
Improve Equity |
Strategic Goal | |
---|---|
Deliver Value on Investment | |
Build on the Strengths of Our Network | |
Stay Competitive | ✓ |
Funding Amounts by Source:
Source | Previous Funding* | 2023 Funding | 2024-2027 Funding | Total |
---|---|---|---|---|
Federal |
$0 |
$1,680,000 |
$6,000,000 |
$7,680,000 |
State |
$0 |
$0 |
$0 |
$0 |
RTA |
$0 |
$233,378 |
$0 |
$233,378 |
Service Board / Local |
$0 |
$0 |
$0 |
$0 |
Total |
$2,400,693 |
$1,913,378 |
$6,000,000 |
$10,314,071 |
PMO:
Total Project Budget^
Budget Status
Schedule Status
Start Date
Dec 2019End Date
Dec 2023^Total Project Budget is the project budget being tracked by the RTA PMO Group
Current Status
The vendor received the permit to implement TSP system along 58 signalized intersections of Dempster Street from IDOT. Systems integration testing were completed at 47 of the 58 signalized Dempster intersections was completed and railroad crossings field tests/data analysis completed at various locations along Dempster. TSP installation along Dempster St. in Evanston is in process and will continue thru Q2-2023. The vendor completed construction and systems implementation along Grand Ave. in a previous but this quarter acquired IDOT District 1 approval and permitting for EOS deployment along Grand and other corridors. Deployment and initial testing of TSP along Roosevelt Rd. was completed and the vendor is currently demonstrating the information to IDOT Dist. 1. TSP deployment along 147th St. was completed and Pace acquired permits for 95th St. with construction continuing through 2023. Permit acquisition activities continues for Rand, Cermak, and 159th.
Last Updated 06.22.2023